Records from 1984 to 1996. Most recent: inspection, 25 March 1996.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 121
25 March 1996
Administrative
Administrative · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1079416
26 February 1996
Administrative
Administrative · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1189378
15 February 1996
Examination of Repairs
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1416248
20 August 1995
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 63206
22 July 1995
Type not recorded
No type recorded · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 880728
23 May 1995
Re-Inspection · Deficiency Check
Physical examination · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 1367406
17 April 1995
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 482752
30 March 1995
Type not recorded
No type recorded · MSO PUGET SOUND · USCG Northwest District (CGD-NW) · Activity 230431
29 January 1995
Deficiency Check
Physical examination · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 1140108
21 December 1994
Damage Survey
Physical examination · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 1170383
10 December 1994
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 163845
7 October 1994
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 454549
5 August 1994
Hull Examination · Examination of Repairs
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1389884
30 June 1994
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 539181
21 May 1994
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 491040
2 May 1994
Type not recorded
No type recorded · MSO SAN FRANCISCO BAY · USCG Southwest District (CGD-SW) · Activity 27263
2 May 1994
Administrative
Administrative · MSO SAN FRANCISCO BAY · USCG Southwest District (CGD-SW) · Activity 858116
11 April 1994
COI Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1168795
24 March 1994
Administrative
Administrative · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 856625
11 February 1994
Deficiency Check
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 851771
27 January 1994
Deficiency Check
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 852670
13 January 1994
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 363808
10 January 1994
Type not recorded
No type recorded · MSO SAN FRANCISCO BAY · USCG Southwest District (CGD-SW) · Activity 446884
4 October 1993
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1442065
2 July 1993
Re-Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1151867
10 May 1993
Examination of Repairs
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1387328
6 May 1993
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 506481
3 May 1993
Type not recorded
No type recorded · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 172901
15 April 1993
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 837774
31 March 1993
Damage Survey · Examination of Repairs
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1426771
26 March 1993
Type not recorded
No type recorded · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 357708
19 February 1993
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 128739
28 November 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 448851
9 October 1992
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 947536
16 September 1992
Administrative
Administrative · MSO SAN FRANCISCO BAY · USCG Southwest District (CGD-SW) · Activity 1261597
2 September 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 642235
26 August 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 139353
26 August 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 352740
10 August 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 642231
8 July 1992
Administrative
Administrative · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 961086
18 June 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 107260
14 May 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 642229
11 May 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 35215
11 May 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 492029
5 May 1992
COI Inspection
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 959721
10 March 1992
Administrative
Administrative · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 944812
19 February 1992
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1391750
23 January 1992
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 523219
18 January 1992
Type not recorded
No type recorded · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 953347
12 January 1992
Type not recorded
No type recorded · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 79942
8 January 1992
Examination of Repairs · Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1391749
14 December 1991
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 949741
3 December 1991
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1252751
14 September 1991
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 493261
10 September 1991
Hull Examination
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1246486
28 June 1991
Re-Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1247848
12 April 1991
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 489592
10 December 1990
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 519397
5 December 1990
Examination of Repairs
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 903257
29 August 1990
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 504841
4 August 1990
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1225379
3 July 1990
Examination of Repairs
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 923838
10 May 1990
COI Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 919953
3 May 1990
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 500706
25 April 1990
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1225781
23 February 1990
Administrative
Administrative · Commandant (CG-CVC) · Activity 1239042
14 January 1990
Examination of Repairs
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1237826
25 October 1989
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 498650
19 September 1989
Deficiency Check · Hull Examination
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1202708
29 June 1989
Re-Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1206193
12 April 1989
Administrative
