ANNAPOLITAN II

ANNAPOLITAN II is a 1972 passenger vessel (inspected). The Coast Guard has recorded 20 inspections since 2016, most recently in April 2026, along with 19 deficiencies and 1 casualty investigation in 2008.

Records from 2008 to 2026. Most recent: inspection, 10 April 2026.

Built
1972
Last inspected
10 April 2026
Documentation
Valid · documentation file of 10 August 2026
Controls
None recorded without a removal date

Everything above is free. The detail below — the inspection history, the deficiency record, the casualty record and the documentation record — is Professional, $39 a month. Sign in.

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 2016.

Inspection record

Last inspected 10 April 2026
Operational controls None recorded without a removal date
Years with a record 11 calendar years (2016–2026)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Identity

WYZ8643
Flag
UNITED STATES
Maury page id
psix-47340

Documentation record

Registered dimensions (L × B × D)65.0 ft × 22.0 ft × 5.8 ft
Registered tonnagegross 85 / net 58
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderLANTANA BOATYARD INC · LANTANA, FL, UNITED STATES · built 1972
Hull materialAluminum
PropulsionDiesel Reduction
Hull shapeUNSPECIFIED
Hull configurationUNSPECIFIED
Hailing portANNAPOLIS, MD
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 4 March 2026 · expires 31 March 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it58 - Regulatory (Subpart C or D), Net Ton
85 - Regulatory (Subpart C or D), Gross Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Professional
Detail on this page

20 inspections, each with its date, unit and type; 19 deficiencies with the resolution recorded against each; 1 casualty investigation, with date and classification; the documentation record: dimensions, tonnage, builder, hailing port, endorsements, dates. The counts in the summary above are the same counts, and they are free.

$39 a month or $299 a year, every vessel page, cancel any time. Founding rate $19.99 a month for life, for the first 200 subscribers. Plans Sign in

Maury does not score, rate or grade vessels, at any price.

Vessel history report
Every record for this hull, in one document — $299

Every recorded inspection, 2016 to 2026 for this class, in one chronology · every deficiency, with system, dates and resolution · operational controls imposed and removed · every name this hull has been recorded under · the vessels it was inspected alongside, and when · how its record compares with hulls of similar age and size, as a fact about the population and never a judgement about this vessel.

Read one first, in full: a forty-year chronology · a hull that changed operators four times · the sparse case, shown as an example, not for sale.

This report is in development and is not for sale yet. There is no date, and nothing is charged. Leave an email and we will tell you when it exists, once.

Inspection history · 20

10 April 2026 Deficiency Check
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8345861
17 March 2026 Annual Inspection · Deficiency Check
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8327842
18 April 2025 Deficiency Check
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8113761
1 April 2025 Deficiency Check · Administrative Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8104026
18 March 2025 Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8096846
7 November 2024 Internal Structural Exam · Drydock Exam
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 8036499
5 March 2024 Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7874780
30 May 2023 Deficiency Check · In-Service Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7688988
14 March 2023 Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7652086
1 March 2022 Administrative Inspection · COI Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7390911
12 November 2021 Internal Structural Exam · Drydock Exam
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7353209
9 March 2021 Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 7153084
5 March 2020 Annual Inspection · Administrative Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6921357
12 March 2019 Annual Inspection · DAPI Audit
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6643042
30 October 2018 Internal Structural Exam · Drydock Exam
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6578119
8 August 2018 Administrative Inspection
Administrative · Navigation Center · Activity 6504651
13 March 2018 DAPI Audit · Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6375667
11 April 2017 Damage Survey
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6127187
8 February 2017 DAPI Audit · COI Inspection · Administrative Inspection · Deficiency Check
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 6085148
17 May 2016 DAPI Audit · Annual Inspection
Physical examination · Sector Maryland-National Capital Region · USCG East District (CGD-E) · Activity 5879421

