Inspection history · 92
5 December 2014
Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 5034916
29 October 2014
Damage Survey · Administrative Inspection
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 5014324
24 December 2013
Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4779399
16 February 2012
Deficiency Check
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4245822
31 January 2012
Examination of Repairs · Annual Inspection · Damage Survey · Administrative Inspection
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4235419
4 January 2012
Administrative Inspection
Administrative · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4218205
12 October 2010
MTSA Verification · Annual Inspection · Administrative Inspection · Deficiency Check
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 3869173
20 January 2009
Administrative Inspection · Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 3396900
5 April 2007
Periodic Inspection
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 2901820
19 April 2006
Annual Inspection
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 2628058
18 January 2005
Cargo Tank Internal · COI Inspection · MTSA Verification · Internal Structural Exam · Hull Examination
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2276652
9 November 2004
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 2238012
15 April 2004
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 2044462
30 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1973695
29 October 2003
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1938206
25 August 2003
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1887005
9 April 2003
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1770847
6 July 2002
Examination of Repairs
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1642933
11 January 2002
Deficiency Check · COI Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1477741
8 September 2001
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 101258
21 June 2001
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1072970
12 April 2001
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1405149
15 March 2001
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1060300
30 January 2001
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1057189
3 November 2000
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 94343
17 May 2000
Examination of Repairs
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 818086
14 January 2000
COI Inspection · Hull Examination
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1381771
16 August 1999
Examination of Repairs
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 777929
26 January 1999
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 424929
26 January 1999
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 763670
26 January 1999
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 763671
26 January 1999
COI Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1408235
11 January 1999
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 643497
4 January 1999
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 190196
2 January 1999
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 190203
21 December 1998
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 102355
20 March 1998
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 414009
18 March 1998
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 414710
29 January 1998
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1456553
9 May 1997
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1100819
27 January 1997
COI Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1422779
23 January 1997
Examination of Repairs
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1101397
17 January 1997
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 197930
17 January 1997
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 763685
24 November 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 643498
21 October 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 763675
2 October 1996
Deficiency Check · Damage Survey
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1137647
23 September 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 190191
15 August 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 158995
15 August 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 205215
26 March 1996
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1445053
16 February 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 753770
15 February 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 199843
8 February 1995
COI Inspection · Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1466382
4 April 1994
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 1167241
15 March 1994
COI Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 855751
18 February 1993
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1144968
3 December 1992
Type not recorded
No type recorded · MSD QUAD CITIES · USCG Heartland District (CGD-H) · Activity 653128
27 October 1992
Type not recorded
No type recorded · MSD QUAD CITIES · USCG Heartland District (CGD-H) · Activity 150535
22 April 1992
Type not recorded
No type recorded · MSD QUAD CITIES · USCG Heartland District (CGD-H) · Activity 350249
22 April 1992
Deficiency Check
Physical examination · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 946933
1 April 1992
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 669572
25 March 1992
COI Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 946978
23 October 1991
Type not recorded
No type recorded · MSD QUAD CITIES · USCG Heartland District (CGD-H) · Activity 503911
9 April 1991
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 455634
24 January 1991
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1231159
12 June 1990
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 517739
23 May 1990
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 905333
29 April 1990
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 922035
23 March 1990
COI Inspection · Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 915406
15 November 1989
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1232125
5 October 1989
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1330985
6 March 1989
Deficiency Check
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1200835
1 February 1989
COI Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 897773
17 March 1988
Administrative
Administrative · MSO Paducah · USCG Heartland District (CGD-H) · Activity 975341
17 March 1988
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1286768
18 December 1987
Administrative
Administrative · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 1004203
21 February 1987
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 450795
17 February 1987
COI Inspection · Hull Examination
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1321875
28 April 1986
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 446182
23 April 1986
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 998615
6 January 1986
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 986494
23 April 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 983896
23 August 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1282975
1 February 1984
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1278541
27 September 1983
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1278200
27 July 1983
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 971934
27 July 1983
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1276400
7 July 1983
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1277261
13 August 1982
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 967325
10 August 1982
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1278268
28 October 1981
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1274411
Deck/Cargo › Cargo Stowage › General
Issued 29 October 2014
Resolved
The #1 cargo tank is leaking into the bow rake void. There is approx 1" of cargo in the void. Barge may not load any additional cargo onboard.
Action required: 705 - Other - as specified
Due 31 December 2014
Resolved 15 November 2022
Resolution: MISLE Clean up
Pollution Prevention/Response › Prevention Equipment › Fixed Containment
Issued 31 January 2012
Resolved
Provide containment for the slop oil transfer connections.
Action required: 705 - Other - as specified
Resolved 16 February 2012
Pollution Prevention/Response › Prevention Equipment › Fixed Containment
Issued 31 January 2012
Resolved
Provide containment for the lube oil transfer connections.
