Records from 2001 to 2026. Most recent: inspection, 4 August 2026.
Everything above is free. The detail below — the inspection history, the deficiency record, the tow units, the recorded names, the casualty record and the documentation record — is Professional, $39 a month. Sign in.
Inspection history · 23
4 August 2026
Deficiency Check
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8455091
20 July 2026
Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8442633
16 February 2026
Administrative Inspection
Administrative · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8311183
17 November 2025
In-Service Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8269620
2 July 2025
Deficiency Check · Annual Inspection
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 8173386
5 November 2024
Hull Examination · Internal Structural Exam
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 8029822
17 May 2024
Annual Inspection
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 7910009
1 May 2023
COI Inspection
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 7671911
28 October 2022
Internal Structural Exam · Hull Examination · Administrative Inspection
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 7587676
23 March 2022
Deficiency Check · Annual Inspection
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 7396580
19 May 2021
Annual Inspection
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 7200021
21 October 2020
Internal Structural Exam · Hull Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7082856
21 March 2020
Deficiency Check · Annual Inspection
Physical examination · Sector Long Island Sound · USCG Northeast District (CGD-NE) · Activity 6929486
21 August 2019
Administrative Inspection
Administrative · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6790150
1 August 2019
Deficiency Check · Administrative Inspection · Annual Inspection
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6784478
15 January 2019
Drydock Exam · Hull Examination · Internal Structural Exam
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6610380
9 May 2018
COI Inspection · DAPI Audit
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6408751
8 May 2018
Administrative Inspection
Administrative · Navigation Center · Activity 6409087
12 May 2017
Administrative Inspection
Administrative · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6144656
3 May 2017
Annual Inspection · DAPI Audit
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6137792
23 January 2017
Damage Survey · Hull Examination · Examination of Repairs · Drydock Exam
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6084200
20 January 2017
Type not recorded
No type recorded · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6109127
18 April 2016
DAPI Audit · Annual Inspection
Physical examination · Sector Southeastern New England · USCG Northeast District (CGD-NE) · Activity 5856882
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 4 August 2026
Resolved
At each initial and subsequent inspection for certification of a vessel, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspection of machinery, fuel, and piping systems. MI discovered in wet exhaust system that there was water leaking into the ER from pipe. Conduct repairs to the satisfaction of the attending MI>
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 4 August 2026
Resolution: Receieved photo evidence of repairs. All sat.
04 - Emergency Systems › N/A - No Subsystem › Functionality of Safety Systems
Issued 4 August 2026
Resolved
A bilge pipe piercing the collision bulkhead must be fitted with a screw-down valve located on the forward side of the collision bulkhead and operable from the weather deck, or, if it is readily accessible under service conditions, a screw-down valve without a reach rod may be fitted to the bilge line on the after side of the collision bulkhead. MI discovered that the vessel would not gain suction from forward most space. Conduct repairs to the satisfaction of the attending MI.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 4 August 2026
Resolution: Received photo evidence of repairs, all sat.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 4 August 2026
No resolution recorded
Each vessel certificated to operate on a coastwise route within three miles of land must either:(1) Be provided with life floats of an aggregate capacity that will accommodate at least 100% of the total number of persons permitted on board; or(2) Meet either the standards for collision bulkheads in § 179.310 of this subchapter or § 171.085 in subchapter S of this chapter, and the standards for subdivision in §§ 179.220 and 179.320 of this chapter, or the standards for subdivision and damaged stability in §§ 171.070 through 171.073 and 171.080 in subchapter S of this chapter, as appropriate, and be provided with life floats of an aggregate capacity that will accommodate at least 50% of the total number of persons permitted on board.(3) Have on board a FCC Type Accepted Category 1 406 MHz EPIRB, installed to automatically float free and activate, and be provided with life floats of an aggregate capacity that will accommodate at least 50% of the total number of persons permitted on board. MI discovered that the Life floats where not in good working condition. Make repairs to the satisfaction of the attending MI. Vessel is restricted to Lakes Bays and Sounds and warm water months only.
Action required: 705 - Other - as specified
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 4 August 2026
Resolved
At each initial and subsequent inspection for certification, the owner or managing operator must be prepared to conduct tests and have the vessel ready for inspection of its fire protection equipment. MI discovered that the fire ext was not secured properly. Make repairs to the satisfaction of the attending MI.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 4 August 2026
Resolution: Recieved photo evidence of repairs, all sat.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 20 July 2026
No resolution recorded
At each initial and subsequent inspection for certification of a vessel, the owner or managing operator shall be prepared to conduct tests and have the vessel ready for inspection of machinery, fuel, and piping systems. MI discovered in wet exhaust system that there was water leaking into the ER from pipe. Conduct repairs to the satisfaction of the attending MI>
Action required: 701 - Prior to carriage of passengers/cargo
04 - Emergency Systems › N/A - No Subsystem › Functionality of Safety Systems
Issued 20 July 2026
No resolution recorded
A bilge pipe piercing the collision bulkhead must be fitted with a screw-down valve located on the forward side of the collision bulkhead and operable from the weather deck, or, if it is readily accessible under service conditions, a screw-down valve without a reach rod may be fitted to the bilge line on the after side of the collision bulkhead. MI discovered that the vessel would not gain suction from forward most space. Conduct repairs to the satisfaction of the attending MI.
