KINGS PT. FERRY is a 1957 passenger barge (inspected). The Coast Guard has recorded 10 inspections since 1998, most recently in October 2005, along with 20 deficiencies.

Records from 1998 to 2005. Most recent: inspection, 26 October 2005.

Built
1957
Last inspected
26 October 2005
Documentation
Not in the documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

466050
Flag
UNITED STATES
—
Maury page id
psix-466050

Inspections, by type

Years with a record 8 calendar years (1998–2005)
The 10 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

This record may be incomplete: the most recent inspection recorded for this vessel was 21 years ago. Maury shows what the Coast Guard recorded, not whether the vessel has been inspected since, is still in service, or what condition it is in. Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Barge class in Maury's sources begin in 1972.

Documentation record

Tonnage as PSIX records it16 - Regulatory (Subpart C or D), Net Ton
16 - Regulatory (Subpart C or D), Gross Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.

Radio station licence

No FCC ship-station licence is recorded against this Official Number in the file of 6 September 2026. That is a fact about the licence file, not about the radio.

Inspection history · 10

26 October 2005 Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2523863
24 March 2005 Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2321950
9 June 2004 Annual Inspection · Hull Examination
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2094701
10 June 2003 Drydock Extension · Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1814784
29 July 2002 Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1653997
5 June 2001 Deficiency Check · COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1370247
12 July 2000 Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1052029
3 November 1999 Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 799737
19 August 1999 Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1361077
10 June 1998 Hull Examination · Initial Certification · Deadweight Survey · Inclining Experiment
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1453412

Deficiency record · 20

Fire Fighting › Portable Dry Chemical Fire Extinguisher
Issued 10 June 2003 Resolved
Service spare portable fire extinguishers. LEGACY COMPONENT DESC: Service
Due 10 July 2003
Resolved 26 June 2003
Fire Fighting › Portable Dry Chemical Fire Extinguisher
Issued 10 June 2003 Resolved
Provide BI fire extinguisher for rescue boat.
Due 10 July 2003
Resolved 26 June 2003
Pollution Prevention/Response › Prevention Equipment
Issued 10 June 2003 Resolved
Clean oily residue under both winch drums. LEGACY COMPONENT DESC: Fixed Containment
Due 10 July 2003
Resolved 26 June 2003
Electrical › Electric Supply System (service)
Issued 10 June 2003 Resolved
Repair battery charger cable. LEGACY COMPONENT DESC: Battery Charger
Due 10 July 2003
Resolved 26 June 2003
Deck/Cargo › Mooring/Anchoring
Issued 10 June 2003 Resolved
Repair winch control box at stern ramp. LEGACY COMPONENT DESC: Winch
Due 10 July 2003
Resolved 26 June 2003
Electrical › Electrical Distribution System (service)
Issued 29 July 2002 Resolved
Prior to using 110v power repair conduit crossing deck of barge. LEGACY COMPONENT DESC: Conduit
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 30 August 2002
Resolved 10 June 2003
Stability
Issued 29 July 2002 Resolved
Repair inclinometer LEGACY COMPONENT DESC: Inclinometer
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 30 August 2002
Resolved 10 June 2003
Engineering › Gasoline Engine (auxiliary)
Issued 29 July 2002 Resolved
Replace gas can cap on outboard fuel tank.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 30 August 2002
Resolved 10 June 2003
Electrical
Issued 5 June 2001 Resolved
Provide fuses or cicurit breaker on lighting system and ramp motors on barge prior to night operations
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Navigation
Issued 5 June 2001 Resolved
Repair/replace stern light on ferry barge, prior to operating at night.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Deck/Cargo
Issued 5 June 2001 Resolved
Provide thimble at rope and at 3' of chain at anchors.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Navigation
Issued 5 June 2001 Resolved
Repair/replace port light on towboat prior to operating at night.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Lifesaving
Issued 5 June 2001 Resolved
Provide a type I or type III PFD for towboat operator.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Electrical
Issued 5 June 2001 Resolved
Provide written instructions to the crew to not operate genset when passengers are on board.
Condition: Unknown
Due 11 July 2001
Resolved 11 July 2001
Deck/Cargo
Issued 12 July 2000 Resolved
Provide 100' of anchor line on anchor.
Condition: Unknown
Due 12 July 2000
Resolved 12 July 2000
Lifesaving
Issued 12 July 2000 Resolved
Provide floatable line on life ring.
Condition: Unknown
Due 28 July 2000
Resolved 28 July 2000
Documentation
Issued 12 July 2000 Resolved
Provide logs of training and drills of crew.
Condition: Unknown
Due 12 July 2000
Resolved 12 July 2000
Fire Fighting
Issued 19 August 1999 Resolved
Service or remove excess fire extinguishers without safety wires on pull pins.
Condition: Unknown
Due 19 August 1999
Resolved 19 August 1999
Fire Fighting
Issued 19 August 1999 Resolved
Provide a fire axe.
Condition: Unknown
Due 19 August 1999
Resolved 19 August 1999
Electrical
Issued 19 August 1999 Resolved
Tape over (insulate) all exposed electrical connections.
Condition: Unknown
Due 19 August 1999
Resolved 19 August 1999

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.