MAURY USCG vessel records
← All vessels

SUPER QUEEN

SUPER QUEEN is a 1972 passenger vessel (inspected). The Coast Guard has recorded 21 inspections since 2016, most recently in May 2026, along with 56 deficiencies, 1 operational control and 7 casualty investigations between 2008 and 2022.

Records from 2008 to 2026. Most recent: inspection, 13 May 2026.

Built
1972
Last inspected
13 May 2026
Documentation
Valid · documentation file of 10 August 2026
Controls
None recorded without a removal date

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 2016.

Inspection record

Last inspected 13 May 2026
…with no type recorded2
Operational controls None recorded without a removal date
Years with a record 11 calendar years (2016–2026)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Identity

WAO9076
Flag
UNITED STATES
Maury page id
psix-47232

Documentation record

Registered dimensions (L × B × D)75.1 ft × 32.0 ft × 9.4 ft
Registered tonnagegross 99 / net 67
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderMONARK CUSTOM CRAFT INC · JEANERETTE, LA, UNITED STATES · built 1972
Hull materialAluminum
PropulsionDiesel Reduction
Hull shapeUNSPECIFIED
Hull configurationUNSPECIFIED
Hailing portCLEARWATER, FL
Trade endorsementsCoastwise, unrestricted, Fishery
DocumentationValid · issued 21 February 2026 · expires 31 March 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it99 - Regulatory (Subpart C or D), Gross Ton
67 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Vessel history report
Every record for this hull, in one document — $299

Every recorded inspection, 2016 to 2026 for this class, in one chronology · every deficiency, with system, dates and resolution · operational controls imposed and removed · every name this hull has been recorded under · the vessels it was inspected alongside, and when · how its record compares with hulls of similar age and size, as a fact about the population and never a judgement about this vessel.

Read one first, in full: a forty-year chronology · a hull that changed operators four times · the sparse case, shown as an example, not for sale.

This report is in development and is not for sale yet. There is no date, and nothing is charged. Leave an email and we will tell you when it exists, once.

Inspection history · 21

13 May 2026 Deficiency Check · Annual Inspection · Administrative Inspection · Vessel Attendance
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8357982
16 September 2025 Internal Structural Exam · Drydock Exam · Administrative Inspection · Examination of Repairs
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8235638
25 February 2025 Annual Inspection · Administrative Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 8073830
23 February 2024 Deficiency Check · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7861297
19 October 2023 Examination of Repairs · Hull Examination · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7806217
10 July 2023 Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7738622
31 May 2023 In-Service Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7694972
21 February 2023 Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7633160
21 December 2022 Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7613512
25 April 2022 COI Inspection · DAPI Audit · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7422180
25 October 2021 Internal Structural Exam · Hull Examination · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7326389
9 April 2021 Administrative Inspection · Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7171921
21 July 2020 Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6991834
31 October 2019 Examination of Repairs · Drydock Exam · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6808501
23 July 2019 Deficiency Check · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6725983
15 May 2018 Administrative Inspection · Examination of Repairs · Annual Inspection · Deficiency Check
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6394636
13 November 2017 Examination of Repairs · Damage Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6310078
10 November 2017 Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6305985
2 November 2017 Welding Related Inspections Qualification Testing · Examination of Repairs · Drydock Exam · Deficiency Check · Internal Structural Exam
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6299541
20 April 2017 COI Inspection · Deficiency Check · Administrative Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6100238
26 July 2016 Deficiency Check · DAPI Audit · Annual Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 5953506

