Inspection history · 96
22 September 2014
Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 4989538
16 September 2014
Administrative Inspection
Administrative · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 4984731
1 August 2014
Administrative Inspection
Administrative · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 4940661
26 July 2014
Damage Survey · Administrative Inspection
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 4937446
7 July 2014
Damage Survey · Administrative Inspection · Permit to Proceed
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4914454
6 March 2014
Examination of Repairs
Physical examination · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 4810949
5 March 2014
Damage Survey
Physical examination · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 4810129
3 February 2014
Damage Survey
Physical examination · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 4793964
21 August 2013
Administrative Inspection · Annual Inspection · MTSA Verification
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 4696810
13 August 2012
MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4405783
4 August 2011
Annual Inspection
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 4120332
23 November 2010
Annual Inspection
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 3908247
20 May 2009
Administrative Inspection
Administrative · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 3480032
20 August 2008
Deficiency Check
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3304575
17 July 2008
Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 3271035
24 June 2008
Periodic Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3246617
5 July 2007
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2984040
23 March 2007
Examination of Repairs
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 2893716
25 January 2007
Permit to Proceed · Administrative Inspection
Administrative · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2861582
22 August 2006
Type not recorded
No type recorded · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 2764858
16 May 2006
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2650536
15 May 2006
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2649599
12 January 2006
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2565473
30 November 2005
Damage Survey
Physical examination · Sector Lower Mississippi · USCG Heartland District (CGD-H) · Activity 2543336
28 June 2005
MTSA Verification
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 2406188
22 June 2005
Periodic Inspection · Internal Structural Exam · Hull Examination · Cargo Tank Internal · COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 2399520
24 March 2005
Damage Survey · Permit to Proceed
Physical examination · MIDET EAST BANK DETAIL · USCG Heartland District (CGD-H) · Activity 2318783
16 March 2005
Administrative Inspection
Administrative · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 2311413
5 January 2005
Examination of Repairs · Damage Survey · Permit to Proceed
Physical examination · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 2269544
30 December 2004
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 2289502
27 April 2004
Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2053477
23 February 2004
Administrative Inspection
Administrative · MIDET WEST DETAIL · USCG Heartland District (CGD-H) · Activity 2011158
23 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1985127
24 October 2003
Damage Survey
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 2001569
28 August 2003
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1889798
3 April 2003
Examination of Repairs · Cargo Tank Internal · COI Inspection · Hull Examination · Internal Structural Exam
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1763369
20 November 2002
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1708166
15 November 2002
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1705435
12 June 2002
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1629738
26 April 2002
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1609762
11 February 2002
Deficiency Check · Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1483560
8 January 2002
Damage Survey
Physical examination · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 1476862
8 January 2002
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 1490407
25 October 2001
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1376776
11 January 2001
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1057482
20 December 1999
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 813695
11 March 1999
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 803556
25 February 1999
Type not recorded
No type recorded · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 797750
24 February 1999
Type not recorded
No type recorded · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 71985
3 December 1998
Re-Inspection
Physical examination · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 806999
23 September 1998
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1451331
25 March 1998
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 787514
25 March 1998
Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1111223
9 January 1998
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 785154
29 October 1997
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 780103
8 August 1997
Type not recorded
No type recorded · MSD ST. PAUL · USCG Heartland District (CGD-H) · Activity 486117
8 August 1997
Type not recorded
No type recorded · MSD ST. PAUL · USCG Heartland District (CGD-H) · Activity 665566
9 January 1997
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1099188
27 October 1996
Type not recorded
No type recorded · MSO Paducah · USCG Heartland District (CGD-H) · Activity 129470
27 October 1996
Damage Survey
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1169132
10 July 1996
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1086799
9 January 1996
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 874312
8 January 1996
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1447518
21 April 1995
Hull Examination
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1434234
21 February 1995
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1160370
6 October 1994
Damage Survey · Examination of Repairs
Physical examination · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 1171467
26 September 1994
Type not recorded
No type recorded · MSO Pittsburgh · USCG Heartland District (CGD-H) · Activity 186334
6 August 1994
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 1178812
25 March 1994
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 855911
8 March 1994
COI Inspection
Physical examination · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 854507
28 February 1994
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 436504
29 March 1993
Re-Inspection · Hull Examination
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1134891
19 November 1992
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 831719
16 March 1992
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1318753
23 May 1991
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 923863
4 September 1990
Type not recorded
No type recorded · MSO MEMPHIS · USCG Heartland District (CGD-H) · Activity 450305
22 May 1990
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 913409
30 April 1990
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 539524
24 April 1990
Deficiency Check
Physical examination · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 911251
26 March 1990
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 903717
13 July 1989
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 1194238
13 July 1989
Administrative
Administrative · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1350234
24 April 1989
Administrative
Administrative · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 892643
18 April 1989
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1204572
23 March 1988
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1287000
25 January 1988
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 441439
7 November 1987
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 532031
16 April 1987
Administrative
Administrative · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1003664
9 April 1987
Re-Inspection
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1000294
22 March 1987
Type not recorded
No type recorded · MSO ST LOUIS · USCG Heartland District (CGD-H) · Activity 501871
26 March 1986
COI Inspection
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 997269
10 May 1985
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 984488
10 May 1985
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 984490
7 May 1985
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 984303
18 April 1984
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 984485
9 April 1984
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 522741
Construction/Loadline › Hull › Hull Plating
Issued 26 July 2014
Resolved
Make permanent repairs to the 1/4" X 12' fracture in headlog.
