Records from 1984 to 2009. Most recent: inspection, 18 March 2009.
Inspection history · 58
18 March 2009
Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3435762
21 November 2008
Permit to Proceed
Administrative · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 3367451
1 August 2008
Administrative Inspection · Examination of Repairs
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 3287522
15 February 2008
Damage Survey · Examination of Repairs
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 3148195
27 October 2007
Annual Inspection
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 3154063
28 December 2006
Annual Inspection · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2847303
14 February 2006
Administrative Inspection
Administrative · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 2584748
25 October 2005
COI Inspection · Deficiency Check
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 2521509
22 September 2005
Type not recorded
No type recorded · Marine Safety Detachment Cincinnati · USCG Heartland District (CGD-H) · Activity 2499333
2 September 2005
Examination of Repairs
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 2524158
6 July 2005
Damage Survey
Physical examination · Marine Safety Detachment Cincinnati · USCG Heartland District (CGD-H) · Activity 2417039
11 February 2005
Damage Survey · Deficiency Check
Physical examination · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 2290963
5 October 2004
Annual Inspection · MTSA Verification
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2212896
24 June 2004
Internal Structural Exam · Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2116424
23 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1984585
12 December 2003
Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1963445
5 September 2002
Examination of Repairs · Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1671027
14 August 2002
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1661782
6 November 2001
Re-Inspection
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1379623
4 April 2001
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1062415
15 March 2001
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 727463
5 March 2001
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 42320
5 March 2001
Damage Survey
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1060803
4 December 2000
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1397529
31 July 2000
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1052717
2 July 2000
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 83665
2 July 2000
Damage Survey
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 819966
29 December 1999
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1401151
24 February 1999
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 803752
24 January 1999
Damage Survey
Physical examination · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 788543
23 January 1999
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 81452
18 December 1998
COI Inspection · Examination of Repairs · Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1472667
6 August 1997
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 782728
12 July 1996
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1090715
30 January 1996
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 886159
30 November 1995
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 506557
8 March 1995
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1390000
9 October 1994
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 497664
16 June 1994
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1332519
19 April 1993
COI Inspection · Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1431209
3 February 1993
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1473167
11 December 1991
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 952721
5 August 1991
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 511666
20 June 1991
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1208359
8 March 1991
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1302916
9 January 1990
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 912454
26 January 1989
Administrative
Administrative · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 895801
18 January 1989
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 895800
21 November 1988
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1205463
4 April 1988
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 471164
6 January 1988
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1316486
30 April 1987
Administrative
Administrative · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1022738
24 April 1987
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1013953
7 April 1987
Re-Inspection
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1020821
25 March 1986
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 999866
6 June 1985
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 487074
15 May 1985
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 980437
7 May 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 972548
Construction/Loadline › Hull › Weld
Issued 25 October 2005
Resolved
Make repairs to externally framed gussets at frames, 8,10 and 11 on starboard side from stern. to be completed next time barge is gas freed
Action required: 705 - Other - as specified
Resolved 28 October 2005
Resolution: Visually inspected welds on gussets. All SAT. Vessel was gas freed for repair work.
Deck/Cargo › Cargo Stowage › General
Issued 25 October 2005
Resolved
Vessel is restricted from carrying benzene hydrocarbons due to lack of closed gauging, no vapor recovery system and no bezene program. Cargo authority needs to be updated.
Action required: 705 - Other - as specified
Due 28 December 2005
Resolved 14 February 2006
Resolution: Received new cargo authority attachment
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 6 July 2005
Resolved
During loading a small (< 1 ft dia) wet product stain was noticed IWO of deck edge and tank top aft on #1 Cargo Tank. Product was transferred to #3 cargo tank and additional product was offloaded to get product level 7" below damage, 39.5" below tank top. Area was cleaned and insp, no visible hole or fracture noted. Temp patch placed over damaged area, perm repairs to be completed.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 7 August 2005
Resolved 10 September 2005
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 11 February 2005
Resolved
There is a 1/2" wastage hole in stbd stern bottom. Barge is prohibited from cargo operations pending gas freeing, drydocking and examination of repairs by an attending marine inspector.
Action required: 705 - Other - as specified
Resolved 25 February 2005
Resolution: Welded and tested.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 24 June 2004
Resolved
Complete annual exam as required by 46 CFR 31.10-17A.
Due 24 June 2004
Resolved 24 June 2004
Deck/Cargo › Holds/Tanks
Issued 15 August 2002
Resolved
Take UT readings on stern deck from cargo tank coaming outward approx. 3ft. LEGACY COMPONENT DESC: Coaming
Condition: Improper/Lack of Maintenance
Due 14 September 2002
Resolved 5 September 2002
Deck/Cargo › Holds/Tanks
Issued 15 August 2002
Resolved
Take UT readings fwd on top cargo tank deck area. LEGACY COMPONENT DESC: Cargo Tank Arrangement/Size
Condition: Improper/Lack of Maintenance
Due 14 September 2002
Resolved 5 September 2002
Deck/Cargo
Issued 5 March 2001
Resolved
Off-load barge at LDC fleet MI 237 LMR, proceed directly to the TT 237 cleaning plant & repair yard. Make permanent repairs to port side raised trunk in way of #2 & #3 cargo tanks to the satisfaction of attending USCG Marine Inspector prior to re-loading cargo.