Deficiency record · 56

09 - Working and Living Conditions › 092 - Working Conditions › Ventilation (Working spaces)
Issued 13 May 2026 Resolved
The construction and arrangement of a vessel must allow the safe operation of the vessel in accordance with the terms of its Certificate of Inspection giving consideration to provisions for a seaworthy hull, protection against fire, means of escape in case of a sudden unexpected casualty, guards and rails in hazardous places, ventilation of enclosed spaces, and necessary facilities for passengers and crew. During inspection of port engine room with engines running and underway, inspector’s 4 gas meter alerted for high levels of H2S and CO. Determine cause and affect repairs so an operational test of port engine room can be completed. 46CFR177.100
Action required: 60 - Rectify deficiencies prior to movement
Resolved 14 May 2026
Resolution: Port engine exhaust lagging rewrapped. Satisfactory space atmospheric testing was completed via 4-gas analyzer showing repair of exhaust leak.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 13 May 2026 Resolved
A vessel of more than 19.8 meters (65 feet) in length must carry a minimum of three life buoys. One life buoy was in deteriorated, unserviceable conditions and must be replaced. 46CFR180.70
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 May 2026
Resolved 1 June 2026
Resolution: Received photo of new ring buoy.
02 - Structural Conditions › N/A - No Subsystem › Closing devices/watertight doors
Issued 13 May 2026 Resolved
Each vessel must meet the applicable requirements in Subchapter S of this chapter. Each hatch exposed to the weather must be watertight. FWD starboard hatch cover gasket was not watertight and must be replaced. 46 CFR 177.13-1 OLD T; 46 CFR 171.124 (a)
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 May 2026
Resolved 9 June 2026
Resolution: Received photo of satisfactory gasket replacement.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 13 May 2026 Resolved
A portable or temporary electric cord or cable must be constructed and used in compliance with the requirements of § 111.60-13 in subchapter J of this chapter for a flexible electric cord or cable. No flexible cord may be used except:(1) As allowed under Sections 400.10 and 400.12 of NFPA 70. Uses Not Permitted (400.12) Unless specifically permitted in 400.10, flexible cables, flexible cord sets, and power supply cords shall not be used for the following: As a substitute for the fixed wiring of a structure...Where run through doorways, windows, or similar openings. Freezer on aft deck must be permanently wired or removed. 46 CFR 183.340(r) 46 CFR 111.60-13(b)(1) NFPA 70 Section 400.12
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 May 2026
Resolved 9 June 2026
Resolution: Freezer removed from vessel.
01 - Certificates & Documentation › 012 - Crew Certificates › Certificates for master and officers
Issued 13 May 2026 Resolved
The Coast Guard will issue a medical certificate to a mariner meeting the medical and physical standards for merchant mariners. Master must provide valid medical certificate. 46CFR10.301
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 May 2026
Resolved 1 June 2026
Resolution: Received valid medical certificate.
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 25 February 2025 Resolved
Each buoyant apparatus on the vessel before March 11, 1996 may be used as long as its in good and serviceable condition. It was deemed that the one of the 4 buoyant apparatus has reached the end of its serviceable life and shall be replaced with a life float meeting 46CFR160.027. 46 CFR 180.15
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 March 2025
Resolved 16 May 2025
Resolution: Raft was removed and passenger count was reduced on the COI.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 25 February 2025 Resolved
The vessel must have on board a number of child size life jackets equal to at least 10% (16) of the number of persons permitted. The vessel only had on board 15 of the 16 required child life jackets. Vessel operations are limited to 15 persons under 90lbs until the additional child life jacket is on board and labeled. 46 CFR 180.71
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 March 2025
Resolved 10 March 2025
Resolution: Child size Life Jacket was procured and placed on board.
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 25 February 2025 Resolved
Each life float and buoyant apparatus shall be fitted with lifelines and pendants. The life lines and pendants on the buoyant apparatus' are deteriorated and dry rotting. Replace with new dark colored synthetic line. 46 CFR 180.175
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 March 2025
Resolved 10 March 2025
Resolution: Line was replaced.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 23 February 2024 Resolved