Deficiency record · 19

11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 17 March 2026 Resolved
11127 - Each life float must be secured to the vessel by a painter and float-free link. The life floats are secured to a piece of PVC, not the vessel. 46 CFR 180.20-1 "Old T"
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 26 March 2026
Resolution: Received photographic evidence the float free link is attached to the vessel.
09 - Working and Living Conditions › 091 - Living Conditions › Lighting (Accommodation)
Issued 17 March 2026 Resolved
09108 - Each vessel must have adequate emergency lighting fitted along the line of escape to the main deck from all passenger and crew accommodation spaces located below the main deck. The emergency light above the starboard engine was inoperable. 46 CFR 183.432(a)
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 10 April 2026
Resolution: Received photographic evidence the engine compartment lights were fixed.
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 18 March 2025 Resolved
For a life float—Approved under approval series 160.027 or other standard specified by the Commandant. Buoyant apparatus may be used to meet requirements for life floats if the buoyant apparatus was installed on board the vessel on or before March 11, 1996, and if the buoyant apparatus remains in good and serviceable condition. 46CFR180.200(a)(2)
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Resolved 1 April 2025
Resolution: Life float was replaced.
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 7 November 2024 Resolved
Repairs or alterations to the hull, machinery, or equipment that affect the safety of the vessel must not be made without the approval of the cognizant OCMI, except during an emergency. Repairs or alterations that affect the safety of the vessel include, but are not limited to: replacement, repair, or refastening of deck or hull planking, plating, and structural members; repair of plate or frame cracks. Damage to hull was identified on the port side stern area of the vessel. 46 CFR 176.700
Action required: 60 - Rectify deficiencies prior to movement
Resolved 10 March 2025
Resolution: Visually inspected and cleared the area that was damaged/delaminated on the port side area on the stern.
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 5 March 2024 Resolved
11127 - The color of the life float must be primarily vivid reddish orange. The bottom life float needs to be painted. 46 CFR 180.200(a)(2) 46 CFR 160.027-2 46 CFR 160.010(n)
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 11 March 2024
Resolution: Received photographic evidence the life float was painted.
11 - Life Saving Appliances › N/A - No Subsystem › Buoyant apparatus
Issued 5 March 2024 Resolved
11127 - Each life float must have Type II retro-reflective material meeting subpart 164.018 of this chapter on each side and end. The retro-reflective tape on the top life float needs to be replaced. 46 CFR 180.200(a)(2) 46 CFR 160.027-2 46 CFR 160.010(p)
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 11 March 2024
Resolution: Received photographic evidence the retro was replaced.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 5 March 2024 Resolved
09209 - Electrical equipment on a vessel must be installed and maintained to provide services necessary for safety under normal and emergency conditions. The PA system was plugged into a power strip. 46 CFR 183.200(a)
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 11 March 2024
Resolution: Received photographic evidence a new outlet was installed.
07 - Fire Safety › N/A - No Subsystem › Fire pumps and its pipes
Issued 30 May 2023 Resolved
Vital systems: Mechanically propelled "S" vessels which are ferry vessels or which carry more than 49 passengers and mechanically propelled "L" vessels shall comply with the provisions of Subchapter F of this chapter. The subject vessel is a "S" vessel (65 feet or less in length), certificated to carry 103 passengers. Therefore, piping for vital systems must meet the provisions of Subchapter F. There is evidence of a temporary repair via a JB-weld type material on the fire main system near the u-bend of the pipe in the engine room overhead. The fire main is a vital system as per 46 CFR 56.07-5 (f)(1)(ii). Provide a repair proposal to the OCMI for permanent repairs. The repair proposal should also address how the lengths of flexible hose in the fire main exceeding 30 inches in length either meet the applicable regulations in 46 CFR 56.60-25, or will also be replaced. *Due at next scheduled dry dock (31 October 2024).
Action required: 701 - Prior to carriage of passengers/cargo
Due 31 October 2024
Resolved 26 March 2026
Resolution: Received photographic evidence the piping was fixed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 14 March 2023 Resolved
The individual bilge suction lines shall be led to a central control point or manifold. Each line shall be provided with a stop valve at the control point. One of the valve handles for the bilge manifold is partially broken off. 46 CFR 182.25-5 (c) in “old T”
