MAURY USCG vessel records Sign in
← All vessels

SEASMOKE

SEASMOKE is a 1967 passenger vessel (inspected). The Coast Guard has recorded 83 inspections since 1985, most recently in June 2026, along with 108 deficiencies and 1 casualty investigation in 2018.

Records from 1985 to 2026. Most recent: inspection, 30 June 2026.

Built
1967
Last inspected
30 June 2026
Documentation
Valid · documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

WDB9317
Flag
UNITED STATES
368425510
Maury page id
psix-47164

Inspections, by type

…with no type recorded8
Years with a record 40 calendar years (1985–2026)
The 83 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 1977.

Documentation record

Registered dimensions (L × B × D)52.3 ft × 22.5 ft × 7.9 ft
Registered tonnagegross 29 / net 28
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderC/S/K CATAMARAN · LOS ANGELES CA, UNITED STATES · built 1967
Hull materialWood
PropulsionAuxiliary Sail
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portWAIKOLOA, HI
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 14 July 2026 · expires 30 June 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it29 - Regulatory (Subpart C or D), Gross Ton
28 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.

Radio station licence

WDQ4437MMSI 368425510 · active · compulsorily equipped · granted 21 June 2025, expires 21 June 2035
WDB9317MMSI 366973740 · expired · compulsorily equipped · granted 1 July 2014, cancelled 30 November 2024
WCD7274MMSI not assigned · expired · voluntarily equipped · granted 3 February 1994, cancelled 4 April 2004
FCC Universal Licensing System ship-station file of 6 September 2026, matched to this hull on its US Official Number. Status and dates are the file’s own. The licensee is not read from the file and is not shown. A lapsed licence’s MMSI is still the number the vessel transmitted under while it was valid.

Inspection history · 83

30 June 2026 Examination of Repairs · Drydock Exam
Physical examination · OP location-Sector Honolulu Prevention Department- Kailua Kona · USCG Oceania District (CGD-O) · Activity 8426405
9 April 2026 Annual Inspection
Physical examination · OP location-Sector Honolulu Prevention Department- Kailua Kona · USCG Oceania District (CGD-O) · Activity 8346048
1 April 2025 Annual Inspection · Deficiency Check
Physical examination · OP location-Sector Honolulu Prevention Department- Kailua Kona · USCG Oceania District (CGD-O) · Activity 8104280
27 June 2024 Examination of Repairs · Drydock Exam
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7944109
18 January 2024 COI Inspection · Deficiency Check · DAPI Audit
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7846778
1 September 2023 Administrative Inspection
Administrative · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7782585
20 April 2023 Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7672313
23 June 2022 Deficiency Check · Drydock Exam
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7486087
23 April 2022 Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7436299
18 February 2021 Deficiency Check · Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7141913
24 June 2020 Internal Structural Exam · In-Service Inspection · Drydock Exam
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7000114
7 April 2020 DAPI Audit · Administrative Inspection · Annual Inspection · Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6936593
24 January 2019 Administrative Inspection · DAPI Audit · COI Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6614594
15 June 2018 Administrative Inspection · Drydock Exam · Internal Structural Exam
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6485082
1 May 2018 Annual Inspection · Administrative Inspection · DAPI Audit · Hull Examination
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6403323
24 February 2018 Type not recorded
No type recorded · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6362945
24 April 2017 Annual Inspection · Administrative Inspection · Hull Examination
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6126657
21 April 2016 Hull Examination · DAPI Audit · Annual Inspection · Administrative Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 5914742
16 September 2015 Type not recorded
No type recorded · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 5743944
28 October 2014 DAPI Audit
Administrative · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 5017955
1 June 2014 Administrative Inspection · Hull Examination
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 4897262
1 December 2011 Administrative Inspection · Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 4199732
20 September 2011 DAPI Audit
Administrative · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 4161867
14 December 2010 Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3897772
1 November 2010 Plan Review "T" Boat
Administrative · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3883493
18 February 2010 DAPI Audit · Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3681434
3 December 2009 Internal Structural Exam · Deficiency Check · Hull Examination
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3644130
4 February 2009 COI Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3412537
4 August 2008 DAPI Audit · Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3288984
3 January 2008 Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3124493
18 October 2007 Deficiency Check · Hull Examination · Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 3082011
20 June 2006 Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 2847336
29 November 2005 Deficiency Check · Hull Examination
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 2617892
24 June 2005 COI Inspection · Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 2550759
8 September 2004 Deficiency Check · Annual Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 2270930
18 May 2004 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 2089106
17 July 2003 Annual Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1850191
25 November 2002 Type not recorded
No type recorded · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1716578
20 August 2002 Annual Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1664078
11 July 2002 Administrative Inspection
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1644790
24 May 2002 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1629293
6 March 2002 Administrative Inspection
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1491907
7 June 2001 Re-Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1362269
27 April 2001 Administrative
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1062706
12 June 2000 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1365862
8 June 2000 COI Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1399399
26 October 1999 Administrative
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1128669
18 August 1999 Administrative
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1113919
17 August 1999 Re-Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1361107
1 December 1998 Administrative
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 806348
17 June 1998 Re-Inspection · MARPOL Annex V Examination · Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1398907
6 November 1997 Type not recorded
No type recorded · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 215170
19 August 1997 Administrative
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1118885
16 July 1997 COI Inspection · MARPOL Annex V Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1458443
18 December 1996 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1421244
13 August 1996 Administrative
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1454359
18 July 1996 Re-Inspection · MARPOL Annex V Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1394583
27 July 1995 Deficiency Check
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1185210
22 June 1995 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1400196
20 April 1995 Drydock Extension
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1358734
18 August 1994 Deficiency Check
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1358505
15 July 1994 COI Inspection · MARPOL Annex V Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1354815
15 October 1993 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1395994
4 August 1993 Re-Inspection · MARPOL Annex V Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1373900
8 October 1992 Deficiency Check
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 932749
4 August 1992 Re-Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1262982
15 April 1992 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 945246
18 July 1991 COI Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 932530
18 July 1991 COI Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 942577
12 September 1990 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1227895
10 July 1990 Re-Inspection · Drydock Extension
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 900964
24 August 1989 Re-Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1042463
6 February 1989 Examination of Repairs · Hull Examination · Damage Survey
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 888032
28 December 1988 Type not recorded
No type recorded · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1343010
20 July 1988 COI Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 893566
3 June 1988 Hull Examination · Deficiency Check
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 887832
9 September 1987 Type not recorded
No type recorded · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1004644
25 August 1987 Re-Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1004153
6 November 1986 Hull Examination
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1325934
19 September 1986 Type not recorded
No type recorded · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1309786
15 July 1986 Re-Inspection
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 988646
29 April 1986 Type not recorded
No type recorded · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1297824
18 July 1985 Initial Certification
Physical examination · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 1291548