In the design of a control, interlock, or indicator circuit, the disconnect device and its connections, including each terminal block for terminating the vessel's wiring, must not have any electrically unshielded or uninsulated surfaces. MI Observed an open section in the distribution panel. 46 CFR 183.330
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 March 2024
Resolved 14 March 2024
Resolution: Vessel sent photographic proof of the distribution panel.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 23 February 2024 Resolved
Electrical equipment on a vessel must be installed and maintained to: Protect passengers, crew, other persons, and the vessel from electrical hazards, including fire, caused by or originating in electrical equipment, and electrical shock. MI Observed multiple dead in wires in the engine machinery space. 46 CFR 183.200
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 March 2024
Resolved 14 March 2024
Resolution: Vessel Representative sent photographic proof of capped wires.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 23 February 2024 Resolved
Each lighting fixture globe, lens, or diffuser must have a guard or be made of high strength material. MI observed the globe in the emergency light in the engine room to not be a high strength material. 46 CFR 183.410
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 March 2024
Resolved 14 March 2024
Resolution: Vessel Representative sent photographic proof of the new globe.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 31 May 2023 Resolved
At each initial and subsequent inspection for certification, reinspection and at every other vessel inspection the marine inspector shall require that all observed unsafe practices and hazardous situations be corrected. MI observed port emergency fuel shut off valve was leaking fuel into the bilge. 46 CFR 176.25-50
Action required: 10 - Deficiency Rectified
Due 31 May 2023
Resolved 31 May 2023
Resolution: Vessel representatives tighten down valve and no fuel leaks were observed.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 31 May 2023 Resolved
At each initial and subsequent inspection for certification, reinspection and at every other vessel inspection the marine inspector shall require that all observed unsafe practices and hazardous situations be corrected. MI observed starboard emergency fuel shut off valve was leaking fuel into the bilge. 46 CFR 176.25-50
Action required: 10 - Deficiency Rectified
Due 31 May 2023
Resolved 31 May 2023
Resolution: Vessel representatives were able to tighten down valve and no fuel leaks were observed.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 21 February 2023 Resolved
A dual voltage generator installed on a vessel shall be of the grounded type, where the neutral of a dual voltage system must be solidly connected at the switchboard's neutral bus. The neutral bus shall be connected to ground. If a grounded distribution system is provided, there must be only one connection to ground, regardless of the number of power sources. This ground connection must be at the switchboard or at the common ground plate, which must be accessible. The neutral for the dual voltage generator is not connected to the ground at the switchboard. The dual voltage generator is not grounded presenting an electrocution hazard to all persons onboard. 46 CFR 183.376 and 46 CFR 183.10-30
Action required: 17 - Rectify deficiencies prior to departure
Due 21 February 2023
Resolved 24 February 2023
Resolution: The operator connected the generator neutral to ground at the switchboard.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 21 February 2023 Resolved
Receptacle outlets and attachment plugs for portable lamps, tools, and similar apparatus operating at 100 volts or more, must have a grounding pole and a grounding conductor IAW 46 CFR 183.370. The generator ground is not installed in the distribution panel and the distribution panel does not have a ground bus bar or grounding conductors to each electrical outlet/device powered by AC current throughout the entire vessel which presents an electrocution hazard to all persons onboard. 46 CFR 183.10-20 and 46 CFR 183.370
Action required: 17 - Rectify deficiencies prior to departure
Due 21 February 2023
Resolved 24 February 2023
Resolution: The operator proved continuity between all AC outlet grounding poles and the vessel's hull using a multi meter.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 21 February 2023 Resolved
The neutral of a dual voltage system must be accessible for checking the insulation resistance of the generator to ground before the generator is connected to the bus. Ground detection must be provided that: For an alternating current system, meets § 111.05-27 in subchapter J of this chapter. Ground fault detection is not installed at the switchboard. 46 CFR 183.10-30 and 46 CFR 183.324
Action required: 50 - Rectify deficiencies w/in 30 days
Due 21 March 2023
Resolved 2 May 2023
