Records from 1982 to 2018. Most recent: inspection, 6 December 2018.
Inspection history · 24
6 December 2018
Administrative Inspection · MTSA Verification · In-Service Inspection · COI Inspection
Physical examination · Sector San Diego · USCG Southwest District (CGD-SW) · Activity 6592971
17 May 2018
Administrative Inspection · COI Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6438085
2 May 2018
Drydock Exam · Administrative Inspection · Internal Structural Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6404123
29 July 2016
Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 5960769
27 June 2014
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4901888
9 May 2014
Internal Structural Exam · Drydock Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 4853591
23 February 2012
Annual Inspection · Deficiency Check
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 4248945
1 February 2012
Hull Examination · Internal Structural Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 4235974
29 December 2011
Plan Review (Other than "T")
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 4215692
31 July 2011
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 4135321
27 January 2009
Initial Certification · Hull Examination · Construction Oversight · Internal Structural Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3400807
7 April 2008
In-Service Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3179087
6 April 1999
Type not recorded
No type recorded · Station Umpqua River · USCG Northwest District (CGD-NW) · Activity 1512500
5 October 1997
Type not recorded
No type recorded · MSO ANCHORAGE · USCG Arctic District (CGD-A) · Activity 675591
30 June 1997
Type not recorded
No type recorded · MSO ANCHORAGE · USCG Arctic District (CGD-A) · Activity 199128
28 March 1995
Type not recorded
No type recorded · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 199129
28 March 1995
Type not recorded
No type recorded · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 755742
3 January 1992
Type not recorded
No type recorded · USCG Arctic District (dp) · USCG Arctic District (CGD-A) · Activity 675592
22 September 1989
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 896520
5 May 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 990412
4 March 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 978030
1 March 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1289916
8 February 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 973000
2 March 1982
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 969692
Operations/Management › Drills/Instruction › Not Conducted
Issued 29 July 2016
No resolution recorded
Perform emergency drills to the satisfaction of a CG MI.
Action required: 17 - Rectify deficiencies prior to departure
Lifesaving › Inflatable Liferafts › Capacity
Issued 29 July 2016
No resolution recorded
46 CFR 199.261(d)(1) - vessel ha 1-20 man raft on each side. Rafts do not seem to be easily tranferable therefore the vessel would not have the correct quantity.
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Engineering › Steering Gear System › Rudder Angle Indicator
Issued 29 July 2016
Resolved
46 CFR 25-10(b)(2) - steering gear must be able to move rudder 35 degrees to 35 degrees. Vessels RAI's only indicate 28 degrees STBD to 22 degrees PORT. Correct steering range of motion.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 August 2016
Resolution: Repaired RAI to read correct rudder angle. A full range of motion has been correctly achieved.
Engineering › Steering Gear System › Rudder Angle Indicator
Issued 29 July 2016
No resolution recorded
Provide rudder angle indicator at the AFT pilot house steering station
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Lifesaving › Rescue Boat Equipment › Searchlight
Issued 29 July 2016
No resolution recorded
46 CFR 199.175(b)(28) Provide serach light for the rescue boat
Action required: 17 - Rectify deficiencies prior to departure
Construction/Loadline › Markings › Vessel Name/Home Port
Issued 29 July 2016
No resolution recorded
46 CFR 67.123 - Provide vessel name and hailing port on stern of vessel.
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 29 July 2016
No resolution recorded
Provide operational nave lights. Both stern, 1 mast head and the STBD nav light are inoperable.
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Communications › Internal Communications System › Sound-powered Telephone
Issued 29 July 2016
No resolution recorded
46 CFR 113.30-3 - Provide additional audible - visual alarm for sound powered phone in E/R.
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Communications › Internal Communications System › Sound-powered Telephone
Issued 29 July 2016
No resolution recorded
46 CFR 113.30-3 - provide a relaiable means of voice communications. The SPP is very weak and voices do not transmit well.