Deficiency record · 108

07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 1 April 2025 Resolved
Remote fuel shut-off stations must be marked in clearly legible letters at 1 inch high. Shut-off station on the portside must be marked to satisfaction of USCG Marine Inspector.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 15 April 2025
Resolved 14 April 2025
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 1 April 2025 Resolved
Flexible nonmetallic hose rated at SAE J1527 may be used in lube oil, fuel oil and fluid power systems, subject to the following requirements: For the purpose of flexibility only, flexible hose installed in lengths of not more than (30 inches) and subject to pressures of not more than 5 psig. Marine Inspector discovered SAE J1527 rated fuel line lengths exceeding 30 inches on the port side. Must conduct the following: -Evaluate all flexible fuel lines from the fuel tanks to the main engines. a. All flexible fuel line runs that are longer than 30 inches and more than 5 psig must be SAE J1942. b. All other flexible fuel line runs that are up to 30 inches may be rated at SAE J1527 (A1, A2, B1, B2). -Must make arrangements to meet the requirements or submit a Special Consideration in accordance with 46 CFR 175.550.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 1 May 2025
Resolved 1 May 2025
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 18 January 2024 Resolved
All vessels must have navigational lights that are in compliance with the proper sections of the Nav rules. Vessels port nav light is no longer illuminating. Provide proper operation of the vessel's navigational lights. Vessel is reduced to day light operations
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 February 2024
Resolved 7 February 2024
Resolution: Vessel's port light illuminates and is in serviceable condition.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 18 January 2024 Resolved
Stowage of each life float must be secured with a CG-approved weak link that is proper strength for the capacity of the survival craft. The vessel's weak link no longer has approved label and markings on it. Provide serviceable weak link and prove proper installation.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 February 2024
Resolved 7 February 2024
Resolution: Vessel installed capable weak link in serviceable condition for the life floats onboard.
09 - Working and Living Conditions › 092 - Working Conditions › Anchoring devices
Issued 18 January 2024 Resolved
Vessel aft shrouds are secured to the tangs of a chain plate via SS bolt. Due to the bolts beginning to rust the integrity of the hardware is no longer in satisfactory condition. Provide new stainless steal hardware for the aft shrouds.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 February 2024
Resolved 24 January 2024
Resolution: Vessel provided new SS hardware and proved proper installation for the aft shrouds.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 14 December 2022 Resolved
Each ring life buoy with a floating waterlight must have a lanyard of at least 910 millimeters (3 feet) in length, but not more than 1,830 millimeters (6 feet), securing the waterlight around the body of the ring life buoy. The buoy is missing the waterlight. Restricted to daytime operations only.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 15 December 2022
Resolved 15 December 2022
Resolution: New light installed with correct length of lanyard.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 14 December 2022 Resolved
Each life float must be fitted with a lifeline, pendants, two paddles, a painter, and a light. The light must be a floating waterlight approved under approval series 161.010 or other standard specified by the Commandant. The floating waterlight must be attached around the body of the life float or buoyant apparatus by a 10 mm (3/8 inch) lanyard, resistant to deterioration from ultraviolet light, and at least 5.5 meters (18 feet) in length. The water light is extinguished, and the lanyard is of insufficient length.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 16 December 2022
Resolved 16 December 2022
Resolution: Replaced with working waterlight and required lanyard.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 14 December 2022 Resolved
For a life float - Approved under approval series 160.027 15 person Life float onboard is cracked and not serviceable. Persons permitted reduced to 30 when operating beyond 3nm on a limited coastwise route.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 28 December 2022
Resolved 15 December 2022
Resolution: New 15 person lifefloat onboard.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance and inspections
Issued 14 December 2022 Resolved