Action required: 705 - Other - as specified
Resolved 16 February 2012
Documentation › Manuals/Policy Documentation › Transfer Procedures
Issued 31 January 2012
Resolved
Update transfer procedures for the slop and lube oil transfer systems.
Action required: 705 - Other - as specified
Resolved 16 February 2012
Documentation › Manuals/Policy Documentation › Transfer Procedures
Issued 12 October 2010
Resolved
Update Notification contacts in vessels Transfer Procedures.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Resolved 19 October 2010
Resolution: Provided evidence of updated numbers in transfer procedures.
Electrical › Electrical Distribution System (service) › Panelboard
Issued 19 April 2006
Resolved
Properly repair electrical box protective cover on stbd electrical box.
Due 19 April 2006
Resolved 5 April 2007
Electrical › Electrical Distribution System (service) › Wiring
Issued 19 April 2006
Resolved
Properly secure wire leading to electrical box on top of Lube Oil tank.
Due 19 April 2006
Resolved 5 April 2007
Deck/Cargo › Vapor Control Systems › Flame Screens
Issued 19 April 2006
Resolved
Replace all flame screens on Lube Oil tank.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 5 April 2007
Documentation › Certificates/Documents › Certificate of Inspection
Issued 19 April 2006
Resolved
Provide copy of MSC letter and dwg #0165, Rev. 2 dated 30 Nov 2005 to MSU Paducah and make vessel available for As Built Verification prior to using newly installed fuel injection system.
Action required: 705 - Other - as specified
Resolved 5 April 2007
Deck/Cargo › Cargo Stowage › General
Issued 4 March 2005
Resolved
Owner of barge is to summit plans for review and approval to MSC for installed gasoline tank on deck. Tank and equipment are not to be used with out approval of MSC and local Coast Guard Inspection Office. Vessel HIGHEST GRADE has been reduced to GRADE "D" and lower. Due to the installation of electric start on the cargo engine, installed lighting, and power distribution panel.
Condition: Improper Installation
Due 4 April 2005
Resolved 4 March 2005
Fire Fighting › Portable Dry Chemical Fire Extinguisher
Issued 9 April 2003
Resolved
Sevrvice tags not properly attached / attachment wires broken on all extinguishers
Due 9 April 2003
Resolved 9 April 2003
Resolution: Corrected during inpsection.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 9 April 2003
Resolved
Water-light not working as batteries not installed.
Due 9 April 2003
Resolved 9 April 2003
Resolution: Light removed from lifering.
Deck/Cargo › Holds/Tanks › Flame Arrester
Issued 9 April 2003
Resolved
Flame SCREENS (3 out of 4) were in need of replacement.
Condition: Unknown
Due 9 April 2003
Resolved 9 April 2003
Resolution: New flame screens installed prior to inspectors departure.
Deck/Cargo › Cargo Transfer/Lightering (liquid)
Issued 11 January 2002
Resolved
Repack reachrods on all cargo tanks LEGACY COMPONENT DESC: Gaskets
Condition: Unknown
Due 11 February 2002
Resolved 23 January 2002
Resolution: All reachrods repacked
Deck/Cargo › Holds/Tanks
Issued 11 January 2002
Resolved
Renew/replace cargo tank hatch cover gaskets LEGACY COMPONENT DESC: Hatch Cover
Condition: Unknown
Due 11 February 2002
Resolved 23 January 2002
Resolution: Cargo tank hatch cover gaskets renewed.
Deck/Cargo
Issued 14 January 2000
Resolved
MAKE TWO CARGO DECK TANKS AVAILABLE FOR INTERNAL EXAMINATION BY USCG MARINEINSPECTOR.
Condition: Unknown
Due 14 March 2000
Resolved 26 January 2000
Construction/Loadline
Issued 14 January 2000
Resolved
MARK PROPER DOCUMENTED VESSEL NAME ON STERN OF VESSEL.
Condition: Unknown
Due 21 January 2000
Resolved 20 January 2000
Electrical
Issued 14 January 2000
Resolved
REPLACE DAMAGED ELECTRICAL CIRCUIT BREAKER BOX ON AFT CARGO DECK TANK AND PROVIDE DRIP PROTECTION FOR NEW INSTALLATION.
Condition: Unknown
Due 20 January 2000
Resolved 20 January 2000
Electrical
Issued 14 January 2000
Resolved
REMOUNT JUNCTION BOX LOCATED OVER LUBE OIL DECK TANK.
Condition: Unknown
Due 21 January 2000
Resolved 20 January 2000
Lifesaving
Issued 14 January 2000
Resolved
RENEW/REMARK FADED CARGO PUMP ENGINE EMERGENCY SHUTDOWN LOCATION SIGNS.