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Engineering › Fuel Oil Service System › Suction Strainer
Issued 29 July 2016
No resolution recorded
Provide metallic bowls for engine fuel strainers
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Engineering › Fuel Oil Service System › Hose
Issued 29 July 2016
No resolution recorded
Provide new fuel hose for STBD main engine
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Engineering › Compressed Air System (start air) › Valve
Issued 29 July 2016
No resolution recorded
provide gauges for pressure vessels with a range of 1.2 to 2 relief valve
Action required: 705 - Other - as specified
Due 30 August 2016 — due date passed with no resolution recorded
Construction/Loadline › Hull › Hull Plating
Issued 9 May 2014
No resolution recorded
Vessel is due for 30 year gauging to ascertain hull condition. ABS will be completing a full gauging report by 31MAR15 for LL renewal. In order to minimize duplications of CG and ABS requirements the vessel is allowed to continue to operate until 31MAR15. Vessel is required to submit the ABS gauging report to the CG for approval and review prior to resuming work after 31MAR15.
Condition: Invalid
Action required: 705 - Other - as specified
Due 31 March 2015 — due date passed with no resolution recorded
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 23 February 2012
Resolved
Lifebuoy float lights all had the incorrect batteries installed. Batteries were of the spring terminal and the vsl needs screw post.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 15 March 2012
Resolution: Vessel installed the proper batteries.
Lifesaving › Lifebuoys › Markings (ship name/port)
Issued 23 February 2012
Resolved
Vsls lifebuoys need new retro tape.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 15 March 2012
Resolution: Vessel installed new retro tape on life buoys.
Electrical › Lighting (emergency) › Battery Operated Lantern
Issued 23 February 2012
Resolved
Found various e-lighting throughout the vsl not working and found two e-lights disassembled.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 15 March 2012
Resolution: Vessel installed new emergency lighting and put together existing lighting that was previously dismantled.
Engineering › Fuel Oil Service System › Hose
Issued 23 February 2012
Resolved
Found f/o piping and hoses throughout the engine room chaffing. Instructed vsl rep to install chaffing gear around piping and hoses.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 15 March 2012
Resolution: Vessel installed chaffing gear on hoses throughout the engine room.
Electrical › Electrical Distribution System (service) › Panelboard
Issued 23 February 2012
Resolved
Power distribution panels were improperly labeled or missing labels.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 15 March 2012
Resolution: Breakers were properly labeled for what they pertained to.
Lifesaving › Lifejacket/PFD (Type I) › Retroreflective Material
Issued 23 February 2012
Resolved
Retro on lifejackets was wasted. Instructed vsl rep to renew lifejackets or replace retro.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 15 March 2012
Resolution: New retro was installed on all lifejackets that were previously call out.
Communications › Alarms/Indicators › Lube Oil Low Pressure Alarm
Issued 23 February 2012
Resolved
Lube oil pressure gauge for the stbd engine on the bridge was not working.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 15 March 2012
Resolution: A new l/o pressure gauge was installed.
Operations/Management › Drills/Instruction › Making Voice Radio Distress Call
Issued 23 February 2012
Resolved
Emergency broadcast placard was not posted or on board.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 15 March 2012
Resolution: Vessel had a new emergency broadcast placard on the bridge.
Operations/Management › Drug and Alcohol Testing › Testing, Equipment
Issued 23 February 2012
Resolved
Alcohol test strips were not on board.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 15 March 2012
Resolution: Vessel had new alcohol test strips on board.
Construction/Loadline › Markings › Load Line Mark
Issued 23 February 2012
Resolved
Load line certificate had not been signed in the last two years.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 28 February 2012
Resolution: Received email from the vessel rep with attachment showing the completion of the Load Line survey signed by ABS.
Operations/Management › Lifesaving › Op Readiness/Maintenance/Inspection
Issued 23 February 2012
Resolved
Vsl had no lifesaving maintenance log.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 15 March 2012
Resolution: Vessel had just started a new life saving maintenance log.
Operations/Management › Pollution › Compliance with Transfer Procedures
Issued 23 February 2012
Resolved
Vsl had no f/o transfer procedures on board.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 15 March 2012
Resolution: Vessel had new f/o transfer procedures on board.