Resolution: Ground fault detection plans were approved by MSC and installation was verified by a USCG marine inspector.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 21 February 2023 Resolved
Except as provided otherwise in this subpart, all electrical equipment including motors, generators, controllers, distribution panels, etc., shall be drip proof protected. Drip proof protected means that equipment and machinery is so constructed or protected that its successful operation is not interfered with when subjected to falling moisture or dirt, and rotating or uninsulated parts cannot be inadvertently touched or approached nearer than a safe distance by any person. Switchboards shall be fitted with drip hoods and hand rails. Non-conducting mats or grating shall be provided on deck in front and rear of switchboards. The 240V switchboard was found without an enclosure or drip shield. The equipment is open in the back, bottom, sides and top and all live conductors can be touched by the crew. 46 CFR 183.10-10 and 46 CFR 183.330
Action required: 50 - Rectify deficiencies w/in 30 days
Due 21 March 2023
Resolved 24 February 2023
Resolution: The operator installed a metallic drip shield above the switchboard and enclosed the sides of the switchboard using aluminum.
09 - Working and Living Conditions › 092 - Working Conditions › Protection machinery
Issued 21 February 2023 Resolved
All wiring and cables shall be suitable for marine service and for the particular installation used. All wiring shall be installed as high as possible above the bilge. Welding cable found installed between battery installations in the port/stbd hull. Welding cable is connected to each battery system between the cross deck of the catamaran hull. Welding cable does not have an adequate thermal plastic to protect the conductor from heat due to resistance and presents a fire hazard. Replace with Marine Grade electrical conductors rated for the current carrying capacity of the electrical load. The starboard generator starting conductor and negative conductor were found installed in the bilge. 46 CFR 183.10-20 and 46 CFR 183.340
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 March 2023
Resolved 24 February 2023
Resolution: The welding cable was replaced using 2AWG marine grade electrical conductors and the generator starting conductor was re-installed out of the engine room bilge.
07 - Fire Safety › N/A - No Subsystem › Fire pumps and its pipes
Issued 21 February 2023 Resolved
Except as further modified in this section, where fire extinguishing systems or equipment are not required, but are installed, the system or equipment and its installation shall meet the requirements of this Part. The vessel is outfitted with two fire pumps on each engine in each separate hull. The starboard fire pump belt drive was found cracked and damaged making the unit inoperable. The port fire pump operated as intended. 46 CFR 181.05-5
Action required: 50 - Rectify deficiencies w/in 30 days
Due 21 March 2023
Resolved 24 February 2023
Resolution: The operator replaced the engine drive belt for the starboard fire pump.
07 - Fire Safety › N/A - No Subsystem › Fire-dampers
Issued 21 February 2023 Resolved
Except where all or a part of the emergency instructions are deemed unnecessary by the Officer in Charge of Marine Inspection the emergency checkoff list shall contain not less than the applicable portions of the Recommended Emergency Checkoff List §185.25-5. Fire at sea. (1) Cut off air supply to fire-close hatches, ports, doors, and ventilators, etc. The engine room fire damper closures are constructed of fiberglass for this aluminum vessel. The port damper closing hatch was found damaged and does not cover the damper. Fire damper construction should match the construction material of the vessel. 46 CFR 185.25-1
Action required: 705 - Other - as specified
Due 28 February 2023
Resolved 24 February 2023
Resolution: The operator installed two new fire damper closures to the engine room which are constructed of aluminum.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 21 February 2023 Resolved
An adult life jacket must be provided for each person carried on board a vessel. 18 adult life jackets were found damaged and destroyed by the crew. Passenger count reduced to 135 plus 3 crew. 46 CFR 180.71
Action required: 50 - Rectify deficiencies w/in 30 days
Due 21 March 2023
Resolved 10 July 2023
Resolution: Vessel representative sent photos of 18 new life jackets for the vessel.
11 - Life Saving Appliances › N/A - No Subsystem › Operational readiness of lifesaving appliances
Issued 25 April 2022 Resolved
EPIRB installation must be a float free arrangement. The Hydrostatic release is expired 46 CFR 180.64
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 May 2022
Resolved 26 April 2022
Resolution: Vessel installed a new hydrostatic release.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 25 April 2022 Resolved
