Records from 2016 to 2026. Most recent: inspection, 14 July 2026.
Inspection history · 24
14 July 2026
Annual Inspection
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 8433985
13 June 2026
Administrative Inspection
Administrative · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 8403830
16 June 2025
COI Inspection
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 8148239
27 August 2024
Annual Inspection
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 8004882
11 April 2024
Hull Examination
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7893798
26 July 2023
Annual Inspection · Deficiency Check
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7770370
25 August 2022
Annual Inspection
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7546231
22 August 2022
Damage Survey
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7541766
20 January 2022
Hull Examination
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7382844
26 August 2021
Administrative Inspection
Administrative · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7297460
19 August 2021
Type not recorded
No type recorded · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7294396
18 August 2021
Damage Survey
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7317334
17 August 2021
Annual Inspection
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7285039
16 June 2021
Deficiency Check
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7239712
18 August 2020
In-Service Inspection
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 7037547
16 June 2020
COI Inspection
Physical examination · Sector Northern Great Lakes · USCG Great Lakes District (CGD-GL) · Activity 6977993
22 January 2020
Examination of Repairs · Internal Structural Exam · Administrative Inspection · Drydock Exam · Hull Examination
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 6893721
19 September 2019
Administrative Inspection · Annual Inspection
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 6815529
27 August 2018
Deficiency Check · Administrative Inspection · Annual Inspection
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 6523994
27 February 2018
Administrative Inspection · Hull Examination · Drydock Exam · Examination of Repairs
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 6362352
22 August 2017
Administrative Inspection · Annual Inspection · Deficiency Check
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 6247628
22 December 2016
Administrative Inspection · Examination of Repairs
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 6061828
1 July 2016
Deficiency Check · Annual Inspection · Administrative Inspection
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 5925614
11 February 2016
Examination of Repairs · Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Unit Portsmouth · USCG Northeast District (CGD-NE) · Activity 5813313
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 27 August 2024
Resolved
Battery in float light needs to be changed.
Action required: 10 - Deficiency Rectified
Due 18 September 2024
Resolved 18 September 2024
09 - Working and Living Conditions › 092 - Working Conditions › Structural features (ship)
Issued 27 August 2024
Resolved
Ladder going down into forepeak need to be secured.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 September 2024
Resolved 17 October 2024
09 - Working and Living Conditions › 092 - Working Conditions › Ventilation (Working spaces)
Issued 27 August 2024
Resolved
Repair baffles on engine room ventilation.
Action required: 10 - Deficiency Rectified
Due 18 September 2024
Resolved 18 September 2024
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 27 August 2024
Resolved
Secure gaps around piping going through engine room space.
Action required: 10 - Deficiency Rectified
Due 18 September 2024
Resolved 18 September 2024
11 - Life Saving Appliances › N/A - No Subsystem › Launching arrangements for survival craft
Issued 27 August 2024
Resolved
Hydro-static releases on IBA's are expired.
Action required: 10 - Deficiency Rectified
Due 18 September 2024
Resolved 18 September 2024
05 - Radio Communications › N/A - No Subsystem › Other (radio communication)
Issued 26 July 2023
Resolved
Vessel did not have current Great Lakes Radio Agreement.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 13 September 2023
10 - Safety of Navigation › N/A - No Subsystem › Magnetic compass
Issued 26 July 2023
Resolved
Found the magnetic compass cloudy making the numbers illegible.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 13 September 2023
09 - Working and Living Conditions › 092 - Working Conditions › Safe means of access Deck - hold/tank, etc.
Issued 26 July 2023
Resolved
The ladder in the forepeak needs to be secured to the bulkhead. Currently it is just leaning in the space.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 13 September 2023
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 26 July 2023
Resolved
Found two life jackets not labeled with the vessel name. Found labels for storage bags showing incorrect quantity.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 26 July 2023
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 26 July 2023
Resolved
Found Float Light Battery in need of replacement.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 13 September 2023
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of liferafts
Issued 26 July 2023
Resolved
Found hydrostatic releases on the IBAs not attached correctly.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 26 July 2023
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 26 July 2023
Resolved
Water heater wiring needs to be made permanent.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 13 September 2023
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 26 July 2023
Resolved
Found hydraulic fluid in the forepeak from return line being pumped into a 5 gallon bucket. Directed them to plumb the return line to dump back into tank.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 4 August 2023
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 26 July 2023
Resolved
Found numerous old light fixtures in machinery spaces that need covers or to be removed.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2023
Resolved 13 September 2023
01 - Certificates & Documentation › 011 - Ships Certificates › USCG Certificate of Documentation (COD)
Issued 25 August 2022
Resolved
No current COD onboard.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 September 2022
Resolved 12 September 2022
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 25 August 2022
Resolved
First aid kit needs to be in compliance with 46 CFR 160.041-4(b).