Condition: Unknown
Due 5 March 2001
Resolved 5 March 2001
Deck/Cargo
Issued 2 July 2000
Resolved
PROCEED DIRECTLY TO DOW HANGING ROCK, MI 333 OHIO RIVER TO DISCHARGE CARGO.MAKE PERMANENT REPAIR TO LEAK IN #1 CARGO TANK IWO STUB-OUT TO STBD DRIP PAN. BARGE IS TO BE CHECKED FOR LEAKS DURING TRANSIT. NOT AUTHORIZED TO RELOAD UNTIL THIS REQUIREMENT IS CLEARED.
Condition: Unknown
Due 2 July 2000
Resolved 2 July 2000
Documentation
Issued 29 December 1999
Resolved
PLACE BENZENE MANAGEMENT PLAN ONBOARD.
Condition: Unknown
Due 30 December 1999
Resolved 30 December 1999
Construction/Loadline
Issued 29 December 1999
Resolved
REPLACE BROKEN HATCH DOGS ON #1 PORT WING VOID AND #2 CARGO TANK.
Condition: Unknown
Due 30 December 1999
Resolved 30 December 1999
Construction/Loadline
Issued 29 December 1999
Resolved
REPAIR/REPLACE BROKEN HATCH HINGE ON #1 PORT WING VOID.
Condition: Unknown
Due 30 December 1999
Resolved 30 December 1999
Construction/Loadline
Issued 29 December 1999
Resolved
INSTALL MISSING PLUG ON WEATHERDECK, #1 PORT WING VOID.
Condition: Unknown
Due 30 December 1999
Resolved 30 December 1999
Deck/Cargo
Issued 29 December 1999
Resolved
REPAINT DRAFT MARKS, VESSEL NAME, AND HAILING PORT.
Condition: Unknown
Due 30 December 1999
Resolved 30 December 1999
Construction/Loadline
Issued 29 December 1999
Resolved
MAKE PERMANENT REPAIRS TO DECK KNUCKLE FRACTURE, # 2 STBD WING VOID.
Condition: Unknown
Due 30 December 1999
Resolved 30 December 1999
Construction/Loadline
Issued 24 January 1999
Resolved
After offloading cargo, make repairs to the port forward timberhead and thestarboard bow caval to the satisfaction of the OCMI.
Condition: Unknown
Due 24 January 1999
Resolved 24 January 1999
Deck/Cargo
Issued 24 January 1999
Resolved
After offloading cargo, make repairs to the port forward cargo tank in way of the external tank framing to the satisfaction of the cognizant OCMI.
Condition: Unknown
Due 24 January 1999
Resolved 24 January 1999
Construction/Loadline
Issued 24 January 1999
Resolved
After cargo is offloaded,drydock barge and make repairs to the rake to the satisfaction of the cognizant OCMI.
Condition: Unknown
Due 24 January 1999
Resolved 24 January 1999
Construction/Loadline
Issued 8 March 1991
Resolved
MAKE PERMANENT REPAIRS TO 8" FRACTURE IN WAY OF THE STERN STARBOARD CORNER WRAPPER._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 8 March 1991
Resolved 8 March 1991
Construction/Loadline
Issued 8 March 1991
Resolved
MAKE PERMANENT REPAIRS TO 6" FRACTURE IN WAY OF THE #2 PORT WING VOID, TWO FEET AFT OF THE #2 PORT WING VOID HATCH COVER._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 8 March 1991
Resolved 8 March 1991
Documentation
Issued 7 April 1987
Resolved
PLACE A VALD CERTIFICATE OF FINANCIAL RESPONSIBILITY ON BOARD THE VESSEL PRIOR TO THE NEXT LOADING OF CARGO.
Condition: Unknown
Due 7 April 1987
Resolved 7 April 1987
Construction/Loadline
Issued 7 April 1987
Resolved
MAINTAIN TEMPORARY REPAIRS TO THE PORT BILGE KNUCKLE IN THE RAKE UNTIL PERMANENT REPAIRS CAN BE MADE BUT PRIOR TO HE NEXT LOADING OF CARGO.
Condition: Unknown
Due 7 April 1987
Resolved 7 April 1987
Deck/Cargo
Issued 7 April 1987
Resolved
PROVIDE PROOF OF CURRENT HYDROSTATIC TEST OF THE CARGO PIPING SYSTEM PRIOR TO THE NEXT LOADING OF CARGO.
Condition: Unknown
Due 7 April 1987
Resolved 7 April 1987