Records from 1984 to 1994. Most recent: inspection, 14 July 1994.
Everything above is free. The detail below — the inspection history, the deficiency record and the documentation record — is Professional, $39 a month. Sign in.
Inspection history · 44
14 July 1994
Administrative
Administrative · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 868098
22 July 1993
Administrative
Administrative · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1153188
27 May 1993
Administrative
Administrative · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 838039
6 May 1993
Administrative
Administrative · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 831191
28 February 1992
Hull Examination
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1258549
21 August 1991
Type not recorded
No type recorded · Marine Safety Detachment Cincinnati · USCG Heartland District (CGD-H) · Activity 511835
4 June 1991
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1227092
28 May 1991
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1240182
20 May 1991
Administrative
Administrative · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1226190
17 May 1991
Re-Inspection
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1225077
5 February 1991
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 500296
1 June 1990
Deficiency Check · Examination of Repairs
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 900162
13 April 1990
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 464067
13 April 1990
Deficiency Check
Physical examination · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 1233367
23 March 1990
COI Inspection
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1221361
29 August 1989
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 471559
27 March 1989
Re-Inspection
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1196741
8 September 1988
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 502473
5 May 1988
Deficiency Check
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1349359
31 March 1988
Type not recorded
No type recorded · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 507910
22 March 1988
COI Inspection
Physical examination · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 1295964
13 November 1987
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 461952
15 October 1987
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1015770
28 May 1987
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 518312
23 February 1987
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1015993
19 February 1987
Hull Examination · Re-Inspection
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1015271
6 November 1986
Examination of Repairs
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1322799
21 August 1986
Deficiency Check
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 986566
19 August 1986
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 440272
7 August 1986
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 510367
14 April 1986
COI Inspection
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 999452
27 February 1986
Deficiency Check
Physical examination · MSO CINCINNATI · Activity 1299989
14 January 1986
Type not recorded
No type recorded · MSO CINCINNATI · Activity 443983
14 January 1986
Deficiency Check
Physical examination · MSO CINCINNATI · Activity 1302642
14 January 1986
Deficiency Check
Physical examination · MSO CINCINNATI · Activity 1303363
9 December 1985
Type not recorded
No type recorded · MSO CINCINNATI · Activity 521695
9 December 1985
Type not recorded
No type recorded · MSO CINCINNATI · Activity 996250
4 October 1985
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 508374
28 March 1985
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1288189
21 March 1985
Type not recorded
No type recorded · MSO CINCINNATI · Activity 981011
21 February 1985
Type not recorded
No type recorded · MSO CINCINNATI · Activity 1280931
6 February 1985
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 523226
5 February 1985
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 975240
19 July 1984
Type not recorded
No type recorded · MSO CINCINNATI · Activity 521576
Construction/Loadline
Issued 17 May 1991
Resolved
PROPERLY REPAIR FRACTURES IN WAY OF RUB BARS PORT AND STBD BOW CORNERS _x001C_ PRIOR TO LOADING CARGO AND NO LATER THAN 17 JUNE 1991.
Condition: Unknown
Due 17 May 1991
Resolved 17 May 1991
Deck/Cargo
Issued 17 May 1991
Resolved
DEMONSTRATE PROPER OPERATION OF NUMBER 1 STBD P/V VALVE PRIOR TO LOADING_x001C_ CARGO AND NO LATER THAN 17JUNE 1991.
Condition: Unknown
Due 17 May 1991
Resolved 17 May 1991
Deck/Cargo
Issued 13 April 1990
Resolved
REPAIR OR REPLACE THE ULLAGE FLAME SCREENS AS NECESSARY TO INSURE A PROPER FIT PRIOR TO THE NEXT TRANSFER OF CARGO, BUT NOT LATER THAN THE COMPLIANCE DATE.
Condition: Unknown
Due 13 April 1990
Resolved 13 April 1990
Deck/Cargo
Issued 23 March 1990
Resolved
PROVIDE PROOF OF HYDROSTATIC TEST OF CARGO PIPING AS REQUIRED BY 33 CFR 156-170 PRIOR TO NEXT TRANSFER OF CARGO.
Condition: Unknown
Due 23 March 1990
Resolved 23 March 1990
Deck/Cargo
Issued 23 March 1990
Resolved
MAKE PERMANENT REPAIRS TO THE ULLAGE FLAME SCREENS PRIOR TO NEXT TRANSFER OF CARGO AS REQUIRED BY 46 CFR 32.20-10.