Each vessel certificated to operate on a limited coastwise route in warm water must be provided with life floats of an aggregate capacity that will accommodate at least 50% of the total number of persons permitted on board. One life float is condemned and unserviceable, vessel is restricted to operations within three miles from land and must carry a 406MHZ EPIRB, until life float is replaced.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 28 December 2022
Resolved 15 December 2022
Resolution: Operational restriction removed due to required lifefloat capacity.
02 - Structural Conditions › N/A - No Subsystem › Steering gear
Issued 23 April 2022 Resolved
All machinery and equipment must be installed and maintained in such a manner as to afford adequate protection from causing fire, explosion, machinery failure, and personnel injury. Signs of hydraulic fluid leakage observed around the stbd steering ram. Replace or rebuild to prevent hydraulic fluid leakage.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 23 June 2022
Resolved 8 September 2022
Resolution: Hydraulic steering rams rebuilt and working satisfactorily.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 23 April 2022 Resolved
ail rigging and components are to be maintained in accordance with good marine practice. -Observed stbd aft chain plate fracture and rust at top of the eye. -Observed port aft chain plate delamination. -Aft I beam wasted areas on end caps at deck level. -fwd jib screw on toggle(shackle stripped -temp double shackle.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 30 June 2022
Resolved 8 September 2022
Resolution: Stbd aft chain plate replaced. Port aft chain plate area rebuilt and considered satisfactory. -Aft I beam end caps repaired satisfactorily. -fwd jib screw on toggle replaced with proper clevis pin.
02 - Structural Conditions › N/A - No Subsystem › Decks - cracking
Issued 23 April 2022 Resolved
Except as otherwise allowed by this subpart, a vessel must comply with the structural design requirements of one of the standards listed below for the hull material of the vessel. Deck fracture underneath the port aft cleat.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 30 June 2022
Resolved 8 September 2022
Resolution: Deck underneath the port aft cleat removed and replaced in kind with marine plywood with two layers of FRP.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 23 April 2022 Resolved
Placards containing instructions for the donning and use of the life jackets aboard the vessel must be posted in conspicuous places that are regularly accessible and visible to the crew and passengers. Placard missing
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 1 May 2022
Resolved 23 April 2022
Resolution: Life jacket placard onboard and displayed prior to completion of inspection.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 18 February 2021 Resolved
Each life jacket must be marked with Type I retroreflective material approved in 46 CFR 164.018. 30 adult and 1 child size life jackets were not marked with appropriate retroreflective material. Provide appropriate markings to the satisfaction of the attending marine inspector. Passenger count reduced to 25 adult and 4 child until corrected.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 14 September 2021
Resolution: Life jackets were marked with appropriate retroreflective material.
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 18 February 2021 Resolved
The painter connecting the life float to the float-free link shall have a breaking strength of at least 680 kilograms (1,500 pounds), except that if the capacity of the life float or buoyant apparatus is 50 persons or more, the breaking strength must be at least 1,360 kilograms (3,000 pounds). The painter on the vessel is deteriorated and shall be replaced.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 20 September 2021
Resolution: The painter on the vessel was replaced.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 18 February 2021 Resolved
Each ring life buoy on a vessel must be approved in accordance with 160.050 in subchapter Q. Grab line on life ring buoy is wasted. Replace.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 September 2021
Resolution: A new grab line was put on the life ring buoy.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 18 February 2021 Resolved
At least one ring life buoy must be fitted with a lifeline. Lifeline missing. Install IAW 46CFR180.70(c).
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 September 2021
Resolution: One ring life buoy has been fitted with a lifeline.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 18 February 2021 Resolved
A vessel must carry one floating waterlight, unless it is limited to daytime operation. Each ring life buoy with a floating waterlight must have a lanyard of at least 910 millimeters (3 feet) in length, but not more than 1,830 millimeters (6 feet), securing the waterlight around the body of the ring life buoy. Install floating waterlight.
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 September 2021
Resolution: A floating waterlight was installed.