Action required: 705 - Other - as specified
Due 25 August 2014
Resolved 29 August 2014
Resolution: COI deactivated, vessel scrapped.
Construction/Loadline › Hull › Bottom Plating
Issued 3 February 2014
Resolved
Repair 1/4"x1" fracture stbd bow rake knuckle just forward of the first gusset on the deck forward of the aft bulkhead which has been jack patched.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 16 March 2014
Resolved 6 March 2014
Resolution: Workers gouged and welded aprox. 20" of weld. Air/soap test at 1.5 psi, test sat.
Construction/Loadline › Hull › Hull Plating
Issued 17 July 2008
Resolved
Barge reported hole on upper deck 6" behind pump at cargo trunk. Temp repair with liquid metal. Required permanent repair.
Condition: Unknown
Action required: 705 - Other - as specified
Due 17 August 2008
Resolved 18 August 2008
Resolution: Permanent repair made with a 7'' X 3'' insert on the #1 cargo tank lower raised trunk. Examined and air tested, all sat.
Construction/Loadline › Hull › Hull Plating
Issued 25 January 2007
Resolved
Small fracture 8 feet starb. of the centerline. Repair and or insert as needed.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Resolved 23 March 2007
Resolution: New plate inserted, all sat
Documentation › Logs/Records › Logbook/Record (unofficial)
Issued 15 May 2006
Resolved
Provide satisfactory documentation to [name withheld]/Galveston that this vessel has operated in fresh water service at least 6 of the last 12 months. If the vessel has not been operated in fresh water service at least 6 of the last 12 months or satisfactory documentation cannot be provided, the vessel will be required to be inspected IAW the salt water intervals prescribed in 46 CFR 31.10-21(a)(1)
Due 15 June 2006
Resolved 16 May 2006
Resolution: 16 May 2006: Reviewed Fresh Water documentation. All Sat
Construction/Loadline › Structures › Rake
Issued 30 November 2005
Resolved
Prior to taking on cargo make permanent repairs to 3" fracture in bow void in way of headlog
Condition: Unknown
Action required: 705 - Other - as specified
Resolved 13 January 2006
Resolution: Witnessed satisfactory air test of repair to the head log.
Operations/Management › Vessel Safety Management › Company Responsibilities/Authority
Issued 5 January 2005
Resolved
Barge not to depart Lewis and Clark fleet (UMR 196)
Action required: 701 - Prior to carriage of passengers/cargo
Due 7 January 2005
Resolved 12 January 2005
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Cargo Pump
Issued 5 January 2005
Resolved
Properly transfer product (cargo off vessel to allow MSO St. louis to re-evaluate voids #2 and 3.
Action required: 17 - Rectify deficiencies prior to departure
Due 7 January 2005
Resolved 5 January 2005
Operations/Management › Vessel Safety Management › Company Responsibilities/Authority
Issued 5 January 2005
Resolved
Properly monitor barges voids #2 and 3 for flooding.
Action required: 701 - Prior to carriage of passengers/cargo
Due 7 January 2005
Resolved 12 January 2005
Construction/Loadline › Hull › Bottom Plating
Issued 5 January 2005
Resolved
Provide proper gauging report of bottom scantlings of barge.
Due 12 January 2005
Resolved 12 January 2005
Construction/Loadline › Hull › Bottom Plating
Issued 5 January 2005
Resolved
Properly replace wastage metal on bottom plate with new metal.
Condition: Unknown
Action required: 701 - Prior to carriage of passengers/cargo
Due 13 February 2005
Resolved 5 August 2005
Resolution: Completed periodic gauging IAW 46 CFR 31.10-21a, bottom plate was replaced along with extensive side shell and bilge knuckle. All repairs are approved and certified for intended service.
Construction/Loadline › Hull
Issued 24 October 2003
Resolved
Do not load cargo until proper and permanent repairs have been made to the leak in the port stern corner of the stern void. LEGACY COMPONENT DESC: Hull Plating
Condition: Unknown
Action required: 705 - Other - as specified
Due 24 November 2003
Resolved 23 February 2004
Construction/Loadline › Hull › Bottom Plating
Issued 28 August 2003
Resolved
Fracture at centerline bottom plate in way of #2 wing void.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 28 August 2003
Resolution: 18" x 18" x 1/2" insert.
Construction/Loadline › Hull › Bottom Plating
Issued 28 March 2003
Resolved
Noted several areas of wastage on bottom plating.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 28 March 2003
Resolution: Crop and renew areas of bottom plating.
