Records from 2007 to 2026. Most recent: inspection, 19 May 2026.
Inspection history · 21
19 May 2026
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8327437
19 May 2025
Annual Inspection · Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8088332
11 December 2024
In-Service Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8043721
16 September 2024
Plan Review "T" Boat
Administrative · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8007737
15 May 2024
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7859903
11 October 2023
Hull Examination
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7733581
16 May 2023
COI Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7640512
16 May 2023
In-Service Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7675563
25 May 2022
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7403515
27 October 2021
Hull Examination · Examination of Repairs
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7341651
17 May 2021
Deficiency Check · Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7199697
5 October 2020
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7071956
20 August 2019
Administrative Inspection · Hull Examination · Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6789729
25 July 2019
Administrative Inspection · Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6763029
25 July 2019
Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6763091
25 June 2019
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6673679
15 May 2018
Administrative Inspection · COI Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6414949
23 October 2017
Hull Examination
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6242461
6 June 2017
Annual Inspection · DAPI Audit
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6131545
31 October 2016
Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6033498
24 March 2016
Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 5829189
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 19 May 2026
Resolved
On a vessel of not more than 65 feet in length carrying more than 49 passengers, each hose must have fittings of brass or other suitable corrosion resistant materials that comply with NFPA 1963. MI observed vessel with plastic firefighting nozzles. Replace current plastic nozzle with brass, bronze or corrosion resistant materials complying with NFPA standards.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 2 June 2026
Resolved 28 May 2026
Resolution: Operator provided imagery with appropriate corrosion resistant nozzles installed.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 19 May 2026
Resolved
On a vessel of not more than 65 feet in length carrying more than 49 passengers each hose must be lined commercial fire hose that conforms to UL 19. MI observed fire hose was not UL 19 rated. Replace existing firehose with UL 19 rated hose.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 2 June 2026
Resolved 28 May 2026
Resolution: Operator provided receipt of purchase and imagery of appropriate UL 19 rated fire hoses installed.
10 - Safety of Navigation › N/A - No Subsystem › Nautical publications
Issued 19 May 2026
Resolved
As appropriate for the intended voyage, a vessel must carry adequate and up-to-date, U.S. Coast Pilot [name withheld] List. MI observed vessel's Coast Pilot and Light Listed have not been updated since 2020, and 2021 respectively. Replace required nautical publications with up-to-date versions.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 2 June 2026
Resolved 28 May 2026
Resolution: Operator provided imagery of up-to-date required nautical publications.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 19 May 2025
Resolved
A vessel must have one or more ring life buoys be orange in color. Marine Inspector observed life ring faded beyond orange color.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 2 June 2025
Resolved 22 May 2025
Resolution: Recieved picture-owner purchased new life rings
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 19 May 2025
Resolved
At each inspection for certification and at every other vessel inspection all observed unsafe practices, fire hazards, and other hazardous situations must be corrected and all required guards and protective devices must be in satisfactory condition. Marine Inspector observed no guard protection on rotating shafts.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 2 June 2025
Resolved 22 May 2025
Resolution: Owner manufactured wooden machinery guards
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 19 May 2025
Resolved
On a vessel of not more than 19.8 meters (65 feet) in length carrying more than 49 passengers, and on a vessel of more than 19.8 meters (65 feet) in length, the minimum capacity of the fire pump must be 189 liters (50 gallons) per minute at a pressure of not less than 414 kPa (60 psi) at the pump outlet. The pump outlet must be fitted with a pressure gauge Marine Inspector observed fire pump gauge was inop.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 2 June 2025
Resolved 22 May 2025
Resolution: Owner purchased new gauge.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 15 May 2024
Resolved
Marine Inspector observed one electric bilge pump was inoperable to to being disconnected from power.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 May 2024
Resolved 28 May 2024
Resolution: Def cleared
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 15 May 2024
Resolved
Marine Inspector observed no oil pollution placard posted.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 May 2024
Resolved 28 May 2024
Resolution: Def cleared
09 - Working and Living Conditions › 091 - Living Conditions › Water, pipes, tanks
Issued 15 May 2024
Resolved
Marine Inspector observed significant patching on the aluminum sewage tank.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 May 2024
Resolved 28 May 2024
Resolution: Def cleared
18 - Maritime Labour Convention (Not Applicable to PSC Exams conducted in the U.S.) › N/A - No Subsystem › Protection machines/parts
Issued 25 May 2022
Resolved
46 CFR 177.960. An exposed hazard, such as gears or rotating machinery, must be properly protected by a cover, guard, or rail. MI Observed the vessel did no thave protective covers for both shafts and protective covers for both engines rotating belts/pulleys.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 June 2022
Resolved 1 June 2022
Resolution: Protective covers for both shafts and protective covers for both engines rotating belts/pulleys were installed
10 - Safety of Navigation › N/A - No Subsystem › Charts
Issued 25 May 2022
Resolved
§ 184.420 Charts and nautical publications.
(a) As appropriate for the intended voyage, a vessel must carry adequate and up-to-date:
(1) Charts of large enough scale to make safe navigation possible
MI Observed vessel didnot have up-to-date charts for appropriate intended voyage.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 June 2022
Resolved 1 June 2022
Resolution: Charts provide
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 25 May 2022
Resolved
46 CFR 180.70 Ring life buoys: A vessel must have one or more ring life buoys as follows:(c) At least one ring life buoy must be fitted with a lifeline. If more than one ring life buoy is carried, at least one must not have a lifeline attached. Each lifeline on a ring life buoy must:
(1) Be buoyant;
(2) Be of at least 18.3 meters (60 feet) in length;
(3) Be non-kinking;
(4) Have a diameter of at least 7.9 millimeters ( 5/16 inch);
(5) Have a breaking strength of at least 5 kilonewtons (1,124 pounds); and
(6) Be of a dark color if synthetic, or of a type certified to be resistant to deterioration from ultraviolet light.
