Documentation record
Registered dimensions (L × B × D)26.0 ft × 10.0 ft × 5.0 ft
Registered tonnagegross 8 / net 6
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderCROSBY YACHT YARD INC · OSTERVILLE, MA, UNITED STATES · built 1999
Hull materialFRP (Fiberglass)
PropulsionDiesel Reduction
Hull shapeShip
Hull configurationMonohull
Hailing portPUT IN BAY, OH
Trade endorsementsCoastwise, unrestricted, Registry
DocumentationValid · issued 13 May 2026 · expires 30 June 2027
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it6 - Simplified, Net Ton
8 - Simplified, Gross Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 29
16 July 2025
Administrative Inspection
Administrative · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 8187119
26 September 2024
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 8019746
4 October 2023
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 7958837
8 September 2022
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 7555132
5 October 2021
COI Inspection · Internal Structural Exam · Hull Examination
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 7345237
6 May 2021
Drydock Exam · Hull Examination · Internal Structural Exam · Annual Inspection · Deficiency Check
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 7187863
17 June 2020
Annual Inspection · DAPI Audit
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 6980810
14 June 2019
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 6716360
15 June 2018
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 6445787
1 June 2017
COI Inspection · DAPI Audit
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 6162088
4 May 2016
DAPI Audit · Internal Structural Exam · Drydock Exam · Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 5872329
5 August 2015
Annual Inspection · DAPI Audit
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 5205054
4 June 2014
Annual Inspection · DAPI Audit
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 4856293
29 May 2012
Administrative Inspection · Simplified Stability Test · COI Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 4326662
28 October 2010
Hull Examination · Internal Structural Exam
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 3879985
4 June 2008
Annual Inspection · DAPI Audit
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 3189119
4 June 2007
COI Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 2951368
10 January 2007
Deficiency Check
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 2853740
26 October 2006
Hull Examination
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 2808304
30 May 2006
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 2664115
8 June 2005
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 2383943
8 October 2004
Hull Examination
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 2216703
2 June 2004
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 2084904
9 June 2003
Annual Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 1813263
15 May 2002
COI Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 1617535
9 May 2001
Re-Inspection
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 1362211
3 May 2000
Re-Inspection · Initial Construction-Excluding Oversight
Physical examination · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 1468573
2 July 1999
Administrative
Administrative · Marine Safety Unit Toledo · USCG Great Lakes District (CGD-GL) · Activity 781165
29 June 1999
Initial Certification
Physical examination · MSO PROVIDENCE · USCG Northeast District (CGD-NE) · Activity 1125796
02 - Structural Conditions › N/A - No Subsystem › Beams, frames, floors-op. damage
Issued 6 May 2021
Resolved
Mid-ship frame fiberglass cracked on port side, Internal plywood is rotted from water intrusion from cracked fiberglass. Owner/Operator has 45 days to repair the vessel frame. Owner must notify USCG Marine Inspector once frame is cropped out to view internals prior to replacing the frame.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 21 June 2021
Resolved 29 June 2021
Resolution: Proper repairs made to the satisfaction of the attending MI.
Engineering › Freshwater System (jacketwater cooling) › Hose
Issued 4 June 2014
Resolved
The raw water suction intake hose is deteriorated. Replace hose. This requirement must be completed to the satisfaction of a USCG Marine Inspector prior to carrying passengers (46CFR182.720).
Action required: 701 - Prior to carriage of passengers/cargo
Due 4 June 2014
Resolved 4 June 2014
Resolution: Rcvd invoice for new hose and photo confirmation of repairs.
Engineering › Shafting/Propeller Arrangements › Bearing
Issued 26 October 2006
Resolved
Replace damaged cutlas bearing prior to operating vessel for summer 2007
Action required: 705 - Other - as specified
Due 1 April 2007
Resolved 10 January 2007
Resolution: Vessels reps sent fax on the purchase and replacement, and the engine alignment spec''s.
Communications › Radio Communications › VHF Radiotelephone
Issued 2 June 2004
Resolved
Post radio procedures.
Due 2 July 2004
Resolved 15 June 2004
Engineering › Fuel Oil Service System › Valve
Issued 2 June 2004
Resolved
Label emergency fuel shutoff valve.
Due 2 July 2004
Resolved 15 June 2004
Engineering › Fuel Oil Service System › Valve
Issued 2 June 2004
Resolved
Install engine fuel shutoff valve.
Due 2 July 2004
Resolved 15 June 2004
Engineering › Bilge Water Management System › Pump
Issued 2 June 2004
Resolved
Install U/L approved bilge pump.
Action required: 701 - Prior to carriage of passengers/cargo
Due 2 June 2004
Resolved 15 June 2004