Records from 1982 to 2003. Most recent: inspection, 24 October 2003.
Inspection history · 12
24 October 2003
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1935222
22 October 2003
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1933664
10 October 2003
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1928261
10 October 2003
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1930523
29 May 2003
Annual Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1805382
25 May 2003
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1800842
24 May 2003
Security Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1800856
6 May 1988
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1039320
23 September 1987
Administrative
Administrative · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1007109
24 January 1986
Re-Inspection
Physical examination · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 1305112
3 November 1984
Type not recorded
No type recorded · ACTIVITIES NEW YORK · USCG Northeast District (CGD-NE) · Activity 976541
10 April 1982
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1281532
Construction/Loadline › Markings
Issued 14 October 2003
Resolved
Have Certificate Issuing Authority approve Load Line Certificate and Load Line Markings prior to departure. LEGACY COMPONENT DESC: Load Line Mark
Action required: 17 - Rectify deficiencies prior to departure
Due 18 October 2003
Resolved 18 October 2003
Resolution: Flag State Representative ammended International Loadline Certificate to reflect loadline marking on vessel.
Engineering › Fuel Oil Storage/Transfer System
Issued 14 October 2003
Resolved
Provide vessel's piping diagram for all systems prior to departure.
Due 18 October 2003
Resolved 18 October 2003
Resolution: Vessel provided piping diagrams for all systems onboard.
Pollution Prevention/Response › Prevention Equipment
Issued 14 October 2003
Resolved
Provide the following for the M.S.D.:
1. Certificate for MSD
2. Operating manual for MSD
3. Piping diagram for MSD
4. High level swith on MSD needs to be repaired/replaced
5. Provide proof of operation of MSD prior to use. LEGACY COMPONENT DESC: Marine Sanitation Device, Type II
Due 20 October 2003
Resolved 20 October 2003
Resolution: Vessel provided all necessary certificates and manuals for MSD system and demonstrated proper operation of the system.
Pollution Prevention/Response › Prevention Equipment
Issued 14 October 2003
Resolved
Provide mechanical means of closure for all containment on main deck prior to departure. LEGACY COMPONENT DESC: Fixed Containment
Due 18 October 2003
Resolved 18 October 2003
Resolution: New closure devices were installed on all containments.
Documentation › Certificates/Documents
Issued 14 October 2003
Resolved
Vessel's class certificate needs to be endorsed from third annual survey. Prior to departure have Certificate Issuing Authority endorse class certificate.
Due 16 October 2003
Resolved 16 October 2003
Resolution: Representative of The Republic of Mexico attended vessel and endorsed certificate.
Pollution Prevention/Response › Prevention Equipment
Issued 14 October 2003
Resolved
Provide proof of operation and proper installation of Oily Water Separator prior to departure. LEGACY COMPONENT DESC: Oily Water Separator (100 ppm)
Due 20 October 2003
Resolved 20 October 2003
Resolution: Crew demonstrated proper operation of OWS.
Engineering › Bilge Water Management System
Issued 14 October 2003
Resolved
Permanently install a bilge pump for a total number of two working pumps prior to departure. LEGACY COMPONENT DESC: Pump
Due 20 October 2003
Resolved 20 October 2003
Resolution: Crew demonstrated proper operation of new bilge pump.
Engineering › Bilge Water Management System
Issued 14 October 2003
Resolved
Remove excessive oil from bilges prior to departure.
Due 20 October 2003
Resolved 20 October 2003
Resolution: Bilges and slops tanks were emptied by approved mobile facility.
Deck/Cargo › Holds/Tanks
Issued 14 October 2003
Resolved
Have Certificate Issuing Authority address forward peak tank being used as slop tank prior to departure.
Due 20 October 2003
Resolved 20 October 2003
Resolution: Peak Tank was emptied and proper use was addressed by Flag State representative and discussed with the crew.
Fire Fighting › Fire Pumps
Issued 14 October 2003
Resolved
Fire pump had inadequate pressure. Repair or replace main fire pump and replace/install emergency fire pump prior to departure.
Due 20 October 2003
Resolved 20 October 2003
Resolution: New fire pump was installed and proper operation was demonstrated by the crew.
Documentation › Logs/Records
Issued 14 October 2003
Resolved
Vessel did not complete Oil Record Book to reflect internal transfers of bilge slop to unauthorized tank (forward peak tank), therefore vessel shall not perform and internal/external transfers. LEGACY COMPONENT DESC: Oil Record Book
Due 20 October 2003
Resolved 20 October 2003
Resolution: New oil record book was aquired and cetified by Flag State representative.
Fire Fighting › International Shore Connection
Issued 29 May 2003
Resolved
Provide International Shore Connection prior to next U.S. Port
Condition: Unknown
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 31 May 2003
Resolved 18 October 2003
Resolution: Vessel provided International Shore Connection and identified location on fire control plan.
Lifesaving › Line-Throwing Appliances
Issued 29 May 2003
Resolved
Provide One additional Line-Throwing Appliance Prior to next U.S. Port LEGACY COMPONENT DESC: Projectiles
Condition: Unknown
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 31 May 2003
Resolved 10 October 2003
Resolution: Vessel provided one additional line-throwing appliance for a total number of 04.
Navigation › Piloting/Steering
Issued 29 May 2003
Resolved
Provide updated charts and publications prior to next U.S. Port. LEGACY COMPONENT DESC: Marine Charts
Condition: Unknown
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 31 May 2003
Resolved 18 October 2003
Resolution: Vessel provided updated charts and required publications.