Records from 2016 to 2025. Most recent: inspection, 23 July 2025.
Everything above is free. The detail below — the inspection history, the deficiency record, the operational controls and the documentation record — is Professional, $39 a month. Sign in.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 17 September 2024
Resolved
No marine employer shall engage or employ any individual to serve as a crew member unless the individual passes a chemical test for dangerous drugs for that employer. A crew member on board was not part of the DAPI consortium for the vessel. Provide evidence that all employees are part of the DAPI program. 46 CFR 16.210(a)
Condition: Invalid
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2024
Resolved 1 October 2024
Resolution: Owner provided evidence of crew member on board enrolled in DAPI consortium.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 17 September 2024
Resolved
Portable and semi-portable extinguishers must be inspected and maintained in accordance with NFPA 10. Extinguisher at operating station was not mounted to the vessel. Properly mount extinguisher in it's approved bracket. 46 CFR 176.810(b)(1)
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2024
Resolved 1 October 2024
Resolution: Owner provided evidence of properly mounted fire extinguisher.
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 17 September 2024
Resolved
All vessels must have navigation lights that are in compliance with the applicable sections of the International and Inland Navigation Rules. Port side navigational light bulb was detached from mounting device exposing electrical wiring. Navigational light shall be properly mounted, securing the exposed wiring. 46 CFR 183.420
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2024
Resolved 2 October 2024
Resolution: Owner replaced and mounted new port side navigational light.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 6 October 2022
Resolved
Forward port bulkhead of the engine compartment is not sealed where wires pass through. Seal bulkhead penetrations as appropriate.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 October 2022
Resolved 21 October 2022
Resolution: Bulkhead Penetrations Sealed
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 6 October 2022
Resolved
Aft bulkhead of engine compartment has multiple holes which appear to have been previously used for bolts. Seal bulkhead penetrations as appropriate.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 October 2022
Resolved 21 October 2022
Resolution: Bulkhead Penetrations Sealed
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 6 October 2022
Resolved
STBD main propulsion engine has intermittent issues with starting and is displaying code 1347. Make permanent repairs to ensure consistent starting operation of propulsion engine.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 October 2022
Resolved 21 October 2022
Resolution: Faulty plug replaced and engine is operating properly
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 6 October 2022
Resolved
First aid kit was missing required items. Replace as appropriate.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 October 2022
Resolved 21 October 2022
Resolution: New First Aid kit present on the vessel.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 6 October 2022
Resolved
Both port and starboard interior hulls, in the locations of tire tie-off rings (3 port, 3 starboard), have compromised welds. Submit repair plan and repair prior to next credit drydock.
Action required: 705 - Other - as specified
Due 30 April 2023
Resolved 16 May 2023
Resolution: All sections cropped/renewed.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 6 October 2022
Resolved
Welds at the intersection of handrails and rail stanchion on port quarter are cracked. Submit repair plan and repair prior to next credit drydock.
Action required: 705 - Other - as specified
Due 30 April 2023
Resolved 7 April 2023
Resolution: Vessel repaired cracked handrail.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 6 October 2022
Resolved
Multiple cracked and broken welds were discovered along the bottom of the stairs on the starboard quarter. Submit repair plan and repair prior to next credit drydock.
Action required: 705 - Other - as specified
Due 30 April 2023
Resolved 16 May 2023
Resolution: Vessel corrected deficiency.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 6 October 2022
Resolved
One small hole was located in the starboard side of the lazarette overhead. Submit repair plan and repair prior to next credit drydock.
Action required: 705 - Other - as specified
Due 30 April 2023
Resolved 16 May 2023
Resolution: Hole in Laz has been repaired.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 6 October 2022
Resolved
A welding rod strike causing compromising the integrity of the bottom hull plating was located on the port side approximately midship. Submit repair plan and repair prior to next credit drydock.