Action required: 16 - Rectify deficiencies w/in 14 days
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 20 July 2026
No resolution recorded
Each vessel certificated to operate on a coastwise route within three miles of land must either:(1) Be provided with life floats of an aggregate capacity that will accommodate at least 100% of the total number of persons permitted on board; or(2) Meet either the standards for collision bulkheads in § 179.310 of this subchapter or § 171.085 in subchapter S of this chapter, and the standards for subdivision in §§ 179.220 and 179.320 of this chapter, or the standards for subdivision and damaged stability in §§ 171.070 through 171.073 and 171.080 in subchapter S of this chapter, as appropriate, and be provided with life floats of an aggregate capacity that will accommodate at least 50% of the total number of persons permitted on board.(3) Have on board a FCC Type Accepted Category 1 406 MHz EPIRB, installed to automatically float free and activate, and be provided with life floats of an aggregate capacity that will accommodate at least 50% of the total number of persons permitted on board. MI discovered that the Life floats where not in good working condition. Make repairs to the satisfaction of the attending MI.
Action required: 701 - Prior to carriage of passengers/cargo
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 20 July 2026
No resolution recorded
At each initial and subsequent inspection for certification, the owner or managing operator must be prepared to conduct tests and have the vessel ready for inspection of its fire protection equipment. MI discovered that the fire ext was not secured properly. Make repairs to the satisfaction of the attending MI.
Action required: 16 - Rectify deficiencies w/in 14 days
09 - Working and Living Conditions › 092 - Working Conditions › Cleanliness of engine room
Issued 2 July 2025
Resolved
Significant accumulation of oily liquid in the bilge. Remove oily liquid from bilge in Engine Room.
46 CFR 176.830(b)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 August 2025
Resolved 17 July 2025
Resolution: completed
04 - Emergency Systems › N/A - No Subsystem › Functionality of Safety Systems
Issued 2 July 2025
Resolved
The fuel shutoff valve must be manually operable from outside the compartment in which the valve is located. Vessels rod sheared off when shut off was tested. Repair and demonstrate that it works.
46CFR 182.455(b)(4)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 2 July 2025
Resolution: completed
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance and inspections
Issued 2 July 2025
Resolved
Color of the life float must be primarily vivid reddish orange. 4 life floats are in need of maintenance and painting (dull in color and inside material is exposed). Conduct maintenance, and provide pics or schedule visit with MI when complete.
46CFR180.200(a)(2)->160.027(a)->160.010-4(n)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 August 2025
Resolved 14 July 2025
Resolution: maintenance completed
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 23 March 2022
Resolved
Vessel missing Ship's FCC Radiotelephony Safety Certificate. Certificate shall be onboard vessel and provide a copy to USCG. (See 47 CFR 80.401)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 23 April 2022
Resolved 25 March 2022
Resolution: rec'd
02 - Structural Conditions › N/A - No Subsystem › Hull - corrosion
Issued 21 October 2020
Resolved
STBD hull at the waterline just forward of the pilothouse, found several pits on hull plating. Submit repair proposal.
Action required: 705 - Other - as specified
Due 30 October 2020
Resolved 23 October 2020
Resolution: Received picture proof of application of compound over pits. All sat.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 21 March 2020
Resolved
Fixed Bilge Pump system must be capable of pumping all required sapces. Make proper repairs and demonstrate proper operation.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 24 March 2020
Resolution: Verified proper operation of bilge pump via face time.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance and inspections
Issued 28 August 2019
Resolved
A vessel must have one or more Ring Life Buoys as follows. Service Ring Life Buoys grab line, Life line and water light lanyard due to deterioration.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 11 September 2019
Resolved 31 October 2019
Resolution: New line fitted.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 28 August 2019
Resolved
Life Floats required must be serviceable as follows. Provide and install new grab lines , painter lines for week link and water light lanyard.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 11 September 2019
Resolved 31 October 2019
Resolution: New Life Floats were purchased and fitted on the vessel.
10 - Safety of Navigation › N/A - No Subsystem › Navigation bridge visibility
Issued 28 August 2019
Resolved
Glass materials used in windows accessible to passengers must be a material that will not break into dangerous fragments. Service window at operators station due to damage.
Action required: 17 - Rectify deficiencies prior to departure
Due 28 August 2019
Resolved 31 October 2019
Resolution: Glass was renewed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 28 August 2019
Resolved
Prove proper operation of generator provided on board vessel.
Action required: 701 - Prior to carriage of passengers/cargo
Due 28 August 2019
Resolved 31 October 2019
Resolution: In kind generator was replaced, Prime-mover remained.
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 28 August 2019
Resolved
Vessel was not able to get underway due to generator not working and operational test of vessel and drills could not be conducted. Vessel must get underway and conduct drill in the presence of the USCG prior to conducting passengers.
Action required: 17 - Rectify deficiencies prior to departure
Due 28 August 2019
Resolved 31 October 2019
Resolution: Satisfactory drills were conducted.
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 21 August 2019
Resolved
A vessel to which this Subchapter applies may not be operated without having on board a valid U.S. Coast Guard Certificate Of Inspection. To maintain a valid Certificate Of Inspection, You must complete your annual inspection as specified and your Certificate Of Inspection must be endorsed. Your vessel must undergo an annual inspection within the 3 months before or after each anniversary date. Your Annual inspection was due no later than 09 August 2019. Please contact USCG to schedule your Annual COI.
Action required: 701 - Prior to carriage of passengers/cargo
Due 21 August 2019
Resolved 19 March 2020
Resolution: This deficiency was cleared with activity 6784478.
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 21 August 2019
Resolved
A vessel to which this subchapter applies may not be operated without having onboard a valid U.S. Coast Guard Certificate Of Inspection. To maintain a valid COI, you must complete your annual inspection as specified by your COI. Your vessel must undergo an annual inspection within the 3 months before or after each anniversary date. Your annual inspection was due no latter than 09 August 2019.
Action required: 701 - Prior to carriage of passengers/cargo
Due 21 August 2019
Resolved 28 August 2019
Resolution: Conducted Annaul COI.