Administrative · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 893314
27 March 1989
Administrative
Administrative · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1347120
16 March 1989
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1201453
14 March 1989
Administrative
Administrative · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 895606
4 February 1989
Damage Survey
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 897785
26 January 1989
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 527452
22 January 1989
Examination of Repairs · Deficiency Check
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1205689
13 January 1989
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 1197407
24 November 1988
Examination of Repairs
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1208162
27 August 1988
Type not recorded
No type recorded · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1352968
30 July 1988
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1346380
6 July 1988
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 900460
29 June 1988
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1206660
6 June 1988
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 461166
29 May 1988
COI Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 892181
30 January 1988
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 321018
22 December 1987
Examination of Repairs
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1008594
27 November 1987
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 465693
28 September 1987
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 318706
28 September 1987
Administrative
Administrative · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1010200
30 July 1987
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1030051
22 June 1987
Re-Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1012219
22 May 1987
Administrative
Administrative · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1025349
19 May 1987
Administrative
Administrative · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1024736
2 April 1987
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 469612
1 October 1986
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 516459
27 September 1986
Examination of Repairs
Physical examination · MSO PORTLAND, OREGON · USCG Northwest District (CGD-NW) · Activity 1005830
22 September 1986
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1316819
19 August 1986
Credit Drydock
Administrative · MSO HONOLULU · USCG Oceania District (CGD-O) · Activity 988304
18 July 1986
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1321037
20 June 1986
Deficiency Check
Physical examination · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 998084
12 June 1986
COI Inspection
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1004727
5 June 1986
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1297360
17 April 1986
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 455628
9 April 1986
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1296564
15 March 1986
Deficiency Check
Physical examination · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 992200
5 January 1986
Examination of Repairs
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 994889
13 December 1985
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 439265
12 September 1985
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 491150
6 September 1985
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 990609
15 August 1985
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 533244
8 August 1985
Deficiency Check
Physical examination · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1298686
9 July 1985
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 982950
14 June 1985
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 978336
7 June 1985
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 982948
29 May 1985
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 1291744
16 May 1985
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 532303
16 May 1985
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 979961
5 February 1985
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 522392
30 October 1984
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 521031
26 May 1984
Type not recorded
No type recorded · Marine Safety Unit Valdez · USCG Arctic District (CGD-A) · Activity 471497
Lifesaving
Issued 23 May 1995
Resolved
REPLACE TWO OUT OF SERVICE LIFERAFTS UPON RETURN TO LONG BEACH, CA NO LATERTHAN 02 JUN 95.
Condition: Unknown
Due 2 June 1995
Resolved 5 June 1995
Electrical
Issued 21 December 1994
Resolved
MAKE PERMANENT REPAIRS TO AUXILLARY DIESEL GENERATOR AND PROVE PROPER OPERATION OF ALL TRIPS AND ALARMS.
Condition: Unknown
Due 21 December 1994
Resolved 21 December 1994
Construction/Loadline
Issued 5 August 1994
Resolved
Make permanent repairs to indications in no. 2 port and no. 2 stbd SBT's. Repairs shall be made to the satisfaction of the attending Marine Inspectorprior to the vessel getting underway.
Condition: Unknown
Due 24 August 1994
Resolved 24 August 1994
Construction/Loadline
Issued 5 August 1994
Resolved
Repair or replace the following sea valves prior to coming off drydock: Sewage treat ovbd-bad disc and pin, replace; Waste drain ovbd-bad disc and seat, replace; Brine ovbd-could not cycle, free up; Main circ low suct.- would not close, repair; No. 2 stbd outbd 15cm (6")-torn boot, replace.
Condition: Unknown
Due 24 August 1994
Resolved 24 August 1994
Engineering
Issued 5 August 1994
Resolved
Replace the fol. boiler mounts prior to placing in service: Port Boiler: Sprhtr header drain valves-steam cuts (2 of 4), replace; Chemical feed valve-cracked disc, replace. Stbd Boiler: Sprhtr header drain valve-steam cut (1 of 4), replace.
Condition: Unknown
Due 24 August 1994
Resolved 24 August 1994
Engineering
Issued 5 August 1994
Resolved
Clean and remove rust and debris from the ship's service air receiver to allow proper internal inspection by the attending Marine Inspector prior toplacing pressure vessel back in service.
Condition: Unknown
Due 24 August 1994
Resolved 24 August 1994
Deck/Cargo
Issued 5 August 1994
Resolved
Make permanent repairs to indications found in 3 P/S, 5 P/S and 3, 4 and 5 Center COT's. Repairs shall be made to the satisfaction of the attending Marine Inspector prior to the vessel getting underway.