Condition: Unknown
Due 23 March 1990
Resolved 23 March 1990
Construction/Loadline
Issued 23 March 1990
Resolved
PROPERLY MAKE ALL DRAFT MARKS TO THE LIGHT WATERLINE LEGIBLE AS REQUIRED BY46 CFR 32.05-1.
Condition: Unknown
Due 23 March 1990
Resolved 23 March 1990
Construction/Loadline
Issued 22 March 1988
Resolved
MAKE PERMANENT REPAIRS TO PINHOLES LOCATED IN THE STERN RAKE ON THE PORT SIDE AT THE APPROXIMATELY 9' DRAFT MARK.
Condition: Unknown
Due 22 March 1988
Resolved 22 March 1988
Construction/Loadline
Issued 22 March 1988
Resolved
MAKE PERMANENT REPAIRS TO CRACKED WELDS IN THE #2 & #3 LONGITUDINALS LOCATED ON THE PORT SIDE OF THE AFT RAKE.
Condition: Unknown
Due 22 March 1988
Resolved 22 March 1988
Deck/Cargo
Issued 22 March 1988
Resolved
MAKE PERMANENT REPAIRS TO MISSING LAGGING ON THE STEAM PIPING AT VARIOUS LOCATIONS ON THE VESSEL.
Condition: Unknown
Due 22 March 1988
Resolved 22 March 1988
Deck/Cargo
Issued 22 March 1988
Resolved
PROVE PROPER OPERATION OF THE ENGINE START HYDRAULIC ACCUMULATOR RELIEF VALVE.
Condition: Unknown
Due 22 March 1988
Resolved 22 March 1988
Construction/Loadline
Issued 19 February 1987
Resolved
MAKE PERMANENT REPAIRS TO CRACK IN THE DECK AT THE 3RD KEVEL STBD SIDE.
Condition: Unknown
Due 19 February 1987
Resolved 19 February 1987
Construction/Loadline
Issued 19 February 1987
Resolved
MAKE LEGIBLE ALL DRAFT MARKS
Condition: Unknown
Due 19 February 1987
Resolved 19 February 1987
Construction/Loadline
Issued 19 February 1987
Resolved
PLACE HOME OR HAILING PORT ON STERN
Condition: Unknown
Due 19 February 1987
Resolved 19 February 1987
Construction/Loadline
Issued 19 February 1987
Resolved
MAKE PERMANENT REPAIRS TO VARIOUS WELD FRACTURES IN THE #1,2,3 AND 5 WING VOIDS STBD SIDE.
Condition: Unknown
Due 19 February 1987
Resolved 19 February 1987
Deck/Cargo
Issued 21 August 1986
Resolved
REPLACE PRESSURE VACUUM VALVES WITH U.S. COAST GUARD APPROVED VALVES OR PROVIDE WRITTEN PROOF FROM VALVE MANUFACTURER THAT EXISTING VALVES ARE U.S.COAST GUARD APPROVED PRIOR TO 21SEP86.
Condition: Unknown
Due 21 August 1986
Resolved 21 August 1986
Construction/Loadline
Issued 14 January 1986
Resolved
REPLACE THE DOG THAT IS MISSING ON THE NO.2 PORT WING TANK ACCESS OPENING.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Deck/Cargo
Issued 14 January 1986
Resolved
PROVIDE A FLAME SCREEN FOR THE NO. 2 PORT ULLAGE OPENING. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING THE NEXT VESSEL CARGO OR THE DATE OF COMPLI- ANCE, WHICHEVER OCCURS FIRST.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Deck/Cargo
Issued 14 January 1986
Resolved
REPAIR OR REPLACE THE GASKET ON THE NO. 1 PORT CARGO TANK ULLAGE OPENING. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING THE NEXT VESSEL CARGO OR THE DATE OF COMPLIANCE, WHICHEVER OCCURS FIRST.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Construction/Loadline
Issued 14 January 1986
Resolved
REWELD AND REPAINT VESSEL DRAFT MARKS AS NECESSARY.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Deck/Cargo
Issued 14 January 1986
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Deck/Cargo
Issued 14 January 1986
Resolved