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 18 February 2021 Resolved
Machinery, equipment, materials, and arrangements not covered by standards in this subchapter may be inspected in accordance with standards acceptable to the cognizant OCMI as good marine practice. The nylon locknut that is used to secure the starboard upper shroud is not fully seated as the bolt is too short. Repairs shall be made so that the nylon lock nut is fully seated to prevent it from backing off.
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Resolved 20 September 2021
Resolution: The nylon lock nut was fully seated to prevent it from backing off.
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 18 February 2021 Resolved
Rails should consist of evenly spacing between courses and the spacing between courses shall be not greater than 12 inches. The courses on the port quarter of the vessel are wasted and shall be repaired.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 4 March 2021
Resolved 14 September 2021
Resolution: The courses on the port quarter of the vessel have been replaced.
09 - Working and Living Conditions › 092 - Working Conditions › Protection machines/parts
Issued 18 February 2021 Resolved
Exhaust piping must be properly supported by noncombustible hangers or blocks. The exhaust piping on the port side is not secured.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 14 September 2021
Resolution: The exhaust piping on the port side has been secured.
09 - Working and Living Conditions › 092 - Working Conditions › Protection machines/parts
Issued 18 February 2021 Resolved
Machinery, equipment, materials, and arrangements not covered by standards in this subchapter may be inspected in accordance with standards acceptable to the cognizant OCMI as good marine practice. The hydraulic steering hoses on the port side are secured with wasted rope and shall be properly secured to prevent damage.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 14 September 2021
Resolution: The hydraulic steering hoses on the port side are properly secured.
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 18 February 2021 Resolved
A positive shutoff valve is shall be installed at the hull penetration when an electric bilge pump is installed. The electric bilge pump installed in the port side fuel tank compartment does not have a positive shutoff valve installed. Install positive shutoff valve at hull penetration and ensure that the discharge hose is properly supported.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 20 September 2021
Resolution: A positive shutoff valve was installed at the hull penetration and ensures that the discharge hose is properly supported.
02 - Structural Conditions › N/A - No Subsystem › Beams, frames, floors-op. damage
Issued 18 February 2021 Resolved
Except as otherwise allowed by this subpart, a vessel must comply with the structural design requirements of one of the standards listed below for the hull material of the vessel. The vessel has a cracked horizontal frame stiffener aft of the rudder shaft in the port side engine compartment. Submit repair proposal to be approved by the attending USCG marine inspector.
Condition: Damaged By Earlier Event
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 14 September 2021
Resolution: A temporary repair was made to the cracked horizontal frame stiffener aft of the rudder shaft in the port side engine compartment. Added in a special note is a request for a repair proposal for a permanent repair to be done at next dry dock.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 18 February 2021 Resolved
All engines must have at least two means for stopping the engines under any operating conditions. The stop switch for the starboard engine is inoperable. Repair.
Condition: Damaged By Earlier Event
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 14 September 2021
Resolution: The stop switch for the starboard engine is operable.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 18 February 2021 Resolved
Electrical equipment on a vessel must be installed and maintained to protect passengers, crew, other persons, and the vessel from electrical hazards, including fire, caused by or originating in electrical equipment, and electrical shock. Vessel has a non-marine grade, non-UL rated, inverter installed by the public address system. The inverter is not permanently installed and has an adapter that allows three devices to be plugged into its single outlet. The invertor shall be removed. If an invertor is required it shall be installed to the satisfaction of the attending USCG inspector and shall be of proper type. Additionally, an electrical line drawing is required to be submitted and approved by USCG marine inspector prior to installation.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 20 September 2021
Resolution: The invertor was removed.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 18 February 2021 Resolved