Condition: Unknown
Due 24 August 1994
Resolved 24 August 1994
Engineering
Issued 5 August 1994
Resolved
Remove the torn steam supply pipe lagging in the area of the no. 2 main feed pump and replace to the satisfaction of the attending Marine Inspector.
Condition: Unknown
Due 24 August 1994
Resolved 24 August 1994
Engineering
Issued 27 January 1994
Resolved
Conduct Design Verification Testing on the Bailey Automated Vital MachineryControl and Monitoring System in accordance with approved Design Verification testing procedures and 46 CFR 61.40-3.
Condition: Unknown
Due 27 January 1994
Resolved 27 January 1994
Lifesaving
Issued 15 April 1993
Resolved
PROVE PROPER OPERATION OF THE PORT LIFEBOAT PROPULSION SYSTEM. UNTIL THE BOAT IS FOUND SATISFACTORY TO A USCG MARINE INSPECTOR AND RETURNED TO THE VESSEL, EXTRA USCG APPROVED RAFTS WITH AT LEAST 35 PERSONS TOTAL CAPACITY SHALL BE KEPT AS A SUBSTITUTE & INTERNATIONAL VOYAGES ARE PROHIBITED.
Condition: Unknown
Due 15 April 1993
Resolved 15 April 1993
Construction/Loadline
Issued 8 January 1992
Resolved
ADDRESS FRACTURES IN #4 PORT W.B.T. IN THE CRITICAL AREA INSPECTION PLAN.
Condition: Unknown
Due 8 January 1992
Resolved 8 January 1992
Construction/Loadline
Issued 8 January 1992
Resolved
INSPECT TEMPORARY REPAIRS TO SIDE LONG'L 31 AT FRAME 53 IN #4P WBT AT LEASTONCE EVERY MONTH AND REPORT ANY CRACKING TO THE COGNIZANT [name withheld] (INSERT IN LONG'L) NO LATER THAN NEXT DRYDOCKING.
Condition: Unknown
Due 8 January 1992
Resolved 8 January 1992
Construction/Loadline
Issued 8 January 1992
Resolved
OBTAIN ABS AND CG (OCMI) REVIEW AND ACCEPTANCE OF THE DESIGN OF THE PROPOSED 1800 NEW BRACKETS PRIOR TO INSTALLATION._x001C_
Condition: Unknown
Due 8 January 1992
Resolved 8 January 1992
Construction/Loadline
Issued 8 January 1992
Resolved
MAKE REPAIRS TO THE FOUR FRACTURES AT FRAME #56 AND ONE FRACTURE FRAME #58 LONGITUDINAL #34 PRIOR TO CARRYING ANY CARGO.
Condition: Unknown
Due 8 January 1992
Resolved 8 January 1992
Documentation
Issued 10 September 1991
Resolved
PROVIDE COAST GUARD APPROVED PLANS ON NEW VAPOR RECOVERY SYSTEM INSTALLATION.
Condition: Unknown
Due 10 September 1991
Resolved 10 September 1991
Fire Fighting
Issued 28 June 1991
Resolved
PROVIDE COPY OF CURRENT FIRE FIGHTING FOAM ANALYSIS CERTIFICATE.
Condition: Unknown
Due 28 June 1991
Resolved 28 June 1991
Lifesaving
Issued 28 June 1991
Resolved
APPLY RETROREFLECTIVE TAPE TO ALL LIFE SAVING EQUIPMENT NOT NOW MARKED WITHRETROREFLECTIVE TAPE, (I.E. RING-BUOYS, LIFEBOATS) AS REQUIRED BY SOLAS 83 AMENDMENTS.
Condition: Unknown
Due 28 June 1991
Resolved 28 June 1991
Lifesaving
Issued 28 June 1991
Resolved
PROVIDE LONGER STEERING CABLE AND MOUNT IN INSTALLED CABLE TIES IN STARBOARD LIFEBOAT AS PERMANENT REPAIR TO STEERING SYSTEM.