Documentation › Logs/Records › Record Book of Engine Parameters
Issued 23 February 2012
Resolved
Vessel did not have a automation servicing report.
Condition: Improper/Lack of Maintenance
Due 1 March 2012
Resolved 26 February 2012
Resolution: Received email from vessel rep with attachment showing the completion of the automation service report.
Personnel › Certificates/Documents/Licenses › STCW Endorsement
Issued 3 May 2010
Resolved
Provide Licensed Master on board w/STCW Vessel Security Officer (VSO) endorsement. Vessel limited to coastwise route until Master on board has STCW VSO endorsement.
Action required: 705 - Other - as specified
Resolved 18 March 2011
Resolution: Master had STCW and VSO endorsement
Deck/Cargo › Mooring/Anchoring › Winch
Issued 3 May 2010
Resolved
Provide proper maintenance and demonstrate proper operation of Anchor Winch
Due 2 June 2010
Resolved 20 May 2010
Resolution: Extra anchor which was on the malfunctioning winch has been removed from vessel. Remaining winch and anchor functioning properly.
Communications › Alarms/Indicators › Lube Oil Low Pressure Alarm
Issued 3 May 2010
Resolved
Demonstrate proper operation of port engine oil pressure gauge
Due 2 June 2010
Resolved 18 March 2011
Resolution: Gauge working properly
Communications › Alarms/Indicators › Lube Oil Low Pressure Alarm
Issued 3 May 2010
Resolved
Demonstrate proper operation of both reduction gear p.s.i. gauges.
Due 2 June 2010
Resolved 19 May 2010
Resolution: Reduction gear gauges working properly
Communications › Alarms/Indicators › Engine RPM Gauge/Indicator
Issued 3 May 2010
Resolved
Demonstrate proper operation of port engine rpm gauge
Due 2 June 2010
Resolved 13 May 2010
Resolution: New gauge installed and working properly.
Electrical › Electrical Distribution System (service) › Junction Box
Issued 3 May 2010
Resolved
Provide proper electric box for A.C. unit in accordance w/ 46CFR 111.01-9(b)
Due 2 June 2010
Resolved 2 June 2010
Resolution: Junction box installed properly
Fire Fighting › Fixed Fire Detection System › Control Panel
Issued 3 May 2010
Resolved
Submit drawing and demonstrate proper operation of Fire Detection System Control Panel
Due 2 June 2010
Resolved 19 May 2010
Resolution: New Fire Detection System control panel installed and operating properly.
Documentation › Logs/Records › Logbook (official)
Issued 3 May 2010
Resolved
Provide lifesaving maintenance record
Action required: 705 - Other - as specified
Resolved 18 March 2011
Resolution: Lifesaving maintenance record on board
Fire Fighting › Nozzles › Condition
Issued 3 May 2010
Resolved
Provide new fire nozzle.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 4 May 2010
Resolution: Verified new fire nozzle on board.
Fire Fighting › Fire Hydrants › Condition
Issued 3 May 2010
Resolved
Demonstrate proper maintenance of all fire stations.
Action required: 705 - Other - as specified
Resolved 18 March 2011
Resolution: All fire stations equipped and maintained properly. Fire pump ran and all stations operating sat.
Personnel › Certificates/Documents/Licenses › STCW Endorsement
Issued 3 May 2010
Resolved
Provide deck personnel w/ STCW Endorsement for Navigation. Vessel limited to coastwise route until deck personnel on board has STCW Navigation endorsement.
Action required: 705 - Other - as specified
Resolved 18 March 2011
Resolution: Deck personnel had proper STCW endorsement for navigation
Fire Fighting › Portable Foam Applicators › General
Issued 3 May 2010
Resolved
Provide proper firefighting equipment for carriage of MPT
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 4 May 2010
Resolution: Verified proper firefighting equipment on board for carriage of MPT
Lifesaving › Lifebuoys › Quantity
Issued 3 May 2010
Resolved
Provide proper number of lifebuoys in accordance w/46 CFR 133.70
Due 2 June 2010
Resolved 2 June 2010
Resolution: Lifebuoys on board