The owner shall be prepared to conduct tests and have the vessel ready for inspection of the following: On a sailing vessel all spars, standing rigging, running rigging, blocks, fittings, and sails. Vessel did not have a preventative maintenance program or a sail rigging plan onboard as required by USCG NVIC 02-16. Both shall be placed on board.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 20 March 2021
Resolved 20 September 2021
Resolution: The vessel has a preventative maintenance program and sail rigging plan onboard.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 7 April 2020 Resolved
Shutoff valves, installed so as to close against the fuel flow, mst be ftted in the fuel supply lines, one at the tank connection and one at the engine end of the fuel line to stop fuel flow when servicing accessories. The shutoff valve at the tank must be manually operable from outside the compartment in which the valve is located, perferably from an accessible position on the weather deck. If the handle to the shutoff valve at the tank is located inside the machinery space, it must be located so that the operator does not have to reach more than 300 milimeters (12 inches) into the machinery space and the valve handle must be shielded from flames by the same material the hull is constructed of, or some noncombustible material. Electric olenoid vlaves must not be used, unless used in addition to the manual valve. The vessel's port side emergency fuel shut is inoperable. Please make permenant repairs to the port side emergency fuel shut.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 7 May 2020
Resolved 22 April 2020
Resolution: Repaired port side emergency fuel shut off.
Sail Rigging › Running Rigging › Topping Lifts/Attachments
Issued 24 April 2017 Resolved
Vessel needs to conduct a third party rigging survey by a recognized rig smith to include all sail rigging components on deck and aloft. A U.S. Coast Guard marine inspector shall be in attendance for this inspection. 46 FR 176.840
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 1 November 2017
Resolution: Vessel completed final inspection survey with Coast Guard inspector and rigsmith. All sail rigging components have been replaced, and a satisfactory sea trial was conducted under sial propulsion.
Documentation › Certificates/Documents › FCC Safety Radiotelephony Certificate
Issued 24 April 2017 Resolved
Vessel needs to have a valid FCC radio safety certificate onboard. 47 CFR 13.
Condition: Invalid
Action required: 705 - Other - as specified
Due 24 May 2017
Resolved 3 May 2017
Resolution: Vessel showed proof of obtaining a valid FCC radio safety certificate onboard.
Documentation › Manuals/Policy Documentation › Emergency Instructions
Issued 24 April 2017 Resolved
Vessel needs to update their emergency instruction list to capture their nature of operations.
Condition: Invalid
Action required: 705 - Other - as specified
Due 24 May 2017
Resolved 3 May 2017
Resolution: Vessel incorporated in-water emergency procedures to the emergency instruction list.
Documentation › Certificates/Documents › Stability Letter
Issued 4 January 2011 Resolved
Submit all information/documentation as requested by MSC email dtd 4JAN2012 in order for a review to be completed for the issuance of a new stability letter to maintain the vsls current person capacity. Failure to submit all required information/documentation to MSC by 4FEB2012 will result in the total number of persons allowed to be reduced from 55 to 47 to be in compliance with the new AAWPP.
Due 4 February 2012
Resolved 4 February 2012
Resolution: Received certification of compliance reducing total number of persons allowed to 47.
Electrical › Electric Supply System (service) › Cable
Issued 3 December 2009 Resolved
Clean up and install supports for all wiring in port forward space. Wiring currently loose and hanging in bilge.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Stability › Watertight Integrity › General
Issued 3 December 2009 Resolved
Make port #2 space forward bulkhead watertight. Owner had run wiring through bulkhead and failed to make watertight.
Action required: 705 - Other - as specified
Due 11 December 2009
Resolved 11 December 2009
Fire Fighting › Structural Fire Protection - General › Structural Bulkhead Construction
Issued 3 December 2009 Resolved
Make engine room spaces vapor tight. Vessel currently has (2) piece bulkheads that leave portions of spaces open to atmosphere potentially rendering fixed fire system ineffective.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Fire Fighting › Combustible Materials › Insulation
Issued 3 December 2009 Resolved
Install insulation on covers to both engine room spaces. Insulation appears to have been removed.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Fire Fighting › Combustible Materials › Paints/Varnishes/Other Finishes
Issued 3 December 2009 Resolved
