Records from 1999 to 2026. Most recent: inspection, 7 July 2026.
Documentation record
Registered dimensions (L × B × D)50.0 ft × 19.0 ft × 7.0 ft
Registered tonnagegross 44 / net 35
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderINTRACOASTAL IRON WORKS · BOURG, LA, UNITED STATES · built 1999
Hull materialAluminum
PropulsionDiesel Reduction
Hull shapeShip
Hull configurationMonohull
Hailing portNEW ORLEANS, LA
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 14 January 2026 · expires 28 February 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it44 - Simplified, Gross Ton
35 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 33
7 July 2026
Administrative Inspection · Annual Inspection · Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8432059
17 September 2025
Internal Structural Exam · Annual Inspection · Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8229645
21 March 2025
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8097617
21 March 2025
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8100153
5 July 2024
Drydock Exam · COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7939568
7 September 2023
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7768743
7 July 2022
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7473644
6 July 2021
Administrative Inspection · Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7225079
24 September 2020
Internal Structural Exam · Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7043826
5 July 2019
Drydock Exam · COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6720039
9 August 2018
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6502586
5 July 2017
Annual Inspection · Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6191807
19 December 2016
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6060211
5 August 2016
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5960411
7 August 2015
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5206828
26 June 2014
COI Inspection · Drydock Exam · DAPI Audit
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4896917
14 July 2009
COI Inspection · Hull Examination
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3529185
20 April 2009
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3456514
12 September 2008
Damage Survey · Examination of Repairs · Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3323348
12 September 2008
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3742820
9 October 2007
Administrative Inspection · Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3067382
27 September 2006
Annual Inspection · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2788453
1 February 2005
Security Plan Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2284735
16 June 2004
COI Inspection · Hull Examination
Physical examination · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 2100019
6 June 2003
Annual Inspection
Physical examination · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 1810955
20 December 2002
Administrative Inspection
Administrative · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 1721451
30 May 2002
Annual Inspection
Physical examination · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 1623338
23 May 2002
Simplified Stability Test · Plan Review "T" Boat
Physical examination · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 1619861
19 October 2001
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1073940
13 June 2001
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1417307
14 June 2000
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1050833
26 May 2000
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1376193
1 March 1999
Initial Construction-Excluding Oversight · Initial Certification
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1375657
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Gauges, thermometers, etc
Issued 7 July 2026
Resolved
Gauges to indicate engine revolutions per minute (RPM), jacket water discharge temperature, and lubricating oil pressure must be provided for all propulsion engines installed in the vessel. The gauges must be readily visible at the operating station. The RPM gauges did not show the RPMs.
cite: 46 CFR 182.410(b)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 3 September 2026
Resolved 12 August 2026
Resolution: Vsl submitted video showing operable RPM gauges. Repair satisfactory.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 17 September 2025
Resolved
Vapor barriers must be provided where insulation of any type is used in spaces where flammable and combustible liquids or vapors are present, such as machinery spaces and paint lockers.
MI observed smoke coming from the engine room, through the cable run underneath the main steering position, into the main cabin. Make space vapor tight to the satisfaction of the attending MI.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 3 October 2025
Resolution: recieved photographic evidience of repair.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 17 September 2025
Resolved
Flexible nonmetallic hose may be used in non-vital water and pneumatic systems if it possesses characteristics adequate for its intended service and environment.
MI observed the nonmetallic hose for the air intake for the STBD engine had ripped in multiple areas. Repair or replace intake hose to the satisfaction of the attending MI.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 7 October 2025
Resolution: recieved photographic evidence satisfactory repair.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Covers (hatchway-, portable-, tarpaulins, etc.)
Issued 17 September 2025
Resolved
A hatch exposed to the weather must be watertight.
MI observed the the hatch leading to the fixed fire fighting storage has a crack. Hatch was repaired multiple times previously. Replace hatch and conduct NDT to the satisfaction of the attending MI.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 3 October 2025
Resolution: Conducted satisfactory NDT on new hatch.
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 21 March 2025
Resolved
The Certificate of Inspection issued to a vessel describes the... the minimum manning requirements. CG inspector observed and verified vessel was operating with only one master onboard.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 21 March 2025
Resolution: Recieved deckhand identification added to meet manning and company letter stating that moving forward they will be manning in acordance with their COI.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 5 July 2024
Resolved
The following spaces must be equipped with a fire detection and alarm system of an approved type installed in accordance with 46 CFR part 76 ... A space containing propulsion machinery. MI observed battery fault alarm on pilothouse indicator panel. 46 CFR 181.405 (a)(1) 60c
Condition: Improper Installation
Action required: 60 - Rectify deficiencies prior to movement
Due 5 July 2024
Resolved 5 July 2024
Resolution: TPO report received. All sat.
10 - Safety of Navigation › N/A - No Subsystem › Revolution counter
Issued 5 July 2024
Resolved
Gauges to indicate engine revolutions per minute (RPM), jacket water discharge temperature, and lubricating oil pressure must be provided for all propulsion engines installed in the vessel. The gauges must be readily visible at the operating station. MI observed inoperable RPM gauges for both MDE in pilothouse. 46 CFR 182.410 (b) 16c
Action required: 16 - Rectify deficiencies w/in 14 days
Due 19 July 2024
Resolved 8 July 2024
Resolution: Received emailed video. All sat.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 5 July 2024
Resolved
Each item of lifesaving equipment with an expiration date must be replaced during the annual inspection and repair if the expiration date has passed. MI observed out of date battery installed. 46 CFR 180.70 (d) 10c
Action required: 10 - Deficiency Rectified
Due 5 July 2024
Resolved 5 July 2024
Resolution: Vessel rep replaced battery to the satisfaction of the attending MI.
Electrical › Electrical Distribution System (service) › Switchboard
Issued 5 July 2017
Resolved
Analyze load on switchboard and mark appropriately. Install proper connectors.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 12 July 2017
Resolved 6 July 2017
Resolution: Added x3 switches, labeled accordingly, and installed proper conenctors to satisfaction of attending MI.
Construction/Loadline › Hull › Hull Plating
Issued 12 September 2008
Resolved
Prior to placing vsl back into water make proper repaire to stbd midship hull (45" X 20" tear)
Action required: 705 - Other - as specified
Resolved 29 September 2008
Construction/Loadline › Hull › Weld
Issued 27 September 2006
Resolved
Cracked welds in the stern box around the fuel tank.
Action required: 705 - Other - as specified
Resolved 29 September 2006
Resolution: Cracks repaired
Navigation
Issued 26 May 2000
Resolved
PROVIDE A COPY OF NAVIGATION RULES ABOARD.
Condition: Unknown
Due 26 May 2000
Resolved 26 May 2000