Condition: Unknown
Due 28 June 1991
Resolved 28 June 1991
Construction/Loadline
Issued 28 June 1991
Resolved
PROVIDE PERMANENT REPAIRS TO FOL FRACTURES IN NO. 4 PORT BALLAST TANK (NOTE: ALL FRACTURES ON LONG #35 FROM CVK, #7 FROM TURN OF BILGE): 18"X5" FRACTURE 1' AFT WEB FRAME 57, 4"X4" FRACTURE 1' FWD WEB FRAME 56, 12"X5" FRACTURE 1.5' FWD OF WEB FRAME 55.
Condition: Unknown
Due 28 June 1991
Resolved 28 June 1991
Lifesaving
Issued 28 June 1991
Resolved
REPAIR DAMAGED STEERING CABLE IN STARBOARD LIFEBOAT AND PROVE PROPER OPERATION OF LIFEBOAT RUDDER.
Condition: Unknown
Due 28 June 1991
Resolved 8 July 1991
Engineering
Issued 10 May 1990
Resolved
PROVIDE APPROVED PLANS FOR NEWLY INSTALLED BAILEY NETWORK 90 BOILER AUTOMATION SYSTEM.
Condition: Unknown
Due 10 May 1990
Resolved 10 May 1990
Fire Fighting
Issued 10 May 1990
Resolved
PROVIDE REPORT OF ANALYSIS OF FIRE FIGHTING FOAM.
Condition: Unknown
Due 10 May 1990
Resolved 10 May 1990
Engineering
Issued 10 May 1990
Resolved
SUBMIT TEST PROCEDURES FOR NEWLY INSTALLED BAILEY NETWORK 90 BOILER AUTOMATION SYSTEM.
Condition: Unknown
Due 10 May 1990
Resolved 10 May 1990
Electrical
Issued 10 May 1990
Resolved
REMOVE OR PROPERLY WIRE THE PRINTER WIRE WHICH IS ON DECK IN CONTROL ROOM.
Condition: Unknown
Due 10 May 1990
Resolved 10 May 1990
Electrical
Issued 10 May 1990
Resolved
REPAIR 24 VOLT TEST CIRCUIT TEST BUTTON IN EMERGENCY GENERATOR ROOM.
Condition: Unknown
Due 10 May 1990
Resolved 10 May 1990
Construction/Loadline
Issued 14 January 1990
Resolved
CONDUCT U/T EXAMINATION OF ALL THE STRAKES IN WAY OF THE 6 PLUS FRACTURED LONGITUDINALS BY BULKHEAD 36.
Condition: Unknown
Due 14 January 1990
Resolved 14 January 1990
Construction/Loadline
Issued 14 January 1990
Resolved
EXAMINE ALL LONGITUDINALS ALONG BULKHEAD 36 FOR FRACTURES.
Condition: Unknown
Due 14 January 1990
Resolved 14 January 1990
Construction/Loadline
Issued 14 January 1990
Resolved
PROVIDE A PROPOSAL TO REDUCE STRESS IN NO. 1 CARGO TANKS TO PREVENT THE FURTHER POSSIBILITY OF CRACKING.
Condition: Unknown
Due 14 January 1990
Resolved 14 January 1990
Construction/Loadline
Issued 14 January 1990
Resolved
CONDUCT AN INVESTIGATION AND ANALYSIS TO DETERMINE THE CAUSE OF THE FRACTURES OF THE LONGITUDINALS IN WAY OF FRAME 32 NO. 1 PORT CARGO TANK.
Condition: Unknown
Due 14 January 1990
Resolved 14 January 1990
Construction/Loadline
Issued 14 January 1990
Resolved
COMPLETE THE LONG-TERM FIX IN CARGO TANK NO. 1 AS DESCRIBED IN CG-835 ITEM #5 DATED 11JAN90.
Condition: Unknown
Due 14 January 1990
Resolved 14 January 1990
Construction/Loadline
Issued 14 January 1990
Resolved
CONDUCT AN INVESTIGATION AND ANALYSIS OF FAILURE IN NO. 1 STBD C/T TO DETERMINE THE CAUSE OF THE FRACTURES IN WAY OF BULKHEAD 36 AND SURROUNDING LONGITUDINALS.