Remove all combustibles from engine room spaces. Vessel currently has combustibles stored IVO batteries in spaces.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Construction/Loadline › Structures › Manhole
Issued 3 December 2009 Resolved
Remove wet wood from beneath port engine room hatch and repair as original.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Construction/Loadline › Hull › Stringer
Issued 3 December 2009 Resolved
Remove wet wood from lower stringers in port engine room and repair as original.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Construction/Loadline › Structures › Machinery Space Opening
Issued 3 December 2009 Resolved
Remove wet wood and repair as original stanchion support in port #2 space.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Construction/Loadline › Structures › Machinery Space Opening
Issued 3 December 2009 Resolved
Remove wet wood and repair as original area under rudder post in steering flat.
Action required: 705 - Other - as specified
Resolved 11 December 2009
Construction/Loadline › Hull › Side Shell
Issued 3 December 2009 Resolved
Make the following areas available for USCG inspection: (1) port inboard area 3' fwd of transom, 1' above waterline, (2) stbd outboard area approx. 2' above waterline amidships, and (3) port underside of wing deck measuring approx. 12" x 24".
Action required: 705 - Other - as specified
Resolved 11 December 2009
Stability › Severe Wind/Roll › General
Issued 3 December 2009 Resolved
Provide comprehensive rigging survey and detailed description of all components to include sizes, age and replacement schedule.
Due 1 January 2010
Resolved 15 January 2010
Communications › Radio Communications › EPIRB
Issued 4 August 2008 Resolved
Installation of the EPIRB under the overhang of the helm cockpit counter is not satisfactory. Mount EPIRB in float free arrangement so there are no obstructions in accordance with 46 CFR 180.64.
Action required: 705 - Other - as specified
Due 14 August 2008
Resolved 18 August 2008
Pollution Prevention/Response › Prevention Equipment › Bilge Monitor
Issued 4 August 2008 Resolved
Vessel did not have properly operating high level bilge alarms in the forward most compartments on both the port and starboard bow. Vessel did not have high level bilge alarm indicators at or near the helm control station for the port and starboard bow compartments. Install and provide proper operation of high level bilge alarms with a visual and audible indicators for the said compartments.
Condition: Unknown
Action required: 705 - Other - as specified
Due 14 August 2008
Resolved 18 August 2008
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 4 August 2008 Resolved
Found no aspirin tablets and the eye wash solution was expired in the first aid kit. Provide aspirin and eye wash for first aid kit in accordance with 46 CFR 184.710.
Condition: Unknown
Action required: 705 - Other - as specified
Due 14 August 2008
Resolved 18 August 2008
Operations/Management › Drug and Alcohol Testing › MIS Submission
Issued 4 August 2008 Resolved
Provide proof of 2007 MIS submission for DAPI Program.
Condition: Unknown
Action required: 705 - Other - as specified
Due 14 August 2008
Resolved 5 August 2008
Operations/Management › Drug and Alcohol Testing › Employee Coverage
Issued 4 August 2008 Resolved
Provide copies of employee acknowledgment forms for DAPI Program.
Condition: Unknown
Action required: 705 - Other - as specified
Due 14 August 2008
Resolved 5 August 2008
Engineering › Shafting/Propeller Arrangements › Propeller Shaft
Issued 14 November 2007 Resolved
Make props and shafts available for USCG inspection.
Action required: 705 - Other - as specified
Resolved 27 November 2007
Resolution: Examined shafts in machine shop (1 replaced). New props to be installed.
Engineering › Steering Gear System › Rudder
Issued 14 November 2007 Resolved
Repair rudder as original.
Action required: 705 - Other - as specified
Resolved 28 December 2007
Resolution: Rudder repaired
Construction/Loadline › Hull › Stringer
Issued 14 November 2007 Resolved
Renew rotted stringers located in stbd fwd space, port steering space, and stbd steering space.
Action required: 705 - Other - as specified
Resolved 27 November 2007
Resolution: Examined repairs to wood rot - sat.
Construction/Loadline › Structures › Deck Plating
Issued 14 November 2007 Resolved
Renew wood rot in hull (8" in diameter) located aft of stbd steering hatch IWO rudder stock.
Action required: 705 - Other - as specified
Resolved 27 November 2007
Resolution: Examined repair to hull IVO rudder stock.
Stability › Severe Wind/Roll › General
Issued 14 November 2007 Resolved
Provide rigging report/survey.
Action required: 705 - Other - as specified
Resolved 3 January 2008
Stability › Watertight Integrity › Deadlight Cover
Issued 14 November 2007 Resolved
Prove operatioin of all portlights.
Action required: 705 - Other - as specified
Resolved 27 November 2007