Condition: Unknown
Due 21 January 2000
Resolved 20 January 2000
Engineering
Issued 18 March 1998
Resolved
46 C.F.R. 35.30-10 Upon inspection the flame sceen on the diesel tank was noticed torn.
Condition: Unknown
Due 26 January 1999
Resolved 26 January 1999
Documentation
Issued 18 March 1998
Resolved
33 C.F.R. 155.1025 The Response Plan letter of apporval for the tank barge was not on board at the time of boarding.
Condition: Unknown
Due 18 April 1998
Resolved 10 April 1998
Construction/Loadline
Issued 29 January 1998
Resolved
DEWATER, LOCATE CAUSE OF FLOODING IN STERN VOID, THEN MAKE PERMANENT REPAIRS PRIOR TO LOADING CARGO. VESSEL IS ALLOWED TO DISCHARGE CARGO.
Condition: Unknown
Due 5 February 1998
Resolved 5 February 1998
Construction/Loadline
Issued 2 October 1996
Resolved
VESSEL HAD DAMAGE IN THE WAY OF A SPLIT WELD ON THE HULL AND RUB RAIL STBD #1 FUEL TANK. ALL REPAIRS SHALL BE COMPLETED PRIOR TO LOADING OF ANY CARGO.
Condition: Unknown
Due 2 October 1996
Resolved 2 October 1996
Deck/Cargo
Issued 18 February 1993
Resolved
5 UNAPPROVED QUICK-RELEASE CAPS/COUPLINGS WERE IN USE. REPLACE THESE FITTINGS WITH APPROVED FITTINGS PRIOR TO TRANSFERRING CARGO BUT NOT LATER THAN COMPLIANCE DATE.
Condition: Unknown
Due 18 February 1993
Resolved 18 February 1993
Deck/Cargo
Issued 18 February 1993
Resolved
INDEPENDENT DECK TANK DISCHARGE TRANSFER SITE HAD NO CONTAINMENT. PROVIDE ADEQUATE CONTAINMENT PRIOR TO TRANSFERRING CARGO FROM TANK BUT NOT LATER THAN COMPLIANCE DATE.
Condition: Unknown
Due 18 February 1993
Resolved 18 February 1993
Deck/Cargo
Issued 25 March 1992
Resolved
CARGO PUMP DRIVE ENGINE FUEL TANK VENT FLAME SCREEN WAS TORN.
Condition: Unknown
Due 26 March 1992
Resolved 26 March 1992
Deck/Cargo
Issued 25 March 1992
Resolved
QUICK RELEASE FITTINGS ON CARGO TRANSFER PIPING AND ONBOARD HOSES WERE NOT OF AN APPROVED TYPE. REPLACE ALL NONAPPROVED FITTINGS WITH APPROVED FITTINGS TO THE SATISFACTION OF THE COGNIZANT O.C.M.I.
Condition: Unknown
Due 25 March 1992
Resolved 25 March 1992
Deck/Cargo
Issued 25 March 1992
Resolved
PLUG TO ELECTRICAL CORD FOR LUBE OIL DECK TANK HEATER THAT CONNECTS TO SHORESIDE OUTLET HAD NOT BEEN PROPERLY INSTALLED.
Condition: Unknown
Due 26 March 1992
Resolved 26 March 1992
Documentation
Issued 25 March 1992
Resolved
CERTIFICATE OF INSPECTION EXPIRED ON 23 MAR 92.
Condition: Unknown
Due 26 March 1992
Resolved 26 March 1992
Unknown
Issued 29 April 1990
Resolved
MAKE VESSEL READY FOR INSPECTION OF ADDED DECK TANK (SLOP OIL TANK). AND PIPING ASSOCIATED WITH TANK. TANK IS NOT TO BE USED BEFORE VESSEL IS INSPECTED FOR COMPLIANCE WITH APPROVED PLANS @ MSO NOLA.
Condition: Unknown
Due 29 April 1990
Resolved 29 April 1990
Electrical
Issued 23 March 1990
Resolved
MAKE WIRING INSULATION AND SPLICES ON CARGO PUMP ENGINE IN A SAFE CONDITIONAS REQUIRED BY 46 CFR 111.60 PRIOR TO NEXT CARGO OPERATION.
Condition: Unknown
Due 23 March 1990
Resolved 23 March 1990
Deck/Cargo
Issued 23 March 1990
Resolved
PROVIDE OCMI WITH APPROVED PLANS FOR INSTALLATION OF TWO DECK CARGO TANKS PRIOR TO PLACING INTO SERVICE.
