Inspection history · 74
15 January 2018
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6350256
28 February 2017
Annual Inspection · MTSA Verification · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6103228
28 April 2015
Examination of Repairs · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5112727
14 April 2015
Damage Survey · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5103796
19 February 2015
MTSA Verification · Periodic Inspection · Deficiency Check
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5073170
26 March 2014
Examination of Repairs · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4823587
20 March 2014
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4819920
10 December 2013
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4839171
12 June 2013
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4618400
28 November 2011
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4233540
14 July 2011
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4080812
11 July 2011
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4077584
24 November 2010
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3924061
9 October 2010
Examination of Repairs · Damage Survey · Administrative Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3867261
30 March 2010
Periodic Inspection · Deficiency Check · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3705391
29 March 2010
Periodic Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3704840
25 March 2010
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3702526
3 December 2007
COI Inspection · Cargo Tank Internal · Administrative Inspection · Examination of Repairs · Hull Examination · Internal Structural Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3104392
10 October 2006
MTSA Verification · Periodic Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2797591
15 September 2006
Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2780111
1 February 2006
MTSA Verification · Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2577613
9 December 2004
Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2256269
18 October 2004
MTSA Verification · Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2223002
31 March 2004
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2034475
24 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1986806
7 July 2003
Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1888098
17 September 2002
COI Inspection · Hull Examination · Examination of Repairs · Internal Structural Exam · Cargo Tank Internal
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1647605
11 June 2002
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1629720
15 May 2002
Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1617253
29 April 2002
Damage Survey
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1610624
26 April 2002
Examination of Repairs · Damage Survey
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1608151
17 April 2002
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1622665
17 May 2001
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1065112
21 August 2000
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 822272
9 February 2000
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 122448
15 July 1999
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1102928
29 July 1998
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1129442
29 July 1998
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1131624
24 July 1997
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 782932
5 May 1997
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1097286
19 April 1997
Damage Survey
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1107324
24 April 1996
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1417935
11 May 1995
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1363279
17 June 1994
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1370886
19 May 1993
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1356344
24 February 1993
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1433982
18 February 1993
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 836819
10 February 1993
COI Inspection
Physical examination · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 1420698
17 December 1992
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 831008
16 May 1992
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1255420
15 February 1992
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1008017
4 February 1992
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 493359
23 December 1991
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 955479
20 September 1991
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1254110
28 June 1991
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 449471
15 February 1991
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 910183
1 November 1990
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 446582
24 May 1990
Re-Inspection · Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 926397
27 October 1989
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 448086
28 February 1989
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1194300
10 January 1989
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 520364
10 January 1989
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 1352435
29 August 1988
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 469247
16 March 1988
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1035160
5 August 1987
Type not recorded
No type recorded · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 508011
4 May 1987
Hull Examination · COI Inspection
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1025906
15 April 1986
Re-Inspection
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 999623
21 May 1985
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1289934
16 May 1985
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 447377
9 January 1985
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 526195
12 April 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1281195
19 May 1983
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 967252
26 January 1983
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1279508
9 June 1982
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 967111
Construction/Loadline › Hull › Hull Plating
Issued 14 April 2015
Resolved
D08 TBSIP self-reported deficiency. Make permanent repairs to 1/2 inch hole in the #1 starboard wing tank, in aft end of transition knuckle, approximately 8 foot aft of the forward bulkhead
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 29 May 2015
Resolved 1 May 2015
Resolution: Cropped and renewed.
Stability › Watertight Integrity › General
Issued 19 February 2015
Resolved
Vessel was found to have warn and dry rotted gaskets on void hatches in the following locations: 1 & 2 P/fwd, 2 P/aft, 3 P/fwd & aft, 4 S/fwd, 3 S/aft, 3 S/fwd, 2S/aft, 2S/fwd, both hatches bow and stern. Vessel must provide proper documentation to MI proving installation of new gaskets.
Action required: 701 - Prior to carriage of passengers/cargo
Due 19 February 2015
Resolved 20 February 2015
Resolution: Vessel provided proper documentation of new gasket installation to the satisfaction of Marine Inspector.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Piping
Issued 20 March 2014
Resolved
Vessel had wastage in its stripping line. Issued CG-835 for vessel to transit unloaded to Southwest Shipyard, Houston for permanent repairs prior to conducting cargo operations.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 3 April 2014
Resolved 26 March 2014
Resolution: Witnessed repair of block valve extension pipe. Air/soap test conducted at 2 psi, all satisfactory.