Resolution: Tested operation of port lights - sat.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 18 October 2007 Resolved
Restock 1st aid kit; missing numerous items.
Due 14 November 2007
Resolved 14 November 2007
Operations/Management › Equipment Service/Testing › EPIRB
Issued 18 October 2007 Resolved
Renew EPIRB hydrostatic release. Vessel restricted to NMT 3 miles from shore until this items is corrected.
Due 14 November 2007
Resolved 14 November 2007
Navigation › Piloting/Steering › Coast Guard Light List
Issued 18 October 2007 Resolved
Provide current copy of Coast Guard light list for operating area.
Due 14 November 2007
Resolved 14 November 2007
Navigation › Piloting/Steering › US Coast Pilot
Issued 18 October 2007 Resolved
Provide current copy of U.S. Coast Pilot for operating area.
Due 14 November 2007
Resolved 14 November 2007
Operations/Management › Drug and Alcohol Testing › MIS Submission
Issued 24 June 2005 Resolved
Provide copy of 2004 MIS report
Due 24 July 2005
Resolved 1 July 2005
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 24 June 2005 Resolved
Obtain tourniquet and new eye wash for first aid kit.
Due 24 July 2005
Resolved 1 July 2005
Communications › Radio Communications › VHF Radiotelephone
Issued 8 September 2004 Resolved
Obtain valid Safety Radiotelephony Certificate.
Due 8 October 2004
Resolved 24 September 2004
Engineering › Fuel Oil Service System › Tank
Issued 8 September 2004 Resolved
Properly ground fuel tank fill piping port and stbd.
Due 8 October 2004
Resolved 24 September 2004
Engineering › Bilge Water Management System › Pump
Issued 8 September 2004 Resolved
Repair bilge pump to port fwd void.
Due 8 October 2004
Resolved 24 September 2004
Communications › Radio Communications › EPIRB
Issued 8 September 2004 Resolved
Obtain new hydrostatic release and install to EPIRB.
Due 8 October 2004
Resolved 24 September 2004
Engineering
Issued 16 July 1997 Resolved
Install insulation on both main engine exhaust piping up to the point of water injection.
Condition: Unknown
Due 16 July 1997
Resolved 16 July 1997
Engineering
Issued 16 July 1997 Resolved
Double hose clamp all exhaust and bilge system flexible hose connections inthe port and stbd engine rooms, and port and stbd forward compartments.
Condition: Unknown
Due 16 July 1997
Resolved 16 July 1997
Construction/Loadline
Issued 16 July 1997 Resolved
Install strainers on all fixed hand bilge pump suction hoses.
Condition: Unknown
Due 16 July 1997
Resolved 16 July 1997
Construction/Loadline
Issued 16 July 1997 Resolved
In lieu of wooden plug install a metallic cap or shutoff valve on the thru hull fitting in the port engine room, behind the fuel filter.
Condition: Unknown
Due 16 July 1997
Resolved 16 July 1997
Navigation
Issued 16 July 1997 Resolved
Double nut, nylock, or cotter pin the steering gear linkage on the stbd rudder.
Condition: Unknown
Due 16 July 1997
Resolved 16 July 1997
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF ANNUAL INSPECTION LIFE SAVING EQUIPMENT BATTERIES IAW 46 CFR 185.726._x001C_
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Lifesaving
Issued 18 July 1996 Resolved
MAKE UP ALL PENDANTS ON BUOYANT APPARATUS' INTO HANKS TO THE SATISFACTION OF A USCG MARINE INSPECTOR.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Fire Fighting
Issued 18 July 1996 Resolved
PROVIDE JUL96 FIRE SERVICING REORT TO USCG OFFICE.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Construction/Loadline
Issued 18 July 1996 Resolved
ALL BILE HOSE TO BE RESISTANT TO SALTWATER, HEAT, VIBRATION, AND PETROLEUM PRODUCTS TO THE SATISFACTION OF A USCG MARINE INSPECTOR.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Construction/Loadline
Issued 18 July 1996 Resolved
PROVIDE POSITIVE ACTION SHUT OFF VALVES FOR ALL ELECTRIC BILGE PUMPS AT ALLTHRU HULL PENETRATIONS AND DOUBLE HOSE CLAMP DISCHARGE HOSES AT THE PUMP AND THRU HULL FITTINGS TO THE SATISFACTION OF A USCG MARINE INSPECTOR.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF LOGGED QUARTERLY CREW TRAINING AND EMERGENCY DRILLS IAW 46CFR 185.420.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE WATERLIGHTS FOR EACH BUOYANT APARATUS AND 100' PAINTERS ATTACHED TOWEAKLINKS PRIOR TO CARRYING PASSENGERS.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Lifesaving
Issued 18 July 1996 Resolved
REPLACE RING BUOY PRIOR TO CARRYING PASSENGERS.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Construction/Loadline
Issued 18 July 1996 Resolved
INSTALL HIGH LEVEL BILGE ALARMS IN BOTH ENGINE ROOM WITH SEPERATE AUDIBLE ALARM/LIGHTS AT THE PILOT STATION TO THE SATISFACTION OF A USCG MARINE INSPECTOR.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF LOGGED ABANDON SHIP & MAN OVERBOARD DRILL/TRAINING.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF LOGGED FIREFIGHTING DRILL AND TRAINING.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF SURVIVAL CRAFT MFG INSTRUCTIONS AND MAINTENANCE IAW 46 CFR185.702.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Lifesaving