Portable fire extinguishers must be maintained and inspected in accordance with NFPA 10. Vessel did not have a record of monthly checks on their extinguishers. 46 CFR 176.810(b)(1)
Action required: 10 - Deficiency Rectified
Due 25 April 2022
Resolved 25 April 2022
Resolution: Educated the vessel master on the need to keep a monthly log.
04 - Emergency Systems › N/A - No Subsystem › Muster list
Issued 11 May 2021 Resolved
The master and crew of a vessel will be familiar with the content of and have mounted at the operating station, emergency instructions containing the actions to be taken in the event of fire, heavy weather, or many overboard conditions. Vessel did not have emergency instructions written or posted on board. 46 CFR 185.510 (a)
Action required: 705 - Other - as specified
Due 18 May 2021
Resolved 17 May 2021
Resolution: Emergency instructions were posted in pilothouse.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 11 May 2021 Resolved
Portable fire extinguishers must be located so that they are clearly visible and readily accessible from the space being protected. 02 portable extinguishers, meant to protect accommodation space on main deck, were found to be stored in closet with no brackets to secure from movement. 46 CFR 181.520
Action required: 705 - Other - as specified
Due 18 May 2021
Resolved 17 May 2021
Resolution: 02 portable extinguishers were mounted in clearly visible and easily accessible locations on main deck.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 11 May 2021 Resolved
The pump outlet must be fitted with a pressure gauge. Fire pump pressure gauge was stuck at 40psi. MI verified that pressure and discharge did increase despite gauge remaining at 40 psi. 46 CFR 181.300 (b)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 June 2021
Resolved 11 June 2021
Resolution: Vessel representative provided picture of operable gauge.
11 - Life Saving Appliances › N/A - No Subsystem › Inflatable liferafts
Issued 11 May 2021 Resolved
Each buoyant apparatus on the vessel on March 11, 1996, may be used to meet the requirements of this part for these survival craft as long as the survival craft is continued in use on the vessel, and is in good and serviceable condition. 01 buoyant apparatus found to have resin failure. Passenger count reduced to 120 until chosen to repair or replace. 46 CFR 180.15 (b)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 June 2021
Resolved 13 July 2021
Resolution: New BA purchased and placed onboard.
04 - Emergency Systems › N/A - No Subsystem › Man Overboard Drill (MOB)
Issued 11 May 2021 Resolved
At each initial and subsequent inspection for certification, the marine inspector may require that an abandon ship or man overboard drill be held under simulated emergency conditions specified by the inspector. While conducting man overboard drill, the crew experienced difficulty communicating and identifying respective responsibilities to retrieve the man in the water. At one point, no crew member had eyes on the man in the water. The master could not see and was not receiving directions from the crew. 46 CFR 176.808 (g)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 June 2021
Resolved 13 July 2021
Resolution: Completed drills to satisfaction of OCMI.
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 11 May 2021 Resolved
A vessel must carry either a first-aid kit approved under approval series 160.041 or a kit with equivalent contents and instructions. Kit had expired ammonia inhalants, aspirin, and eye wash. 46 CFR 184.710
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 June 2021
Resolved 11 June 2021
Resolution: Vessel representative provided picture of renewed ammonia inhalants, eye wash, and aspirin.
01 - Certificates & Documentation › 013 - Documents › Signs, indications
Issued 11 May 2021 Resolved
On a vessel on which the number of passengers permitted on upper decks is limited by stability criteria, as indicated by the vessel’s stability letter, the maximum number of passengers allowed on an upper deck must be indicated by a durable marking of at least 2 mm (1 inch) numbers and letters at the entranceway to that deck. Maximum passengers allowed on upper deck was not found at the entranceway to that deck. 46 CFR 185.602 (g)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 June 2021
Resolved 11 June 2021
Resolution: Vessel representative provided picture of the new location of upper deck passenger count sign.
14 - Pollution Prevention › 145 - MARPOL Annex V › Garbage management plan
Issued 11 May 2021 Resolved
A vessel must comply with the applicable design, equipment, personnel, procedures, and record requirements of 33 CFR parts 151, 155, and 156. Vessel printed out Garbage Management Plan while MI was on board. Plan meets requirements in accordance with 33 CFR 151.57. 46 CFR 184.702
Action required: 10 - Deficiency Rectified
Resolved 11 May 2021
Resolution: Vessel printed and posted Garbage Management Plan.