Action required: 705 - Other - as specified
Due 30 April 2023
Resolved 16 May 2023
Resolution: Vessel repaired area.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 6 October 2022
Resolved
Pre-engineered fire extinguishing system was installed after 1996. Installed systems must comply with applicable regulations. Fire extinguishing system must meet applicable regulations. Extinguishing system does not shut down generator when activated. Generator is required to shut down upon activation of fixed fire extinguishing system. Vessel is instructed to not operate generator while underway until fixed fire extinguishing system has been brought into compliance no later than 14 days from receipt of this CG-835.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 October 2022
Resolved 21 October 2022
Resolution: Pre-Engineered fire system tested and shown operable on both main engines and the generator.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 9 September 2021
Resolved
All electrical installations shall be to the satisfaction of the Officer in Charge, Marine Inspection. The wiring on the lazzertte bile pump was exposed. Make effective repairs to the wiring for the lazzertte bilge pump.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 23 September 2021
Resolved 16 November 2021
Resolution: Received pictures attesting to the repairs
03 - Water/Weathertight Conditions › N/A - No Subsystem › Cargo & other hatchways
Issued 9 September 2021
Resolved
A hatch exposed to the weather must be watertight, both engine room hatches had wasted gaskets. Replace gaskets on both engine room hatches.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 10 October 2021
Resolved 16 November 2021
Resolution: Received pictures attesting to the repairs
02 - Structural Conditions › N/A - No Subsystem › Steering gear
Issued 9 September 2021
Resolved
All vessels except non-self-propelled vessels shall be provided with suitable steering apparatus. Vessel was missing cotter pin on bolt on steering gear.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 10 October 2021
Resolved 16 November 2021
Resolution: Received pictures attesting to the repairs
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 9 September 2021
Resolved
Internal combustion engine exhausts, boiler and galley uptakes, and similar sources of ignition shall be kept clear of and suitably insulated from any woodwork or other combustible matter. Vessel was missing a piece of insulation on bulkhead separating engine room compartment and accommodation space.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 10 October 2021
Resolved 3 May 2022
Resolution: Photo was provided showing properly installed fire retardant material.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 9 September 2021
Resolved
In general, compliance with the standards established by a recognized classification society will be considered satisfactory evidence of the structural adequacy of a vessel. Rub rail had a sharp inset, port side amidships, with a small puncture. There was also a crack on the same rub rail, port quarter. Make effective repairs to the port side rub rail to the satisfaction of the attendant Marine Inspector.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 10 October 2021
Resolved 3 May 2022
Resolution: Photos were provided showing repairs of inset on rub rail.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 9 September 2021
Resolved
Each ring life buoy must be marked with Type II retro reflective material approved in accordance with 46 CFR 164.018 or other standards. Both life rings did not have approved retro reflective tape. Make effective repairs to the satisfaction of the attendant Marine Inspector.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 10 October 2021
Resolved 16 November 2021
Resolution: Received pictures attesting to the repairs
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 27 April 2021
Resolved
Discovered cracked welds on the starboard shaft tube connection point to shaft strut. Make permanent repairs to starboard shaft tube. Clean away paint and inspect port side welds and ensure any visible cracks are identified and repaired. 46CFR176.15-5(Old-T)
Condition: Damaged By Earlier Event
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 May 2021
Resolved 12 May 2021
Resolution: Owner submitted photographs of final welds on prop shaft tube. all sat
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 27 April 2021
Resolved
Replace gasket on forward compartment's watertight hatch.