Issued 18 July 1996 Resolved
INSTALL RETROREFLECTIVE TAPE ON RING BUOY IAW 46 CFR 185.604(i).
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Engineering
Issued 18 July 1996 Resolved
ALIGN EMERGENCY FUEL SHUT OFF CABLES SO FUEL VALVES COMPLETELY SHUT OFF TO THE SATISFACTION OF A USCG MARINE INSPECTOR.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Engineering
Issued 18 July 1996 Resolved
REPLACE STBD EMERGENCY FUEL SHUT OFF VALVE HANDLE TO THE SATISFACTION OF A USCG MARINE INSPECTOR.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Construction/Loadline
Issued 18 July 1996 Resolved
REPLACE PORTABLE HAND/FIRE BILGE PUMP WITH TYPE THAT WILL DEWATER LOWEST BILGE ON VSL TO THE SATISFACTION OF A USCG MARINE INSPECTOR.
Condition: Unknown
Due 5 August 1996
Resolved 5 August 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF LOGGED PASSENGER COUNT IAW 46 CFR 185.504.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF LOGGED INSPECTION AND MAINTENANCE OF SURIVIAL CRAFT IAW 46CFR 185.720.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Lifesaving
Issued 18 July 1996 Resolved
PROVIDE PROOF OF MONTHLY INSPECTION OF SURVIVAL CRAFT IAW 46 CFR 185.722.
Condition: Unknown
Due 18 July 1996
Resolved 18 July 1996
Electrical
Issued 22 June 1995 Resolved
Provide overcurrent protection for generators and starters.
Condition: Unknown
Due 22 June 1995
Resolved 22 June 1995
Electrical
Issued 22 June 1995 Resolved
In accordance with 46 CFR 183.05-50(d)(2) provide bonding system.
Condition: Unknown
Due 22 June 1995
Resolved 22 June 1995
Engineering
Issued 15 July 1994 Resolved
PROPERLY BOND FUEL TANK FILL PIPES TO FUEL TANKS FOR BOTH PORT AND STARBOARD FUEL TANKS.
Condition: Unknown
Due 15 July 1994
Resolved 15 July 1994
Construction/Loadline
Issued 15 July 1994 Resolved
PROPERLY CONNECT THE FORWARD STARBOARD HAND FIXED BILGE OVERBOARD DISCHARGELINE TO THE THROUGH-HULL FITTING.
Condition: Unknown
Due 15 July 1994
Resolved 15 July 1994
Engineering
Issued 15 July 1994 Resolved
RENEW THE PORT AND STARBOARD FUEL SHUT OFF CABLES.
Condition: Unknown
Due 15 July 1994
Resolved 15 July 1994
Lifesaving
Issued 15 July 1994 Resolved
RENEW WATERLIGHTS FOR THE RING BUOY AND THE BUOYANT APPARATUS. VESSEL RESTRICTED TO DAYLIGHT OPERATIONS ONLY UNTIL COMPLETED.
Condition: Unknown
Due 15 July 1994
Resolved 15 July 1994
Engineering
Issued 15 July 1994 Resolved
PROVIDE PROPER VENTILATION TO BOTH PORT AND STARBOARD FUEL TANK SPACES.
Condition: Unknown
Due 15 July 1994
Resolved 15 July 1994
Engineering
Issued 15 July 1994 Resolved
PROVIDE PROPER VENTILATION TO BOTH PORT AND STARBOARD ENGINE SPACES.
Condition: Unknown
Due 15 July 1994
Resolved 15 July 1994
Engineering
Issued 4 August 1992 Resolved
PROVIDE ADEQUATE VENTILATION TO PORT AND STARBOARD FUEL TANK SPACE.
Condition: Unknown
Due 4 August 1992
Resolved 4 August 1992
Lifesaving
Issued 4 August 1992 Resolved
PROPERLY LABEL PFD STOWAGE WITH TYPE AND QUANTITY.
Condition: Unknown
Due 4 August 1992
Resolved 4 August 1992
Engineering
Issued 4 August 1992 Resolved
PROVIDE ADEQUATE VENTILATION TO PORT AND STARBOARD DIESEL MACHINERY _x001C_ SPACE.
Condition: Unknown
Due 4 August 1992
Resolved 4 August 1992
Engineering
Issued 4 August 1992 Resolved
PROPERLY LABEL REMOTE FUEL SHUT-OFFS.
Condition: Unknown
Due 4 August 1992
Resolved 4 August 1992
Engineering
Issued 4 August 1992 Resolved
RENEW FLAME SCREENS, 30X30 MESH, ON FUEL TANK VENTS.
Condition: Unknown
Due 4 August 1992
Resolved 4 August 1992
Lifesaving
Issued 4 August 1992 Resolved
STENCIL BUOYANT APPARATUS WITH PASSENGER CAPACITY.
Condition: Unknown
Due 4 August 1992
Resolved 4 August 1992
Lifesaving
Issued 10 July 1990 Resolved
PLACE ONBOARD FLOAT FREE LINK RATED FOR 18 PERSON BUOYANT APPARATUS.
Condition: Unknown
Due 10 July 1990
Resolved 10 July 1990
Engineering
Issued 10 July 1990 Resolved
LABEL FUEL OIL CUTOUT VALVE.
Condition: Unknown
Due 10 July 1990
Resolved 10 July 1990
Lifesaving
Issued 10 July 1990 Resolved
PROVIDE ONBOARD 2 ADDITIONAL ADULT LIFE PRESERVERS OF APPROVED TYPE. TOTAL NUMBER OF PERSONS ALLOWED ONBOARD IS LIMITED TO 46 UNTIL THIS ITEM ISCOMPLETED
Condition: Unknown
Due 10 July 1990
Resolved 10 July 1990
Engineering
Issued 10 July 1990 Resolved
INSTALL METAL BOWL SHIELDS ON STBD RACOR FUEL SEPERATOR.
Condition: Unknown
Due 10 July 1990
Resolved 10 July 1990
Construction/Loadline
Issued 20 July 1988 Resolved
REPLACE ALL PLASTIC THROUGH HULL FITTINGS WITH METAL THROUGH HULL FITTINGS.
Condition: Unknown
Due 20 July 1988
Resolved 20 July 1988
Documentation
Issued 25 August 1987 Resolved
PROVIDE CURRENT RADIO TELEPHONY CERTIFICATE, FCC FORM 824.
Condition: Unknown
Due 25 August 1987
Resolved 25 August 1987

Casualty record · 1

24 February 2018Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 6362945
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it, and the bridge, lock or dam the investigation names where it names one. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.

Ownership record