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 28 March 2023
Resolved 20 June 2023
Resolution: Vessel rep provided email with photos of newly replaced bilge handle.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 14 March 2023 Resolved
each life jacket must be approved in accordance with either § 160.002, § 160.005, or § 160.055 in subchapter Q of this chapter, or other standard specified by the Commandant, including, but not limited to, approval series 160.155 or 160.176. (04) life jackets were inoperable.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 May 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 14 March 2023 Resolved
Through hull fittings and shutoff valves shall be metal. Through hull fitting / shutoff valve for bilge overboard piping has a flex hose between the shutoff valve and the hull. 46 CFR 182.40 (a)(3) in “old T”
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 28 March 2023
Resolved 20 June 2023
Resolution: Vessel rep provided evidence that overboard valve in question is located >6 inches above the deepest loaded waterline, so under "old S", 46 CFR 171.119, a shutoff valve is not technically required.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 14 March 2023 Resolved
Piping used in a vital system must: (1) Be composed of ferrous materials except when: (i) Nonmetallic piping materials are permitted by § 182.720; or (ii) Nonferrous metallic piping materials are permitted by § 182.730; and (2) If subject to a pressure of more than 1,034 kPa (150 psig), be designed, fabricated, and inspected in accordance with the principles of ANSI B 31.1. There is a leak on the connection line/hose between the bilge and fire main piping.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 May 2023
Resolution: Confirmed that there is no leak on the connection line/hose between the bilge and the fire main.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 5 March 2020 Resolved
At each initial and subsequent inspection for certification, the owner or managing operator must be prepared to conduct tests and have the vessel ready for inspection of its fire protection equipment, including each portable fire extinguisher to check for excessive corrosion and general condition. Aft cabin fire extinguisher was found to be under-pressurized.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 10 March 2020
Resolved 10 March 2020
Resolution: Replaced
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 5 March 2020 Resolved
All fittings on fire hose shall be of brass, copper, or other suitable corrosion-resistant metal. Garden hose fittings were plastic. Old T- 46CFR181.15-10(f)
Condition: Improper Installation
Action required: 10 - Deficiency Rectified
Due 10 March 2020
Resolved 10 March 2020
Resolution: Replaced
10 - Safety of Navigation › N/A - No Subsystem › Automatic Identification System (AIS)
Issued 8 August 2018 Resolved
Vsl is broadcasting: No static draft information and no dimension information (AIS Antenna Position ABCD values equals 0).
Condition: Invalid
Action required: 705 - Other - as specified
Due 8 September 2018
Resolved 18 March 2019
Engineering › Shafting/Propeller Arrangements › Coupling Bolt
Issued 11 April 2017 Resolved
Vessel reported port tail-shaft seized in place with shaft coupling spinning on locked tail-shaft. Forward water lubricated shaft bearing material broke free from its' molding and became lodged around shaft in its' housing internal of vessels shaft log, this seizing of material caused the coupling key internal of shaft coupling to sheer in half, thus allowing the coupling to free spin on tail-shaf
Condition: Design Flaw
Action required: 705 - Other - as specified
Resolved 13 April 2017
Resolution: Reviewed survey report from repair facility. Vessel fit for intended service.
Engineering › Bilge Water Management System › Valve
Issued 15 March 2017 Resolved
Conduct maintenance and regularly exercise screw down valve located on aft side of collision bulkhead.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 17 March 2017
Resolved 17 March 2017
Resolution: Vessel rep conducted maitenance on valve and proved proper operation.
Lifesaving › Lifejacket/PFD (General) › Condition
Issued 15 March 2017 Resolved
Repair lifefloat/life jacekets IAW manufacturer's recommendations.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 29 March 2017
Resolved 17 March 2017
Resolution: Vessel rep repaired life float and life jackets using proper [name withheld] kit.
Accommodation/Occupational Safety › Occupational Safety › Spark Producing Device
Issued 15 March 2017 Resolved
Remove or properly cap dead end wiring.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 22 March 2017
Resolved 17 March 2017
Resolution: Vessel rep removed all dead end wiring.

Casualty record · 1

24 August 2008Routine · role: Involved in a Marine Casualty · activity 3317522
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.