Construction/Loadline › Hull › Side Shell
Issued 11 July 2011
Resolved
D8 TBSIP SELF-REPORTED DEFICIENCY. Make permanent repairs to hole (approx 1/4" x 1/4") on stbd bow approx 7" down on side shell.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 20 August 2011
Resolved 13 July 2011
Resolution: Crop & renew (1) 24"x24"x1/2" gunnel
Stability › Watertight Integrity › General
Issued 9 October 2010
Resolved
Prior to loading cargo, proceed directly to Tx Barge and Boat shipyard, Freeport, TX. Complete repairs to the barge IWO deck edge, port side, approximately 40' from the stern, where barge sustained damage in the form of a 54" X 12" buckle/fracture at the deck edge. Complete repairs to the satisfaction of the attending CG inspector.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 22 October 2010
Resolution: Soap and air tested approx. 5ft x 4ft insert on bilge knuckle.
Construction/Loadline › Markings › Draft Marks/Indicating System
Issued 29 March 2010
Resolved
Draft marks and vessel name incomplete
Action required: 705 - Other - as specified
Due 29 March 2010
Resolved 30 March 2010
Resolution: Draft marks repainted, vessel name corrected
Deck/Cargo › Mooring/Anchoring › Winch
Issued 29 March 2010
Resolved
cable to be replaced
Action required: 705 - Other - as specified
Due 29 March 2010
Resolved 30 March 2010
Resolution: winch cable renewed
Deck/Cargo › Cargo Heating › General
Issued 29 March 2010
Resolved
Replace steam system relief valve and bypass valve to #1 steam drop
Action required: 705 - Other - as specified
Due 29 March 2010
Resolved 30 March 2010
Resolution: pressure relief and bypass valve replaced
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 29 March 2010
Resolved
Inspector unable to visually inspect vapor piping for polymerzation.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 March 2010
Resolution: vapor line visually inspected, all sat
Deck/Cargo › Vapor Control Systems › Vessel Vapor Overpressure/Vacuum Protection
Issued 29 March 2010
Resolved
PV valve to be replaced
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 March 2010
Resolution: P/V valve replaced
Deck/Cargo › Vapor Control Systems › Liquid Overfill Protection
Issued 29 March 2010
Resolved
vessel overfill alarm enclosure not weather tight.
Condition: Improper Installation
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 March 2010
Resolution: all enclosures repaired
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Cargo Pump
Issued 29 March 2010
Resolved
verify cargo pump relief valve testing and gage calibration
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 March 2010
Resolution: cargo pump relief valve tested at 125 psi, cargo and Vapor piping gages replaced
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 25 March 2010
Resolved
The vessel while loaded with heavily fuel, was found with 2 fractures in the bow rake, a 12"x1/4" fracture on the portside IVO the timberhead and a 21"x1/16" fracture on the stbdside IVO timberhead. The vessel is authorized to discharge cargo and upon completion, make permanent repairs in the Port of Houston, to the satisfaction of the attending Marine inspector prior conducting cargo operations.
Action required: 701 - Prior to carriage of passengers/cargo
Due 25 March 2010
Resolved 29 March 2010
Resolution: witnessed g/w repairs
Construction/Loadline › Hull › Bottom Plating
Issued 31 March 2004
Resolved
Port bow transition knuckle crushed / fractured.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 31 March 2004
Resolution: 6'' x 6'' x 3/4" insert.
Construction/Loadline › Hull
Issued 21 August 2002
Resolved
Washed weld seam exist from void #4 to the stern box. LEGACY COMPONENT DESC: Hull Plating
Action required: 705 - Other - as specified
Due 20 September 2002
Resolved 30 August 2002
Resolution: Conducted repair check of weld seam (approx 220 feet) from void #4 to the stern box. All sat.
Construction/Loadline › Hull
Issued 30 July 2002
Resolved
Hull plating damaged from the result of a collision via void #1,2 and 3 port side. LEGACY COMPONENT DESC: Side Shell
Action required: 705 - Other - as specified
Due 29 August 2002
Resolved 13 August 2002
Resolution: Witness repair check and air test 3/8" X 3, X 8'''' void #1; 3/8" X 3'' X 3'' void #2; 3/8" X 2'' X 6'' void #3. All sat.
Deck/Cargo
Issued 17 July 2002
Resolved
Modification of the vessel with high level and over fill alarm. Repair check and air test required.