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 September 2022
Resolved 12 September 2022
10 - Safety of Navigation › N/A - No Subsystem › Electronic charts (ECDIS)
Issued 25 August 2022
Resolved
Electronic charts and plotter software need to be updated.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 September 2022
Resolved 12 September 2022
09 - Working and Living Conditions › 092 - Working Conditions › Cleanliness of engine room
Issued 25 August 2022
Resolved
Found debris in the bilges including oil soaked absorbent pads.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 September 2022
Resolved 12 September 2022
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 25 August 2022
Resolved
Junction box behind bar needs to be capped.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 September 2022
Resolved 12 September 2022
09 - Working and Living Conditions › 092 - Working Conditions › Cleanliness of engine room
Issued 25 August 2022
Resolved
Found excess hydraulic fluid in the forepeak. Not sure if is residual from the install of the bow thruster or a leak. Directed owner to clean and remove and then monitor.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 September 2022
Resolved 12 September 2022
09 - Working and Living Conditions › 091 - Living Conditions › Furnishings
Issued 25 August 2022
Resolved
Found two bench seats that need to be secured. Directed owner no pax in those seats until corrected.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 September 2022
Resolved 12 September 2022
02 - Structural Conditions › N/A - No Subsystem › Hull - cracking
Issued 26 August 2021
Resolved
Vessel may not operate until satisfactory repairs have been made to make the vessel seaworthy and ensure vessel is not a pollution hazard.
Action required: 60 - Rectify deficiencies prior to movement
Due 26 August 2021
Resolved 10 May 2022
Resolution: Corrected.
02 - Structural Conditions › N/A - No Subsystem › Steering gear
Issued 18 August 2021
Resolved
Remove rudder and examine securing devices, connections, rudder post, and packing for damage. Ensure the proper operation of a fully functional steering system prior to movement to the satisfaction of the attending Coast Guard Marine Inspector.
Action required: 60 - Rectify deficiencies prior to movement
Due 18 August 2021
Resolved 10 May 2022
Resolution: Corrected.
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 18 August 2021
Resolved
Investigate extent of damage to the hull at the keel. Make necessary repairs to ensure the seaworthiness of the vessel prior to movement to the satisfaction of the attending Coast Guard Marine Inspector.
Action required: 60 - Rectify deficiencies prior to movement
Due 18 August 2021
Resolved 10 May 2022
Resolution: Corrected.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 18 August 2021
Resolved
Remove damaged propeller and shaft, inspect all associated gear for damage. Make all necessary repairs or replacements affecting the vessel's running gear prior to movement to the satisfaction of the attending Coast Guard Marine Inspector.
Action required: 60 - Rectify deficiencies prior to movement
Due 18 August 2021
Resolved 10 May 2022
Resolution: Corrected.
02 - Structural Conditions › N/A - No Subsystem › Ballast, fuel and other tanks
Issued 18 August 2021
Resolved
Investigate fuel leak on port independent fuel tank. Secure/remove source of leak. Make permanent repairs to tank/ eliminate possible pollution scenario prior to movement to the satisfaction of the attending Coast Guard Marine Inspector.
Action required: 60 - Rectify deficiencies prior to movement
Due 18 August 2021
Resolved 28 June 2022
Resolution: corrected
10 - Safety of Navigation › N/A - No Subsystem › Electronic charts (ECDIS)
Issued 18 August 2021
Resolved
Make necessary updates and repairs to onboard navigational equipment. Apply electronic chart and software updates to chart-plotter and ensure vessel's depth-sounder is functioning properly prior to the carriage of passengers, to the satisfaction of the attending Coast Guard Marine Inspector.
Action required: 701 - Prior to carriage of passengers/cargo
Due 18 August 2021
Resolved 10 May 2022
Resolution: Corrected.
02 - Structural Conditions › N/A - No Subsystem › Decks - cracking
Issued 18 August 2021
Resolved
Inspect/repair numerous cracked welds and missing/sheared off hardware on the aft swim platform that is utilized as the vessel's primary MOB recovery platform prior to the carriage of passengers, to the satisfaction of the attending Coast Guard Marine Inspector.
Action required: 701 - Prior to carriage of passengers/cargo
Due 18 August 2021
Resolved 10 May 2022
Resolution: Corrected.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 17 August 2021
Resolved
Vessel did not have required FIRE BUCKETS onboard.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 September 2021
Resolved 10 May 2022
Resolution: Corrected.
