Inspection history · 84
19 October 2017
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6291162
5 July 2017
Administrative Inspection · Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6197813
21 June 2017
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6182697
5 July 2016
Annual Inspection · MTSA Verification · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5935528
15 June 2015
Periodic Inspection · Administrative Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5155800
27 April 2015
Examination of Repairs · Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 5111890
23 March 2015
Type not recorded
No type recorded · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 5089426
23 March 2015
Permit to Proceed · Damage Survey
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 5099622
16 June 2014
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4941616
24 July 2013
Internal Structural Exam · Administrative Inspection · COI Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4663187
28 December 2012
Examination of Repairs · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4507786
16 November 2012
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4485178
6 March 2012
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4331716
27 December 2011
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4214343
16 August 2011
Deficiency Check
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 4117591
19 July 2011
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4086971
7 June 2011
Examination of Repairs
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 4037689
12 August 2010
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3821926
6 August 2010
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3816650
7 May 2010
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3733134
13 April 2010
Periodic Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3716560
4 September 2009
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3585030
6 April 2009
Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3533531
14 May 2008
Drydock Exam · MTSA Verification · COI Inspection · Internal Structural Exam · Cargo Tank Internal
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3206098
22 January 2008
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3153767
10 December 2007
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3112580
5 December 2007
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3110019
4 December 2007
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3109066
3 May 2007
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2921482
16 April 2007
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2908570
9 April 2007
Deficiency Check
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2904537
24 February 2007
Damage Survey · Permit to Proceed
Physical examination · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 2878031
14 January 2007
Damage Survey · Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2857349
10 January 2007
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2853593
9 January 2007
Periodic Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2863570
22 November 2006
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2827073
29 October 2006
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2813225
12 June 2006
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2677602
27 March 2006
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2610188
27 February 2006
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2610564
22 June 2005
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2398853
3 March 2005
COI Inspection · MTSA Verification
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2303254
29 November 2004
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2244470
12 February 2004
Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2027405
24 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1986376
7 August 2003
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1869549
20 February 2003
Damage Survey · Examination of Repairs · Periodic Inspection · Internal Structural Exam
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1732898
18 November 2002
Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1707215
29 October 2002
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1704905
13 February 2002
Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1495688
8 February 2002
Damage Survey
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1485091
20 October 2001
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 460170
13 February 2001
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1057949
8 November 2000
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 93044
8 November 2000
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 122720
6 March 2000
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1047438
21 May 1999
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 801789
24 April 1998
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1414991
7 May 1997
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1101607
24 February 1997
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1096310
15 January 1997
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 45179
15 January 1997
Permit to Proceed · Damage Survey
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1434506
19 April 1996
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1088108
14 June 1995
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1187897
2 May 1994
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 858273
17 June 1993
Hull Examination · COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1134991
1 October 1992
Type not recorded
No type recorded · MSO Mobile · USCG Heartland District (CGD-H) · Activity 457434
7 May 1992
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 642283
30 April 1992
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 169892
1 April 1992
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 962897
21 June 1991
Hull Examination · Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 908617
25 January 1991
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 520132
9 May 1990
COI Inspection
Physical examination · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 899416
7 November 1989
Administrative
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1029296
6 November 1989
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 514674
14 August 1989
Re-Inspection
Physical examination · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 1348672
10 May 1988
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1195547
17 June 1987
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1017240
25 June 1986
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 990503
2 July 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 986033
15 June 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1280356
3 June 1984
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 973128
27 July 1983
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1273171
22 June 1981
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1276903
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 21 June 2017
Resolved
MIs received notification of a leak on the #1 port cargo tank at the seam where the cargo tank side meets the walking deck. Vessel is authorized to transit to fleeting area as per approved transit plan. Vessel then authorized one time discharge of cargo and is to clean/gas free space for inspection. Make permanent repairs to the satisfaction of the attending marine inspector.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 21 July 2017
Resolved 19 October 2017
Resolution: Vessel owner/operator opted to surrender COI and CAA vice make appropriate repairs to cargo tank seepage issue. Special note created for this vessl.
Deck/Cargo › Cargo Stowage › General
Issued 23 March 2015
Resolved
After off load of cargo and prior to loading next cargo the fracture on the STBD side of #1 cargo tank must be repaired to the satisfaction of the Cogn OCMI.
Condition: Invalid
Action required: 705 - Other - as specified
Due 30 May 2015
Resolved 1 May 2015
Resolution: O/O cropped and renewed section of plate on the raised trunk.
Construction/Loadline › Hull › Hull Plating
Issued 16 November 2012
Resolved
TBSIP Self reported def. Make permenant repairs to 1" X 1/16" fracture in the #3 starboard wing tank, 12 foot back aft of forward hatch, at the 7 foot draft mark.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 28 December 2012
Resolved 27 December 2012
Resolution: affected repairs as per narrative to the satisfaction of [name withheld].
Construction/Loadline › Hull › Side Shell
Issued 27 December 2011
Resolved
Fracture in # 3 stbd gunwale
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 27 December 2011
Resolved 27 December 2011
Resolution: Croped and renewed (1) 4'' x 4'' x 3/8" peice of gunwale plat
Construction/Loadline › Hull › Side Shell
Issued 19 July 2011
Resolved
D8 TBSIP SELF-REPORTED DEFICIENCY. Make permanent repairs to 1" x 1/2" fracture in the #3 Stbd wing tank at fwd hatch in the corner where the bulkhead seperates the #2 and 3 void meets the sideshell, 12" down from the gunner.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 25 August 2011
Resolved 16 August 2011
Resolution: Examined welds and witnessed satisfactory air test of a 4'' x 2.5'' x 3/8" section of deck gunnel from the #2 stbd into the #3 stbd wing void.