Construction/Loadline › Hull
Issued 3 March 2003
Resolved
Hull plating wasted IWO port and STBD IAW gauging report. LEGACY COMPONENT DESC: Hull Plating
Action required: 705 - Other - as specified
Due 25 April 2003
Resolved 31 March 2003
Resolution: Conducted repair check and air test of the hull plating 8'' X 3/8" X 160'' on the port and STBD side, all sat.
Deck/Cargo › Vapor Control Systems
Issued 15 November 2002
Resolved
Clean polymer build up from forward half of VCS main pipe and downcomers prior to loading cargo. LEGACY COMPONENT DESC: Piping/Hoses
Action required: 701 - Prior to carriage of passengers/cargo
Due 15 December 2002
Resolved 20 November 2002
Resolution: polymer has been removed
Construction/Loadline › Hull › Bottom Plating
Issued 12 June 2002
Resolved
3' set in and fractured weld in way of #1 wing void double bottom.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 12 June 2002
Resolution: 6''6" x 5'' x 3/8" insert.
Construction/Loadline
Issued 26 April 2002
Resolved
Present barge to Coast Guard Marine Inspector prior to next loading to survey possible damage as a result of a grounding on 26 April 2002 in MSU Baton Rouge's AOR.
Due 26 May 2002
Resolved 23 February 2004
Stability › Unintentional Flooding
Issued 9 January 2002
Resolved
Prior to loading cargo, barge is to be gas freed and have an internal structural exam and make permanent repairs to damaged areas. Flooding in #2 wing tank port and starboard. LEGACY COMPONENT DESC: Hull
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 11 February 2002
Resolution: gouge and reweld of 6" fracture
Construction/Loadline
Issued 25 February 1999
Resolved
INVESTIGATE SOURCE OF LEAK IN BOW VOID AND MAKE PERM REPAIRS TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR PRIOR TO LOADING CARGO.
Condition: Unknown
Due 25 February 1999
Resolved 25 February 1999
Deck/Cargo
Issued 9 January 1996
Resolved
PRIOR TO LOADING SPECIFIED DANGEROUS CARGOES (BHA & BHB) IN CONCENTRATIONS GREATER THAN 70% BENZENE BY VOLUME, BUT IN NO CASE LATER THAN 20JUN96, PROVIDE DOCUMENTATION OF G-MSC APPROVAL FOR CARRIAGE WITH VESSEL'S VAPOR COLLECTION SYSTEM.
Condition: Unknown
Due 9 January 1996
Resolved 9 January 1996
Deck/Cargo
Issued 8 January 1996
Resolved
Gauge cargo tank bulkhead in way of following areas: a.) #1/#2 Port Cargo Tank b.) #2/#3 Port Cargo Tank using no more than four (4) spots spaced equally about the above leaks. No cargo ops authorized until completion of repairs. See Nat. Marine SIP rpt for subj barge dtd 01/5/96 [name withheld]
Condition: Unknown
Due 15 January 1996
Resolved 12 January 1996
Construction/Loadline
Issued 6 October 1994
Resolved
Make permanent repairs to impact damage in rake hull plating on centerline two feet above the light waterline. To be completed before next cargo loading.
Condition: Unknown
Due 1 November 1994
Resolved 18 October 1994
Construction/Loadline
Issued 8 March 1994
Resolved
MAKE REPAIRS TO AFT STARBOARD TIMBERHEAD.
Condition: Unknown
Due 8 March 1994
Resolved 8 March 1994
Deck/Cargo
Issued 8 March 1994
Resolved
TEST HIGH LEVEL ALARM AND SHUTDOWN SYSTEM FOR VAPOR CONTROL SYSTEM.
Condition: Unknown
Due 8 March 1994
Resolved 8 March 1994
Deck/Cargo
Issued 16 March 1992
Resolved
VAPOR RECOVERY OPERATIONS SHALL NOT BE CONDUCTED UNTIL THE VAPOR RECOVERY SYSTEM HAS BEEN APPROVED BY USCG (G-MSC) IAW 46CFR39.10.13 AND THE COI HAS BEEN AMENDED TO AUTHORIZE VAPOR RECOVERY OPERATIONS.
Condition: Unknown
Due 16 March 1992
Resolved 16 March 1992
Construction/Loadline
Issued 24 April 1990
Resolved
RENEW GASKETS TO ALL VOID HATCH COVERS.
Condition: Unknown
Due 24 April 1990
Resolved 24 April 1990
Deck/Cargo
Issued 26 March 1990
Resolved
DRAIN ALL POLLUTION CONTAINMENT DRIP PANS (33 CFR 155.310).
Condition: Unknown
Due 26 March 1990
Resolved 26 March 1990
Construction/Loadline
Issued 26 March 1990
Resolved
DRAIN ALL VOIDS (46 CFR 31.10-21).
Condition: Unknown
Due 26 March 1990
Resolved 26 March 1990