46CFR171.124(a)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 May 2021
Resolved 9 September 2021
Resolution: Forward hatch gasket was replaced, all sat.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 6 August 2020
Resolved
Repair/Replace the bilge high level alarm switch in lazarette. 46 CFR 182.530
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 20 August 2020
Resolved 14 August 2020
Resolution: O/O provided video showing alarm functioning after replacement of switch.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 11 May 2020
Resolved
Vessel does not have appropriate ground detection.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 June 2020
Resolved 27 April 2021
Resolution: Vessel has installed ground detection.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 20 April 2020
Resolved
FF SYSTEM FOUND UNSERVICED. SERVICE FIRE EXTINGUISHING SYSTEM. CONDUCT SATISFACTORY TEST OF SYSTEM IN PRESENCE OF COAST GUARD MARINE INSPECTOR.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 22 May 2020
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 20 April 2020
Resolved
OBSERVED FAULTY ECU ON PORT MAIN ENGINE. CROP AND REPAIR. CONDUCT SATISFACTORY SEA TRIAL IN PRESENCE OF COAST GUARD MARINE INSPECTOR.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 22 May 2020
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 20 April 2020
Resolved
UP TO DATE DRILL RECORDS UNABLE TO BE PROVIDED. CONDUCT MAN OVERBOARD AND FIRE DRILLS IN PRESENCE OF COAST GUARD MARINE INSPECTOR.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 11 May 2020
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 20 April 2020
Resolved
AILED DAPI AUDIT. COMPLETE DAPI AUDIT TO SATIFACTION OF COAST GUARD MARINE INSPECTOR.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 11 May 2020
04 - Emergency Systems › N/A - No Subsystem › Water level indicator
Issued 20 April 2020
Resolved
FAILED BILGE PUMPING TEST. CONDUCT BILGE TESTS IN ALL VOID SPACES IN PRESENCE OF COAST GUARD MARINE INSPECTOR.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 11 May 2020
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 20 April 2020
Resolved
A VESSEL IS INSPECTED FOR COMPLIANCE WITH THE STANDARDS REUQUIRED BY THIS SUBCHAPTER. THIS VESSEL FAILED THE COI RENEWAL INSPECTION AS IT WAS FOUND TO HAVE MANY GRAVE DEFICIENCIES TO SYSTEMS VITAL TO THE VESSELS SURVIVABILITY AND SAFETY IDENTIFIED DURING A LIMITED SCOPE INSPECTION .
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 22 May 2020
Electrical › Electrical Distribution System (service) › Ground Detection
Issued 4 June 2018
Resolved
vessel is to install ground detection
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 July 2018
Resolved 9 August 2018
Resolution: Vessel installed ground detection and verified by MI.
Lifesaving › Visual Distress Signals (General) › Expired
Issued 4 June 2018
Resolved
all flares on board were expired. Vessel is restricted to short runs.
Action required: 705 - Other - as specified
Resolved 21 June 2018
Construction/Loadline › Hull › Weld
Issued 4 June 2018
Resolved
vessel is to repair cracked weld located at the keel in the frame located fwd of aft bulkhead located in the lazarette spece.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 July 2018
Resolved 21 June 2018
Construction/Loadline › Structures › Deck Plating
Issued 4 June 2018
Resolved
vessel is to repair holes in overhead and rubrail (port side) located in the lazarette space.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 4 July 2018
Resolved 21 June 2018
Navigation › Piloting/Steering › Marine Charts
Issued 23 August 2017
Resolved
Provide updated marine chart, light list, coast pilot, and tide table publications.
Due 25 September 2017
Resolved 21 September 2017
Resolution: Provided all up to date charts and publications.
Accommodation/Occupational Safety › Medical/First Aid › Medicine Chest
Issued 23 August 2017
Resolved
Provide burn cream and aspirin in accordance with 46 CFR 160.041.
Due 25 September 2017
Resolved 21 September 2017
Resolution: Provided burn cream and aspirin.
Fire Fighting › Fire Bucket › Quantity
Issued 23 August 2017
Resolved
Provide (01) fire bucket.
Due 25 September 2017
Resolved 21 September 2017
Resolution: Provided fire bucket.
Operations/Management › Passenger Operations › Safety Orientation
Issued 23 August 2017
Resolved
Provide emergency instructions and post onboard.
Due 25 September 2017
Resolved 21 September 2017
Resolution: Posted Emergency Instructions.
Operations/Management › Passenger Operations › Safety Orientation
Issued 23 August 2017
Resolved
Label new alarm panel on bridge.
Due 25 September 2017
Resolved 21 September 2017
Resolution: Labeled panel.
Electrical › Electric Supply System (service) › Battery Charger
Issued 23 August 2017
Resolved
Provide ammeter on battery charger in engine room.
Due 25 September 2017
Resolved 21 September 2017
Resolution: Provided ammeter.