Action required: 705 - Other - as specified
Due 17 August 2002
Resolved 12 August 2002
Resolution: Repair check and air test the 3/8" X 18" X 18" insert and cargo tank top pentration. All sat.
Construction/Loadline › Hull
Issued 17 July 2002
Resolved
Washed out weld seam via bottom plating from void #4 to rake transition plate. LEGACY COMPONENT DESC: Hull Plating
Action required: 705 - Other - as specified
Due 31 August 2002
Resolved 22 August 2002
Resolution: Inspect repaired seam from bow rake to void 4 with vessel on DD (East-point). Approx 150 feet of seam was repaired. All sat.
Construction/Loadline › Hull › Bottom Plating
Issued 24 April 2002
Resolved
STBD BOW RAKE BOTTOM PLATE AND KNUCKLE CRUSHED AND FRACTURED.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 26 April 2002
Resolution: 4'' X 6'' X 1/2" KNUCKLE INSERT
8'' X 7'' X 1/2" BOTTOM PLATE INSERT.
Stability › Unintentional Flooding
Issued 17 April 2002
Resolved
Vsl ran aground causing a 1 inch crack in the bow rake just fwd of collision bulkhead, stbd side. No other damage was found. LEGACY COMPONENT DESC: Crack in bow rake causing flooding
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 27 April 2002
Resolved 17 April 2002
Deck/Cargo
Issued 17 June 1994
Resolved
MAKE VAPOR HEADER OPEN FOR CG INSPECTION.
Condition: Unknown
Due 17 July 1994
Resolved 22 June 1994
Engineering
Issued 17 June 1994
Resolved
F/O LINE FOR CARGO PUMP ENGINE FROM F/O TANK NOT MOUNTED TO DECK, BRAKET BROKEN. REPAIR PROPERLY.
Condition: Unknown
Due 17 July 1994
Resolved 22 June 1994
Deck/Cargo
Issued 17 June 1994
Resolved
PROVE PROPER OPERATION OF HIGH LEVEL ALARM/SHUT DOWN. PRIOR TO LOADING OF CARGO.
Condition: Unknown
Due 17 July 1994
Resolved 22 June 1994
Deck/Cargo
Issued 10 February 1993
Resolved
PROVE PROPER OPERATION OF REMOTE EMERGENCY PUMP ENGINE SHUTDOWN PRIOR TO TRANSFERING CARGO._x001C_ _x001C_ 33 CFR 155.780_x001C_
Condition: Unknown
Due 2 March 1993
Resolved 2 March 1993
Engineering
Issued 10 February 1993
Resolved
PROVIDE OIL CONTAINMENT AROUND CARGO PUMP ENGINE OR REPAIR OIL LEAK FROM ENGINE._x001C_ _x001C_ 33 CFR 155.330_x001C_
Condition: Unknown
Due 10 February 1993
Resolved 10 February 1993
Deck/Cargo
Issued 10 February 1993
Resolved
PROVIDE PROPER CARGO PIPING DIAGRAM INCLUDING VAPOR RECOVERY SYSTEM PIPING IN OIL TRANSFER PROCEDURES._x001C_ _x001C_ 33 CFR 155.750 _x001C_
Condition: Unknown
Due 2 March 1993
Resolved 2 March 1993
Engineering
Issued 10 February 1993
Resolved
PROVIDE FUEL OIL CONTAINMENT FOR FUEL OIL TANK AT NEXT AVAILABLE PERIOD WHEN BARGE IS GAS FREED._x001C_ _x001C_ 33 CFR 155.320 _x001C_
Condition: Unknown
Due 2 March 1993
Resolved 2 March 1993
Construction/Loadline
Issued 10 February 1993
Resolved
REPAIR BROKEN DOG LATCH ON #1 PORT FORWARD WING VOID HATCH._x001C_ _x001C_ _x001C_ 33 CFR 155.815_x001C_
Condition: Unknown
Due 2 March 1993
Resolved 2 March 1993
Deck/Cargo
Issued 15 February 1991
Resolved
VAPOR RECOVERY OPERATIONS SHALL NOT BE CONDUCTED UNTIL THE VAPOR RECOVERY SYSTEM HAS BEEN APPROVED BY COMDT (G-MSC) IN ACCORDANCE WITH 46CFR39.10.13_x001C_AND THE C.O.I. HAS BEEN AMENDED TO AUTHORIZE VAPOR RECOVERY OPERATIONS.
Condition: Unknown
Due 15 February 1991
Resolved 15 February 1991