MI observed the vessel did not have a 60ft of life line for assigned life bouy.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 June 2022
Resolved 1 June 2022
Resolution: Life line 60ft is on board.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 17 May 2021
Resolved
At each initial and subsequent inspection for certification the marine inspector shall examine and test the main and auxiliary steering apparatus to the extent necessary to determine that its condition is satisfactory and that it is fit for the service intended. Portside steering ram mount is fractured. Vessel is to repair steering mount to the satisfaction of the attending marine inspector.
46CFR176.25-35
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 18 May 2021
Resolution: The vessels completed repair to steering system. MI witnessed steering test. All Satisfactory.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 25 July 2019
Resolved
Vessel experienced partial loss of propulsion to stbd engine. Vessel must be provided with an auxiliary means of steering. Vessel must prove proper operation of propulsion and steering systems.
Action required: 701 - Prior to carriage of passengers/cargo
Due 25 July 2019
Resolved 26 July 2019
Resolution: Deficiency rectified, to the satisfaction of the attending Marine Inspector, during damage survey.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 25 June 2019
Resolved
#3 void and lazerette hatches were unable to secure properly and create a watertight seal.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 25 June 2019
Resolved 25 June 2019
Resolution: Crew member fixed both arms to secured the hatches and was able to make them watertight.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 25 June 2019
Resolved
Line between life floats and life float water lights were deteriorated and unserviceable.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 25 June 2019
Resolved 25 June 2019
Resolution: crew newed line on all.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 15 May 2018
Resolved
Conduct a Satisfactory renewal Certificate of Inspection.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 17 May 2018
Resolved 17 May 2018
Resolution: Conducted satisfactory COI Inspection
Pollution Prevention/Response › Prevention Equipment › Marine Sanitation Device, Type III
Issued 23 October 2017
Resolved
Replace STBD Flex hose on MSD Tank.
Action required: 705 - Other - as specified
Resolved 13 November 2017
Resolution: Owner replace flex hose on MSD tank.
Construction/Loadline › Hull › Longitudinal Frame
Issued 23 October 2017
Resolved
Treat wood on floor aft of the STBD engine.
Action required: 705 - Other - as specified
Resolved 13 November 2017
Resolution: Owner cleaned affect area and treated to prevent further decay.
Engineering › Diesel Engine (propulsion-reduction gear) › Exhaust Manifold
Issued 23 October 2017
Resolved
Repair port MDE exhaust leak and clean and treat wood in surrounding area.
Action required: 705 - Other - as specified
Resolved 13 November 2017
Resolution: Owner fixed exhaust leak and cleaned and treated wood in the surrounding area.
Engineering › Fuel Oil Service System › Piping
Issued 23 October 2017
Resolved
Replace identified hydraulic line on starboard generator.
Action required: 705 - Other - as specified
Resolved 13 November 2017
Resolution: Owner replaced hydralic line making it leak free.
Accommodation/Occupational Safety › Occupational Safety › Deck Rail
Issued 23 October 2017
Resolved
Make permanent repoairs to topside ladder rail and ensure it can withstand a point load of 200 pound and uniform load of 50 pounds per foot.
Condition: Improper Installation
Action required: 705 - Other - as specified
Resolved 13 November 2017
Resolution: Owner welded on rails that are IAW the regulations as opposed to the taped on rails that were there before.
Accommodation/Occupational Safety › Occupational Safety › Deck Rail
Issued 23 October 2017
Resolved
Repair identified railing weak points and tighten connections.
Action required: 705 - Other - as specified
Resolved 13 November 2017
Resolution: Owner tighted all connection points for deck railing around the ship and also added backing plates to areas identified as weak connection points.
Construction/Loadline › Penetrations › Valve Flange
Issued 23 October 2017
Resolved
Replace 02 identified ball valves.
Action required: 705 - Other - as specified
Resolved 13 November 2017
Resolution: Owner replaced the two identified ball valves with new ones.
Navigation › Piloting/Steering › Marine Charts
Issued 6 June 2017
Resolved
Provide current marine charts for navigation.
Action required: 705 - Other - as specified
Due 6 June 2017
Resolved 6 June 2017
Resolution: See narrative
Lifesaving › Lifefloat › Painter
Issued 6 June 2017
Resolved
Provide two 100FT replacement painter lines for vessel's lifefloats.
Action required: 705 - Other - as specified
Due 6 June 2017
Resolved 6 June 2017
Resolution: See Narrative
Lifesaving › Lifefloat › Lifeline
Issued 24 March 2016
Resolved
Replace line connecting the float light to the life float in accordance with 46 CFR 160.010-8
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 28 April 2016
Resolved 25 April 2016
Lifesaving › Lifefloat › Platform
Issued 24 March 2016
Resolved
Provide seperations for life floats as per 46 CFR 180.137(f)
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 28 April 2016
Resolved 25 April 2016
Lifesaving › Lifejacket/PFD (General) › Marking
Issued 24 March 2016
Resolved
Properly mark life jacket storage as per 46 CFR 185.604(b)
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 28 April 2016
Resolved 25 April 2016