Documentation › Certificates/Documents › Certificate of Inspection
Issued 5 April 2017
Resolved
Vessel is restricted from carrying passsengers until credit drydock is completed. 46 CFR 176.600
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 17 August 2017
Resolution: MI's attested to complete DD/ISE inspection, including completion of all worklist items.
Construction/Loadline › Hull › Hull Plating
Issued 24 May 2016
Resolved
AM01: Crop and renew identified areas of hull.
01: Starboard side, aft of collision bulkhead to 2nd frame to chime.
02: Starboard #2 comp, between #3-4 frame at seams.
03: Port side Lazerette at keel.
Action required: 705 - Other - as specified
Resolved 28 June 2016
Resolution: See report and photos.
Fire Fighting › Fixed Gas Fire Extinguishing System › Operating Controls
Issued 4 May 2016
Resolved
Fire boy system not serviced
Action required: 701 - Prior to carriage of passengers/cargo
Due 4 May 2016
Resolved 11 July 2016
Resolution: Observed current inspection tag installed on Fire boy cylinder.
Fire Fighting › Fixed Gas Fire Extinguishing System › Operating Controls
Issued 4 May 2016
Resolved
Prove proper operation of fire boy system. Shutdown-Overide
Action required: 705 - Other - as specified
Due 18 July 2016
Resolved 20 July 2016
Resolution: Engine shut down up on discharge of agent. Vessel cannot reset system from control station, this is to be followed up with in special notes.
Fire Fighting › Fire Bucket › Quantity
Issued 4 May 2016
Resolved
Provide 03 Fire buckets. 01 missing.
Action required: 701 - Prior to carriage of passengers/cargo
Due 4 May 2016
Resolved 4 May 2016
Resolution: Operator provide 03 fire buckets.
Stability › Watertight Integrity › General
Issued 4 May 2016
Resolved
Provide repair proposal for hull damage port and starboard side quarters
Action required: 705 - Other - as specified
Due 15 May 2016
Resolved 11 July 2016
Resolution: Vessel conducted repairs, see attached documents for details.
Engineering › Sea-water System (primary cooling) › Piping
Issued 4 May 2016
Resolved
Renew R/W Pipe for Stbd M/E
Action required: 705 - Other - as specified
Due 15 May 2016
Resolved 11 July 2016
Resolution: Vessel repaired with welding. Piping no longer leaking.
Documentation › Certificates/Documents › FCC SSL
Issued 4 May 2016
Resolved
Provide FCC Station license.
Action required: 705 - Other - as specified
Due 15 May 2016
Resolved 11 July 2016
Resolution: Vessel provided FCC station license current as of 11Jul2016
Electrical › Electrical Distribution System (service) › Wiring
Issued 4 May 2016
Resolved
Properly wire heater in pilot house. Heater hard wired to outlet.
Action required: 705 - Other - as specified
Due 15 May 2016
Resolved 11 July 2016
Resolution: Observed heater properly wired in pilot house.
Electrical › Electrical Distribution System (service) › Wiring
Issued 4 May 2016
Resolved
Properly wire fan in pilot house. Fan wired with exposed wires.
Action required: 705 - Other - as specified
Due 15 May 2016
Resolved 11 July 2016
Resolution: Vessel removed fan
Stability › Watertight Integrity › Watertight Subdivision Standard
Issued 4 May 2016
Resolved
make FWD & AFT bulkheads e/r watertight. Aft B-head stuffing tube open & FWD B-head shore power cable penetration.
Action required: 705 - Other - as specified
Due 15 May 2016
Resolved 11 July 2016
Resolution: Observed penetrations secure and watertight
Electrical › Electrical Distribution System (service) › Wiring
Issued 4 May 2016
Resolved
Extension cords found permanently installed and plugged into outlet for block heaters. Cords were also found running through the bilge.
Action required: 705 - Other - as specified
Due 4 May 2016
Resolved 4 May 2016
Resolution: Operator removed permanent extension cord installation.
Documentation › Certificates/Documents › Stability Letter
Issued 3 May 2016
Resolved
Post stability letter at control station
Action required: 705 - Other - as specified
Due 15 May 2016
Resolved 11 July 2016
Resolution: Vessel displayed stability and plans to permanently display in pilot house.