10 - Safety of Navigation › N/A - No Subsystem › Other (navigation)
Issued 17 August 2021
Resolved
Vessel needs the name displayed on both sides of the forward half of the vessel.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 September 2021
Resolved 28 June 2022
Resolution: corrected
07 - Fire Safety › N/A - No Subsystem › Remote Means of control (opening,pumps,ventilation,etc.) Machinery spaces
Issued 17 August 2021
Resolved
Fuel shut off valves need to be re-labeled.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 September 2021
Resolved 28 June 2022
Resolution: corrected
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 17 August 2021
Resolved
Numerous items expired in the First Aid Kit.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 18 September 2021
Resolved 28 June 2022
Resolution: corrected
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 16 June 2020
Resolved
Vessel's bow thruster was not operational. Effect necessary repairs to bow thruster to the satisfaction of the attending Coast Guard Marine Inspector.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 July 2020
Resolved 13 July 2020
Resolution: Corrected.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 27 August 2018
Resolved
Several lifejackets need the retro-reflective tape replace.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 10 September 2018
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 27 August 2018
Resolved
The F/O return hose on the generator prime mover is too large and cannot be tightened to fit; repair or replace as needed.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 10 September 2018
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 22 August 2017
Resolved
Provide the manufacturer recommended battery for the water light.
Due 5 September 2017
Resolved 24 August 2017
Fire Fighting › Structural Fire Protection - General › Hull Construction
Issued 1 July 2016
Resolved
Engine compartment is not gas tight - properly mount all plywood to sides and fore/aft end of compartment. Provide means to adequately seal off area around exhaust and shaft penetration.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 July 2016
Fire Fighting › Structural Fire Protection - General › Accommodation Space Protection
Issued 1 July 2016
Resolved
Ensure all sides and top of engine compartment are covered with fire protective insulation.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 July 2016
Documentation › Logs/Records › Logbook/Record (unofficial)
Issued 1 July 2016
Resolved
Provide vessel log for training, drills, and fire equipment maintenance.
Due 1 August 2016
Resolved 14 July 2016
Operations/Management › Drills/Instruction › Man Overboard Recovery
Issued 1 July 2016
Resolved
Conduct man overboard and fire drill in the presence of a marine inspector.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 July 2016
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 1 July 2016
Resolved
Troubleshoot and repair short to nav lights.
Due 1 August 2016
Resolved 14 July 2016
Fire Fighting › Remote Fuel Shutoff › General
Issued 1 July 2016
Resolved
Install adequate shut off valve for generator fuel supply.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 July 2016
Engineering › Fuel Oil Service System › Hose
Issued 1 July 2016
Resolved
Replace generator fuel return hose with "USCG TYPE A1" hose - max length 30".
Due 1 August 2016
Resolved 14 July 2016
Engineering › Diesel Engine (auxiliary) › Piping (exhaust)
Issued 1 July 2016
Resolved
Install double hose clamps on generator muffler.
Due 1 August 2016
Resolved 14 July 2016
Electrical › Electric Supply System (service) › Battery Installation
Issued 1 July 2016
Resolved
Replace wing nuts on generator battery with mechanical fasteners.
Due 1 August 2016
Resolved 14 July 2016
Engineering › Bilge Water Management System › Pump
Issued 1 July 2016
Resolved
Replace non UL approved forepeak bilge pump with UL approved pump.
Due 1 August 2016
Resolved 14 July 2016
Construction/Loadline › Markings › Vessel Name/Home Port
Issued 1 July 2016
Resolved
Properly post hull markings to include name and hailing port.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 14 July 2016
Stability › Watertight Integrity › Watertight Subdivision Standard
Issued 1 July 2016
Resolved
Adjust all watertight hatches.
Due 1 August 2016
Resolved 14 July 2016
Lifesaving › Lifebuoys › Markings (ship name/port)
Issued 1 July 2016
Resolved
Label ringbuoy with vessel name.
Due 1 August 2016
Resolved 14 July 2016
Electrical › Electrical Distribution System (service) › Wiring
Issued 1 July 2016
Resolved
Remove all extension cords and aplitters that are installed as "permenant".
Due 1 August 2016
Resolved 14 July 2016
Electrical › Electrical Distribution System (service) › Cable
Issued 1 July 2016
Resolved
Properly terminate dead end cable in lazarette.
Due 1 August 2016
Resolved 14 July 2016
Construction/Loadline › Hull › Hull Plating
Issued 1 July 2016
Resolved
Properly cover pinholes in fuel tank void IWO generator exhaust.
Due 1 August 2016
Resolved 14 July 2016
Engineering › Sea-water System (primary cooling) › Valve
Issued 1 July 2016
Resolved
Provide valve handle for raw water cooling through hull valve - locted in fuel tank space.
Due 1 August 2016
Resolved 14 July 2016
Fire Fighting › Ventilation Systems › Ducts
Issued 1 July 2016
Resolved
Replace non-rigid machinery space ducting with rigid ducting for both supply and return ducts.
Due 1 August 2016
Resolved 14 July 2016