HYDROSTATICALLY TEST THE CARGO PIPING AT 1.5 TIMES THE MAWP OR PROVE THAT AHYDROSTATIC TEST HAS BEEN ACCOMPLISHED WITHIN THE LAST YEAR. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING THE NEXT VESSEL CARGO OR THE DATE OF COM- PLIANCE, WHICHEVER OCCURS FIRST.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Deck/Cargo
Issued 14 January 1986
Resolved
PROVE THE PROPER OPERATION OF THE RELIEF VALVE ON THE CARGO PUMP OR PROVIDESATISFACTORY EVIDENCE THAT IT HAS BEEN TESTED WITHIN THE LAST YEAR. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING THE NEXT VESSEL CARGO OR THE DATE OF COMPLIANCE, WHICHEVER OCCURS FIRST.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Unknown
Issued 14 January 1986
Resolved
PROVIDE A PROPER SIZE VENT ON THE FUEL OIL TANK. THE VENT ON THE TANKS LACKS THE REQUIRED CROSS-SECTIONAL AREA WHEN COMPARED TO THE FILL LINE. THIS ITEM IS TO BE COMPLETED PRIOR TO FILLING THE FUEL TANK OR THE DATE OF COMPLIANCE, WHICHEVER OCCURS FIRST.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Deck/Cargo
Issued 14 January 1986
Resolved
MAKE REPAIRS AS NECESSARY TO THE STEAM COILS IN THE NO. 1 PORT CARGO TANK. THIS ITEM IS TO BE COMPLETED PRIOR TO OPERATING THE SEAM SYSTEM OR THE DATEOF COMPLIANCE, WHICHEVER OCCURS FIRST.
Condition: Unknown
Due 14 January 1986
Resolved 14 January 1986
Unknown
Issued 9 December 1985
Resolved
REPAIR OR REPLACE THE RELIEF VALVE ON THE STEAM LINE.
Condition: Unknown
Due 9 December 1985
Resolved 9 December 1985
Documentation
Issued 9 December 1985
Resolved
PROVIDE OIL TRANSFER PROCEDURES ON BOARD THE VESSEL. THIS ITEM IS TO BE COMPLETED PRIOR TO LOADING THE NEXT VESSEL CARGO OR THE DATE OF COMPLIANCE WHICHEVER OCCURS FIRST.
Condition: Unknown
Due 9 December 1985
Resolved 9 December 1985
Deck/Cargo
Issued 21 March 1985
Resolved
ADEQUATELY SUPPORT THE EXHAUST SYSTEM TO PREVENT EXCESSIVE FLEXING AND VIBRATION IN WAY OF THE FLEXIBLE EXHAUST PIPING. THIS ITEM IS TO CORR- ECTED PRIOR TO OPERATING THE CARGO PUMP ENGINE.
Condition: Unknown
Due 21 March 1985
Resolved 21 March 1985
Deck/Cargo
Issued 21 March 1985
Resolved
GUARD OR INSULATE THE CARGO PUMP ENGINE EXHAUST PIPING IN WAY OF THE FLEXIBLE CONNECTION. THIS ITEM IS TO BE CORRECTED PRIOR TO OPERATING THE CARGO PUMP ENGINE.
Condition: Unknown
Due 21 March 1985
Resolved 21 March 1985
Deck/Cargo
Issued 21 February 1985
Resolved
MAKE NECESSARY REPAIRS TO THE STARTER TO PREVENT ITS LEAKING HYDRAULIC FLUID.
Condition: Unknown
Due 21 February 1985
Resolved 21 February 1985
Deck/Cargo
Issued 21 February 1985
Resolved
GUARD OR INSULATE THE CARGO PUMP ENGINE EXHAUST PIPING IN WAY OF THE FLEX- IBLE CONNECTION.
Condition: Unknown
Due 21 February 1985
Resolved 21 February 1985
Deck/Cargo
Issued 21 February 1985
Resolved
ADEQUATELY SUPPORT THE EXHAUST SYSTEM TO PREVENT EXCESSIVE FLEXING AND VI- BRATION IN WAY OF THE FLEXIBLE EXHAUST PIPING.
Condition: Unknown
Due 21 February 1985
Resolved 21 February 1985
Deck/Cargo
Issued 5 February 1985
Resolved
MAKE PERMANENT REPAIRS TO EMERGENCY REMOTE SHUTDOWN PRIOR TO OPERATION OF DECK MACHINERY BUT NO LATER THAN COMPLIANCE DATE.
Condition: Unknown
Due 5 February 1985
Resolved 5 February 1985