Condition: Unknown
Due 14 January 1990
Resolved 14 January 1990
Construction/Loadline
Issued 14 January 1990
Resolved
PROVIDE A WRITTEN REPAIR PROPOSAL THAT HAS BEEN APPROVED BY THE LOCAL ABS OFFICE TO PERMANENTLY REPAIR THE SIDESHELL AND LONGITUDINAL FRACTURES. INCLUDE THE FOLLOWING: (1) STRAKES (2) FRAMES (3) LONGITUDINALS (4) LOCATION RELATIVE TO MILD/HIGH STRENGTH STEELS (5) ANY OTHER DAMAGE
Condition: Unknown
Due 14 January 1990
Resolved 14 January 1990
Engineering
Issued 29 June 1989
Resolved
REPAIR AND PROVE PROPER OPERATION OF STARBOARD MAIN CIRCULATOR PUMP. EXCESSIVE VIBRATION DUE TO BEARINGS.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Accommodation/Occupational Safety
Issued 29 June 1989
Resolved
REPAIR AND PROVE PROPER OPERATION OF ENGINEROOM VENTILATION DAMPERS.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Navigation
Issued 29 June 1989
Resolved
PROVIDE VESSEL WITH STEERING FAILURE ALARM IAW 46 CFR 113.43-3.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Electrical
Issued 29 June 1989
Resolved
DEADEND IN A JUNCTION BOX ARMORED CABLING IN MAST OVER PILOT HOUSE.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Electrical
Issued 29 June 1989
Resolved
BLANK OFF OPEN SPACES IN GALLEY FUSE BOX #01-84-1.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Fire Fighting
Issued 29 June 1989
Resolved
ADJUST UPPER DECK AND NO.3 DECK STAIR TOWER DOORS SO THAT THEY ARE SELF CLOSING.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Electrical
Issued 29 June 1989
Resolved
PROVIDE COVER FOR JUNCTION BOX IN FREEZER ROOM.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Fire Fighting
Issued 29 June 1989
Resolved
MAKE REPAIRS TO LEAKING DRESSER COUPLINGS IN FIRE AND FOAM MAINS ON DECK.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Engineering
Issued 29 June 1989
Resolved
REPAIR AND PROVE OF PORT BOILER SURFACE BLOW.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Engineering
Issued 29 June 1989
Resolved
REPAIR LEAKING SUPERHEATER CONTROL VALVE ON STARBOARD BOILER.
Condition: Unknown
Due 29 June 1989
Resolved 29 June 1989
Construction/Loadline
Issued 27 March 1989
Resolved
PROVIDE TO USCG MSO PORTLAND, OREGON, A COPY OF THE METALLURGICAL ANALYSIS REPORT CONDUCTED ON THE FRACTURED BOTTOM PLATING THAT WAS REMOVED IN JANUARY 1989.
Condition: Unknown
Due 27 March 1989
Resolved 27 March 1989
Construction/Loadline
Issued 13 January 1989
Resolved
PROCEED TO DRYDOCK AND MAKE PERMANENT REPAIRS TO THE FRACTURE LOCATED IN THE #3 STB CARGO TANK AT PLATE E AND F FRAME 48 AND RUNNING UNDER LONGITUDINALS 16 THUR 19.THIS REPAIR IS TO BE TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR AND NLT 30 JAN 89.
Condition: Unknown
Due 13 January 1989
Resolved 13 January 1989
Engineering
Issued 6 July 1988
Resolved
PROCEED TO NEXT US PORT OF CALL AND MAKE PERMANENT REPAIRS TO THE VESSELS STERN TUBE LUBE OIL SEAL, TO THE SATISFACTION OF THE ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 6 July 1988
Resolved 6 July 1988
Electrical
Issued 29 May 1988
Resolved
REPAIR OR REPLACE FREQUENCY METER FOR EMERGENCY GENERATOR.
Condition: Unknown
Due 29 May 1988
Resolved 29 May 1988
Engineering
Issued 29 May 1988
Resolved
OPEN FOR INSPECTION OR HYDROSTATICALLY TEST THE DC HEATER.
Condition: Unknown
Due 29 May 1988
Resolved 29 May 1988
Engineering
Issued 29 May 1988
Resolved
PROVE PROPER OPERATION OF THE OILY WATER SEPARATOR.