Construction/Loadline › Hull › Hull Plating
Issued 6 August 2010
Resolved
3" X 1/8" FRACTURE #3 P W/T @ AFT HATCH 5' OFF BOTTOM. INSTALLED SHINGLES & EPOXY PATCH. [Minor Damage and [name withheld] reported 05AUG2010 by Kirby Inland Marine under the D8 Tank Barge Streamlined Inspection Program (TBSIP)].
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 19 September 2010
Resolved 12 August 2010
Resolution: Examined welds and witnessed satisfactory air test of 5'' x 10'' x 3/8” side shell insert to the #3 port wing void.
Deck/Cargo › Cargo Stowage › General
Issued 4 September 2009
Resolved
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Resolved 4 September 2009
Resolution: Conducted repair check. Examined welds and witnessed satisfactory air tested welds of 18"x18"x3/8" section of cargo tank top in way of #1stbd C/T and 18"x18"x3/8" section of cargo tank flanged raised trunk in way of #1stbd C/T
Deck/Cargo › Cargo Stowage › General
Issued 5 December 2007
Resolved
The vessel has a pinhole leak on #3 stbd cargo tank at the walking deck.
Action required: 701 - Prior to carriage of passengers/cargo
Due 7 December 2007
Resolved 10 December 2007
Resolution: Conducted repair check. Examined welds and witnessed satisfactory air test of 3'' x 3'' x 3/8" cargo tank insert to #3 stbd cargo tank.
Construction/Loadline › Hull › Side Shell
Issued 16 April 2007
Resolved
1" FRCTR IN PORT SIDE STERN 6FT. AFT FROM FWRD BLKHD @ 3rd SIDELONG FROM BOTTOM APPROX. 6ft. DRFT. WILL INSTALL SHINGLE WITH EPOXY (SPLASHZONE) PATCH. AFTER DSCHRG WILL CLEAN AND REPAIR BARGE PERMANENTLY.
Due 30 May 2007
Resolved 7 May 2007
Resolution: Permanent repairs made.
Construction/Loadline › Hull › Hull Plating
Issued 24 February 2007
Resolved
Maintain suitable dewatering pumps on leaking bowrake while in transit. Make suitable temp repair to leak and make void available to CG Marine Inspector for examination prior to departing Huntington AOR.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 26 February 2007
Resolution: Suitable temp repair (shingling) conducted. PTP issued.
Construction/Loadline › Hull › Hull Plating
Issued 24 February 2007
Resolved
Make permanent repair to 13" fracture in starboard sideshell iwo first vertical frame aft of headlog prior to loading cargo.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Resolved 4 April 2007
Resolution: Permanent repair made to 13" fracture in stbd sideshell iwo first vertical frame aft of headlog prior to loading cargo.
Construction/Loadline › Hull › Bottom Plating
Issued 14 January 2007
Resolved
Found 10 inches of water inside the #3 wing void at the 2' 6" draft mark on the port side.
Condition: Unknown
Action required: 705 - Other - as specified
Due 14 January 2007
Resolved 23 January 2007
Resolution: Witnessed satisfactory repairs and air test of one 2''''x2''''x1/2" kuckle in the #3 port wing void.
Construction/Loadline › Hull › Longitudinal Frame
Issued 29 October 2006
Resolved
Vessel has 2, 2 inch fractures located on the #2 and #3 side chord on the 3rd side long. Temporary repairs consisting of wood shingles and splash zone were applied. Issued CG 835 requiring vessel to transit to Vopak DP to offload and then make permanent repairs.
Action required: 705 - Other - as specified
Due 29 November 2006
Resolved 23 November 2006
Resolution: Conducted repair check. Examined satisfactorily air tested welds of (1) 4''6" x 26'' x 3/8" side shell insert in the #1 port wing void, gouged and welded (1) 24" fracture and (1) 12" fracture in the port stern corner.
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 29 November 2004
Resolved
#2 & #3 cargo tank tops crushed from vaccum blockage.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 29 November 2004
Resolution: #3 cargo tank top renewed; #2 cargo tank top partially renewed. Repair summary on file.
Construction/Loadline › Hull › Bottom Plating
Issued 7 August 2003
Resolved
Port stern bilge knuckle crushed / fractured.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 7 August 2003
Resolution: 3'' x 4'' x 1/2" insert.
Construction/Loadline › Hull
Issued 9 January 2003
Resolved
Port and STBD gunwale wasted as per gauging report. LEGACY COMPONENT DESC: Hull Plating
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 30 January 2003
Resolved 23 January 2003
Resolution: Conducted repair and air test of the knuckle port side 105'' X 1/2" X 4; STBD #2 void 10'' X 1/2" X 4''), all sat. Non-credit DD is desired and a non-credit DD letter required.
Construction/Loadline › Hull
Issued 8 February 2002
Resolved
CROP AND RENEW 7 FOOT OF KNUCKLE ON THE STARBOARD BOW RAKE. LEGACY COMPONENT DESC: Hull Plating
Condition: Damaged By Earlier Event
Due 20 February 2002
Resolved 13 February 2002
Deck/Cargo
Issued 14 August 1989
Resolved
OVERHAUL THE PRESSURE-VACUUM VALVE ON THE #3 CARGO TANK PRIOR TO LOADING NEXT CARGO.
Condition: Unknown
Due 14 August 1989
Resolved 14 August 1989
Deck/Cargo
Issued 14 August 1989
Resolved
CONDUCT A HYDROSTATIC TEST OF THE CARGO PIPING SYSTEM PRIOR TO LOADING NEXTCARGO. TEST TO BE CONDUCTED AT 150 PER CENT OF MAWP, AND NOT LESS THAN 150PSI.
Condition: Unknown
Due 14 August 1989
Resolved 14 August 1989