Condition: Unknown
Due 23 March 1990
Resolved 23 March 1990
Documentation
Issued 23 March 1990
Resolved
REMEASURE VESSEL DUE TO ADDITION OF TWO DECK CARGO TANKS AS REQUIRED BY 46 CFR 69.05.
Condition: Unknown
Due 23 March 1990
Resolved 23 March 1990
Documentation
Issued 1 February 1989
Resolved
THE OIL TRANSFER PROCEDURES ARE OUTDATED, ARE NOT APPLICABLE TO THIS VESSELAND DO NOT COMPLY WITH THE REQUIREMENTS OF 33 CFR 155.750. PROVIDE PROPER OIL TRANSFER PROCEDURES WHICH COMPLY WITH ALL OF THE REQUIREMENTS OF 33 CFR 155.750.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Deck/Cargo
Issued 1 February 1989
Resolved
THE CARGO PUMP ENGINE REMOTE EMERGENCY SHUT DOWN WARNING SIGN IS LOOSE. SECURE THIS SIGN TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Deck/Cargo
Issued 1 February 1989
Resolved
THE WARNING SIGN IS IMPROPERLY INSTALLED. MOVE THIS SIGN TO A MORE VISIBLELOCATION THAT IS SATISFACTORY TO THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Navigation
Issued 1 February 1989
Resolved
THE PORT RUNNING LIGHT STAND IS BENT INBOARD. CORRECT THIS ITEM TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Construction/Loadline
Issued 1 February 1989
Resolved
TWO DOG BOLTS ARE MISSING ON THE P/S BOW VOID HATCH COVER AND THE STBD STERN VOID HATCH COVER. REPLACE THESE ITEMS TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Fire Fighting
Issued 1 February 1989
Resolved
THE SEMI-PORTABLE UNIT'S NITROGEN CYLINDER REQUIRES A HYDROSTATIC TEST. THE UNIT REQUIRES SERVICING. COMPLETE THIS ITEM TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Construction/Loadline
Issued 1 February 1989
Resolved
THE VESSEL'S NAME AND DRAFT MARKS ARE WORN. REMARK THESE ITEMS TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Deck/Cargo
Issued 1 February 1989
Resolved
THE CARGO PUMP DRIVE SHAFT GUARD DOES NOT COVER THE AFTER UNIVERSAL JOINT. EXTEND THIS GUARD TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Deck/Cargo
Issued 1 February 1989
Resolved
1,2 P/S CARGO TANK P/V VALVE FLAME SCREENS ARE CLOGGED. CLEAN OR REPLACE THE SCREENS TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 1 February 1989
Resolved 1 February 1989
Documentation
Issued 17 February 1987
Resolved
TRANSFER PROCEDURES SHOW IMPROPER LOCATION FOR EMERGENCY SHUT DOWN, AND DO NOT HAVE PIPING DIAGRAM FOR LUBE OIL CARGO SYSTEM. CORRECT THE TRANSFER PROCEDURES IN THESE AREAS.
Condition: Unknown
Due 17 February 1987
Resolved 17 February 1987
Construction/Loadline
Issued 17 February 1987
Resolved
BILGE KNUCKLE FRACTURED AND SET UP IN NUMEROUS PLACES IN BOW RAKE. CROPPED OUT AND RENEWED 18' OF PORT KNUCKLE AND 4' OF STBD KNUCKLE, AND RENEWED ALL GUSSETS IN WAY OF REPLACED KNUCKLE.
Condition: Unknown
Due 17 February 1987
Resolved 17 February 1987
Deck/Cargo
Issued 23 April 1986
Resolved
FLAME SCREENS MISSING. REPLACE MISSING FLAME SCREENS FOR THE #1 PORT AND #2 STARBOARD TANK TOP OPENINGS.
Condition: Unknown
Due 23 April 1986
Resolved 23 April 1986
Deck/Cargo
Issued 23 April 1986
Resolved
CARGO ENGINE WOULD NOT START TO TEST REMOTE SHUTDOWN. PROVE OPERATION OF CARGO ENGINE REMOTE SHUTDOWN.
Condition: Unknown
Due 23 April 1986
Resolved 23 April 1986
Unknown
Issued 23 August 1984
Resolved
THE FOLLOWING DEFICIENCY PERTAIN TO THE VESSEL, BAC 420, DN568032 AND IS TO BE COMPLIED WITH BY 30AUG84.
Condition: Unknown
Due 23 August 1984
Resolved 23 August 1984
Unknown
Issued 23 August 1984
Resolved
REPLACE DAMAGED FLAME SCREENS ON PV VALVES TO THE SATISFACTION OF THE ATTENDING U.S. COAST GUARD INSPECTOR.
Condition: Unknown
Due 23 August 1984
Resolved 23 August 1984