Condition: Unknown
Due 29 May 1988
Resolved 29 May 1988
Engineering
Issued 22 December 1987
Resolved
HYDROSTATICALLY TEST PORT BOILER TO 1.25X MAWP (1375 PSIG) AFTER EITHER: (A) SHOWING THAT FOSTER-WHEELER NOW ACCEPTS THE "TEMPORARY" DOUBLER WINDOW REPAIR AS PERMANENT; OR (B) MAKING AN ACCEPTABLE PERMANENT REPAIR.
Condition: Unknown
Due 22 December 1987
Resolved 22 December 1987
Deck/Cargo
Issued 30 July 1987
Resolved
DETERMINE STATUS OF PLAN APPROVAL REQUIRED BY CG-835 ITEM #29 OF 13JUN87 (AIR COMPRESSOR INSTALLATION).
Condition: Unknown
Due 30 July 1987
Resolved 30 July 1987
Accommodation/Occupational Safety
Issued 22 June 1987
Resolved
REPAIR FIRE DAMPER #4-90-2.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Accommodation/Occupational Safety
Issued 22 June 1987
Resolved
SHORTEN WORN LEAD ON EVAP. SALINITY CELL.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Deck/Cargo
Issued 22 June 1987
Resolved
TEST O/S AND LOW L.O. TRIPS OF ALL CARGO PUMPS, GP PUMP AND BALLAST PUMP.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Engineering
Issued 22 June 1987
Resolved
DETERMINE STATUS OF PLAN APPROVAL PER CG-835 #29 OF 13 JUN 86 (AIR COMPR. INST.)
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Engineering
Issued 22 June 1987
Resolved
TEST RELIEF/SAFETY VALVES ON BOTH BOILERS, LP STEAM GENERATOR, PORTABLE WATER TANK, BOTH FEED PUMPS, DECK AIR TANK.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Deck/Cargo
Issued 22 June 1987
Resolved
DEMONSTRATE PROPER OPERATION OF IGS.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Electrical
Issued 22 June 1987
Resolved
TEST ALL EDG SHUT-OFFS AND TRIPS (LOW L.O., F.O. PRESS AND O/S) AFTER SOLENOID IS REPLACED.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Accommodation/Occupational Safety
Issued 22 June 1987
Resolved
PROVIDE LETTER SHOWING USCG APPROVAL OF MSD FOR USE ON INSPECTED VESSELS.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Engineering
Issued 22 June 1987
Resolved
REPAIR STARTING AIR CAGE ON DIESEL GENERATOR.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Engineering
Issued 22 June 1987
Resolved
REPAIR LUBE OIL LEAKS ON DIESEL AND TURBO GENERATORS.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Engineering
Issued 22 June 1987
Resolved
PROVIDE PRESSURE-TEMP RATING AND PLAN APPROVAL FOR NEW EXPANSION JOINTS IN FEED PUMP SUCTION LINES.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Construction/Loadline
Issued 22 June 1987
Resolved
ADJUST DOGS ON CONTROL ROOM ESCAPE TRUNK DOOR.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Engineering
Issued 22 June 1987
Resolved
REPAIR STEAM LEAK AT NIPPLE FOR BLOWDOWN LINE IN VICINITY OF STBD SIDE OF MAIN GEAR.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Fire Fighting
Issued 22 June 1987
Resolved
PROPERLY CONDUCT FIRE DRILL.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Lifesaving
Issued 22 June 1987
Resolved
PROPERLY CONDUCT BOAT DRILL.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Fire Fighting
Issued 22 June 1987
Resolved
REPAIR ENGINEROOM GENERAL ALARMS.
Condition: Unknown
Due 22 June 1987
Resolved 22 June 1987
Unknown
Issued 19 August 1986
Resolved
PROVIDE PERMANENT REPAIRS TO DETERIORATED AND BROKEN ELECTRICAL CONDUITS, CONNECTIONS AND JUNCTION BOXES SERVING COMMUNICATIONS AND TANKE GAUGING SYSTEMS AND TANK GAUGING SYSTEMS ON WEATHER DECK.