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 11 May 2021 Resolved
Each door, hatch, or scuttle, used as a means of escape, must be capable of being opened by one person, from either side. Hatches identified as emergency escapes routes were over-tightened and unable to be opened by one person from inside the space. Crew members loosened handles to allow persons inside the space to be able to open. 46 CFR 177.500 (h)
Action required: 10 - Deficiency Rectified
Resolved 11 May 2021
Resolution: Crew members loosened handles to allow persons inside the space to be able to open.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 11 May 2021 Resolved
Protection must be approved in compliance with 177.970 of this chapter at such locations where persons or equipment might come in contact with an exhaust pipe. MI found small portion of dry exhaust pipe exposed. Crew member repaired insulation to prevent future injuries. 46 CFR 182.430 (a)
Action required: 10 - Deficiency Rectified
Resolved 11 May 2021
Resolution: Crew member repaired insulation to prevent future injuries.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 11 May 2021 Resolved
Each life jacket must be marked with Type I retroreflective material approved in 46 CFR 164.018. MI found 03 adult life jackets and 02 child life jackets with deteriorated retroreflective material. Crew members replaced retroreflective material on the life jackets identified. 46 CFR 185.604
Action required: 10 - Deficiency Rectified
Resolved 11 May 2021
Resolution: Crew members replaced retroreflective material on the life jackets identified.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 23 July 2019 Resolved
Safety Radiotelephony Certificate expired. Provide a valid Safety Radiotelephony Certificate. 46 CFR 184.502
Action required: 16 - Rectify deficiencies w/in 14 days
Due 6 August 2019
Resolved 1 August 2019
Resolution: Owner provided a valid Safety Radiotelephony Certificate.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 23 July 2019 Resolved
Replace plastic piping arrangement with metallic shut off valve at hull penetration in both engine rooms. 46 CFR 182.520
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 6 August 2019
Resolved 24 July 2019
Resolution: Replaced both plastic valves with metallic shut off valves at hull penetrations.
Engineering › Bilge Water Management System › Valve
Issued 15 May 2018 Resolved
Replace wasted bilge / fire cross over valve port side as original. Provide proposal for use of non-metallic piping in bilge system or replace flex hose metallic piping as original. 46 CFR 182.710
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 May 2018
Resolved 26 May 2018
Resolution: Operator replaced wasted pipe and valve with metallic piping and new valve.
Construction/Loadline › Structures › Superstructure
Issued 15 May 2018 Resolved
Replace cracked glass window port side main deck using safety glazing materials IAW 46 CFR 177.1020
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 May 2018
Resolved 26 May 2018
Resolution: Operator installed new window meeting requirements.
Electrical › Electrical Distribution System (service) › Distribution Panel Bus
Issued 15 May 2018 Resolved
Electrical equipment on a vessel must installed and maintained to minimize accidental personnel contact with energized parts. Replace missing breakers in pilot house panel. 46 CFR 183.200(e)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 May 2018
Resolved 26 May 2018
Resolution: Operator installed protection covering exposed areas in breaker panel.
Construction/Loadline › Hull › Hull Plating
Issued 13 November 2017 Resolved
Repair pinhole prior to carrying passengers IAW 46 CFR 176.610.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 20 November 2017
Resolution: Tested insert. All sat.
Construction/Loadline › Hull › Weld
Issued 6 November 2017 Resolved
Found cracked weld at fore peak tunel area, grind down and re-weld to the satisfaction of the attending marine inspector. 46CFR177.300(d)
Action required: 705 - Other - as specified
Due 20 November 2017
Resolved 9 November 2017
Resolution: Inspected satisfactory weld.
Lifesaving › Lifejacket/PFD (General) › Condition
Issued 25 April 2017 Resolved
Found 24 adult lifejackets in not serviceable condition, replace with 24 adult lifejackets in good serviceable condition to the satisfaction of attending marine inspector. Persons count reduce to 124.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 1 May 2017
Resolved 27 April 2017
Resolution: 24 adult lifejackets in good serviceable condition properly marked provided to the satisfaction of the attending Marine Inspector, deficiency cleared.
Navigation › Collision/Grounding Avoidance › Radar
Issued 25 April 2017 Resolved
Radar dome found cracked at support bracket, repair to the satisfaction of attending marine inspector.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 1 May 2017
Resolved 27 April 2017
