Inspection history · 63
22 June 2012
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4421674
7 November 2011
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4190955
12 September 2011
Permit to Proceed
Administrative · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 4143420
19 August 2011
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4120379
27 July 2011
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4095893
30 December 2010
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3917888
14 October 2010
MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3870714
27 January 2010
Deficiency Check · Damage Survey
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3671057
16 July 2009
Permit to Proceed · Damage Survey
Physical examination · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 3536205
12 November 2008
Internal Structural Exam · COI Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3361653
28 November 2007
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3105844
10 November 2007
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3096991
1 October 2007
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3070488
6 September 2007
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3071877
12 January 2007
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2854786
3 October 2006
MTSA Verification · Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2564181
8 September 2006
MTSA Verification · Periodic Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2797866
9 March 2005
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2306428
16 November 2004
Annual Inspection · MTSA Verification
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2288467
24 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1989502
15 October 2003
COI Inspection · Internal Structural Exam · Hull Examination · Cargo Tank Internal · Examination of Repairs
Physical examination · MIDET WEST DETAIL · USCG Heartland District (CGD-H) · Activity 1928628
17 September 2002
Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1682903
21 September 2001
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1074698
12 December 2000
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1420434
6 January 2000
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1384327
10 December 1999
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 63660
16 December 1998
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 810955
10 August 1998
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1131922
21 November 1997
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1437332
22 July 1997
Deficiency Check
Physical examination · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1118275
18 July 1997
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 171747
7 February 1997
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1103534
7 February 1997
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1103538
17 January 1997
Damage Survey
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1380737
13 November 1996
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1404263
21 November 1995
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1357386
20 September 1995
Administrative
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 875094
1 November 1994
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1446135
22 November 1993
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 839496
19 October 1993
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1133598
2 September 1992
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1249253
22 July 1992
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 507285
26 March 1992
Examination of Repairs
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1269857
4 December 1991
Examination of Repairs · Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 945302
27 April 1991
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 441626
9 November 1990
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1232994
5 October 1990
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 506735
17 April 1990
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 460504
11 April 1990
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 520646
12 February 1990
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1227135
4 October 1989
Administrative
Administrative · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1018396
14 February 1989
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1348598
19 January 1989
Damage Survey
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 890140
16 December 1988
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1039784
16 December 1988
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1347717
25 June 1988
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 515762
4 January 1988
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1316950
22 June 1987
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 443293
9 May 1987
Damage Survey
Physical examination · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 1329965
16 December 1986
Hull Examination · COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1005461
28 January 1986
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1305889
20 December 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 976342
13 January 1983
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1279686
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Piping
Issued 12 September 2011
No resolution recorded
Pinhole leak on cargo line elbow near 1P cargo tank access hatch. Temporary repairs have been affected. Permit to proceed to Freeport, TX for permanent repairs.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Construction/Loadline › Hull › Hull Plating
Issued 27 July 2011
Resolved
D8 TBSIP SELF-REPORTED DEFICIENCY. Make permanent repairs to 1/4" hole in bow stbd bilge corner knuckle
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 5 September 2011
Resolved 19 August 2011
Construction/Loadline › Hull › Hull Plating
Issued 27 January 2010
Resolved
Gauge extend of fracture and make permanent repairs to stern box hull plating.
Condition: Unknown
Action required: 705 - Other - as specified
Resolved 4 February 2010
Resolution: Repaired wastage in stern box with 4''''''''x7''''''''x3/8" steel plate. Witnessed 1.5# air test satisfactory.
Construction/Loadline › Hull › Hull Plating
Issued 16 July 2009
Resolved
Barge has a 20" x 1/4" fracture along the push knee, turn of the deck, bow void, stbd side. Barge is allowed to transit in a loaded condition from Dow Seadrift to Houston to offload cargo and the proceed to conduct permanent repairs.
Action required: 705 - Other - as specified
Resolved 1 August 2009
Resolution: Cleared 01AUG09 by [name withheld].
Construction/Loadline › Hull › Hull Plating
Issued 1 October 2007
Resolved
Vessel reports 1/2" x 1/8" ftracture in stbd void 2" from orange peel .
Condition: Unknown
Action required: 705 - Other - as specified
Due 12 November 2007
Resolved 10 November 2007
Resolution: Examined welds and witnessed satisfactory air tested welds of 4''x30"x1/2" section of bilge knuckle in way of the stbd bow and a 30"x18"x3/8" section of bottom plate in way of the stbd bow.
Construction/Loadline
Issued 22 July 1997
Resolved
After discharge of cargo, make permanent repairs to fracture on starboard stern corner, just below the deck turn. Repairs to be completed prior to next cargo load transfer, and to be inspected by a Coast Guard inspector.
Condition: Unknown
Due 22 July 1997
Resolved 22 July 1997
Construction/Loadline
Issued 17 January 1997
Resolved
MAKE PERMANENT REPAIRS TO FRACTURE IN WAY OF STARBOARD BOW CORNER AT 2' DRAFT MARK. NO FURTHER CARGO OPERATIONS PERMITTED UNTIL PERMANENT REPAIRS ARE INSPECTED TO THE SATISFACTION OF A COAST GUARD MARINE INSPECTOR.
Condition: Unknown
Due 17 January 1997
Resolved 17 January 1997
Documentation
Issued 13 November 1996
Resolved
PROVIDE CERTIFICATE OF DOCUMENTATION AS REQUIRED BY 46 CFR 67.7.
Condition: Unknown
Due 13 November 1996
Resolved 13 November 1996
Construction/Loadline
Issued 19 January 1989
Resolved
PERMANENTLY REPAIR 18" FRACTURE IN STBD STERN CORNER AT 11' DRAFT PRIOR TO LOADING CARGO BUT NOT LATER THAN 28FEB89.
Condition: Unknown
Due 19 January 1989
Resolved 19 January 1989
Construction/Loadline
Issued 19 January 1989
Resolved
PERMANENTLY REPAIR 4" WELD FRACTURE IN RUB PAD ON STBD SIDE AT 2' DRAFT AT NEXT GAS-FREE AVAILABILITY BUT NOT LATER THAN 28FEB89.
Condition: Unknown
Due 19 January 1989
Resolved 19 January 1989