Condition: Unknown
Due 19 August 1986
Resolved 19 August 1986
Engineering
Issued 18 July 1986
Resolved
REPAIR LEAKING SUPERHEATER SAFETY VALVE ESCAPE PIPING ON STBD BOILER AND LEAKING PILOT SAFETY VALVE ESCAPE PIPING FLANGE ON PORT BOILER.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Construction/Loadline
Issued 18 July 1986
Resolved
MAKE PERMANENT (INSERT) REPAIRS TO FRACTURE IN WAY OF 3 PORT AND 3 STBD CARGO TANKS 3 FOOT FWD OF FR52.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
REPAIR FLUE GAS SAMPLING NOZZLE IN STBD BOILER.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
MAKE PERMANENT REPAIRS TO BOWED SUPERHEATER TUBEIN PORT BOILER AND REMOVE REPAIRS OF ALL PLUGGED TUBES.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
REMOVE PLUGGED SUPERHEATER TUBE IN STBD BOILER.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
CLEAN FIRE BOX AND FIRESIDE OF ALL TUBES IN BOTH BOILERS AND MAKE THEM AVAILABLE FOR USCG INSPECTION.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
REPAIR FRACTURED WELDS ART FWD END OF LP STEAM GENERATOR DRY PIPE WHERE ATTACHED TO SHELL USING QUALIFIED WELDERS AND APPROVED PROCEDURES.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
CLEAN ALL WATERSIDE TUBES IN BOTH BOILERS.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
CLEAN STEAM SIDE TUBES ON PORT BOILER.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Engineering
Issued 18 July 1986
Resolved
HYDROSTATICALLY TEST COMPOUND INJECTION TANK.
Condition: Unknown
Due 18 July 1986
Resolved 18 July 1986
Construction/Loadline
Issued 20 June 1986
Resolved
MAKE PERMANENT REPAIRS TO THE FRACTURE IN THE BOTTOM SHELL, APPROX. LOCATION, 3 FT. FWD. OF FRAME 52, IN WAY OF THE LONGITUDINAL BKHD. BETWEEN #3P AND #3C CARGO TANKS. REPAIRS ARE TO BE MADE TO THE SATISFACTION OF THE COGNIZANT O.C.M.I.
Condition: Unknown
Due 20 June 1986
Resolved 20 June 1986
Construction/Loadline
Issued 15 March 1986
Resolved
MAKE PERMANENT REPAIRS TO THE FRACTURE AT FRAME 31, LONGITUDENAL 43 IN WAY OF #1STBD CARGO TANK. ULLAGE IS NOT BE LESS THAN 34FT UNTIL REPAIRS ARE MADE.
Condition: Unknown
Due 15 March 1986
Resolved 15 March 1986
Electrical
Issued 7 June 1985
Resolved
REPAIR DIESEL GENERATOR START SYSTEM SO IT WILL START FROM THE CONTROL COUNSEL WHEN WARM.
Condition: Unknown
Due 7 June 1985
Resolved 7 June 1985
Electrical
Issued 7 June 1985
Resolved
ON EMERGENCY GENERATOR REPLACE CRACKED HYDRAULIC STARTING PUMP AND PROVE PROVE PROPER OPERATION.
Condition: Unknown
Due 7 June 1985
Resolved 7 June 1985
Engineering
Issued 7 June 1985
Resolved
REPAIR LUBE OIL LEAK ON THE AFT LOW PRESSURE TURBINE BEARING. THIS ITEM ISTO BE COMPLETED AT DRYDOCK BUT NO LATER THAN COMPLIANCE DATE.
Condition: Unknown
Due 7 June 1985
Resolved 7 June 1985
Lifesaving
Issued 16 May 1985
Resolved
REPLACE THE FORWARD INFLATABLE LIFERAFT.
Condition: Unknown
Due 16 May 1985
Resolved 16 May 1985
Lifesaving
Issued 16 May 1985
Resolved
REPLACE THE HYDRAULIC RELEASE ON EACH OF THE INFLATABLE LIFERAFTS.
Condition: Unknown
Due 16 May 1985
Resolved 16 May 1985