Resolution: Radar dome cracked at support bracket properly repair to the satisfaction of attending marine inspector, deficiency cleared.
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 25 April 2017 Resolved
Found nav lights not in compliance with UL1104, replace with appropriate type to the satisfaction of the attending marine inspector. Restricted to day time only.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 1 May 2017
Resolved 2 May 2017
Resolution: Replaced new nav lights in compliance with UL1104, to the satisfaction of the attending marine inspector.
Construction/Loadline › Structures › Door
Issued 25 April 2017 Resolved
Found starboard side engine watertight door with a broken handle, repair to the satisfaction of attending marine inspector.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 1 May 2017
Resolved 27 April 2017
Resolution: Watertight door properly repair to the satisfaction of attending marine inspector, deficiency cleared.
Engineering › Diesel Engine (propulsion-direct drive) › Exhaust Manifold
Issued 25 April 2017 Resolved
Main dry exhaust systems found with broken lagging, repair or replace to satisfaction of marine inspector. 46 cfr 176.25-10
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 1 May 2017
Resolved 27 April 2017
Resolution: Main dry exhaust systems lagging properly repair to the satisfaction of attending marine inspector, deficiency cleared.
Engineering › Bilge Water Management System › Not Operational
Issued 25 April 2017 Resolved
Bilge pump manifold system not functioning on stbd side at engine room and aft stern. make repairs as needed and prove proper operation.
Action required: 705 - Other - as specified
Due 1 May 2017
Resolved 27 April 2017
Resolution: Bilge pump manifold system operational, properly repair to the satisfaction of attending marine inspector, deficiency cleared.
Lifesaving › Lifejacket/PFD (Type I) › Quantity
Issued 26 July 2016 Resolved
Vessel is restricted to carry 14 children until 2 more PFDs are provided iaw 46 CFR 180.71(b).
Due 9 August 2016
Resolved 11 August 2016
Resolution: 02 Child PFD's obtained and proven in good condition.
Documentation › Certificates/Documents › FCC Vessel Bridge-to-Bridge Radiotelephony Cert.
Issued 26 July 2016 Resolved
FCC Bridge to Bridge certificate is not onboard and not valid for vessel iaw 47 CFR 80.1101.
Due 9 August 2016
Resolved 11 August 2016
Resolution: FCC Bridge to Bridge Certificate obtained. Restriction of 1000 ft from shore cleared.
Fire Fighting › Fire Main › Condition
Issued 26 July 2016 Resolved
Fire main piping has 2 pinhole leaks in each side and must be repaired or replaced prior to operation iaw 46 CFR 81.314.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 27 July 2016
Resolution: Pipes were replaced and firepump was run to test operability. All sat.
Fire Fighting › Fire Pumps › Pressure
Issued 26 July 2016 Resolved
Main Fire Pump not operating iaw 46 CFR 181.300.
Due 26 July 2016
Resolved 26 July 2016
Resolution: Corrected on spot.
Fire Fighting › Remote Fuel Shutoff › General
Issued 26 July 2016 Resolved
Emergency fuel shutoff valve tested with fuel leaking at valve stem iaw 46 CFR 182.455(b)(4).
Due 26 July 2016
Resolved 26 July 2016
Resolution: Corrected on spot.
Accommodation/Occupational Safety › Heating › Piping
Issued 26 July 2016 Resolved
Stbd engine exhaust pipe needs to be replaced iaw 46 CFR 182.425.
Due 9 August 2016
Resolved 11 August 2016
Resolution: STBD Engine Exhaust pipe replaced
Stability › Watertight Integrity › General
Issued 26 July 2016 Resolved
Stuffing tubes on port and stbd side need to be replaced iaw 46 CFR 182.40-1.
Due 9 August 2016
Resolved 11 August 2016
Resolution: Stuffing tubes on port and stbd side replaced.
Electrical › Lighting (service) › Conductor
Issued 26 July 2016 Resolved
Loose wiring needs to be addressed in port engine room iaw 46 CFR 176.806.
Due 9 August 2016
Resolved 11 August 2016
Resolution: Loose wiring addressed and placed in bracket.
Electrical › Electric Supply System (service) › Battery Conductor
Issued 26 July 2016 Resolved
Loose connections on port battery 46 CFR 176.806(f).
Due 9 August 2016
Resolved 11 August 2016
Resolution: Tightened connections on port battery.

Casualty record · 7

14 March 2008Routine · role: Involved in a Marine Casualty · activity 3195887
13 November 2008Routine · role: Involved in a Marine Casualty · activity 3362907
25 March 2012Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 4274365
21 March 2013Routine · role: Involved in a Marine Casualty · serious marine incident, as classified · 1 injured · activity 4553958
2 April 2013Routine · role: Involved in a Marine Casualty · 1 injured · activity 4562596
10 November 2017Routine · role: Involved in a Marine Casualty · activity 6305985
21 December 2022Routine · role: Involved in a Marine Casualty · 1 injured · activity 7613512
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.