Records from 1981 to 2007. Most recent: inspection, 1 February 2007.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 44
1 February 2007
PII Safety Exam · Deficiency Check · ISPS II Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2863655
16 February 2006
Security Plan Amendment Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2586280
18 November 2003
Security Plan Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 1950197
3 December 2001
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 772572
30 August 2000
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1446978
23 August 1999
Hull Examination · Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1452534
9 September 1998
COI Inspection
Physical examination · MSO Mobile · USCG Heartland District (CGD-H) · Activity 1466012
18 February 1998
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 776051
2 January 1998
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 786335
5 October 1997
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 203482
5 October 1997
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 768814
14 August 1997
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1388340
18 June 1997
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 776559
29 October 1996
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 852936
11 September 1996
Hull Examination · COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1413052
31 July 1996
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 765049
1 July 1996
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 198248
18 April 1996
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1414614
15 May 1995
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 655502
25 April 1995
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 861731
21 April 1995
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 81844
21 April 1995
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 164026
13 April 1995
Examination of Repairs
Physical examination · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 851867
11 April 1995
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 73740
21 February 1995
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1355109
2 December 1994
Examination of Repairs
Physical examination · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1182064
1 December 1994
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 10797
29 August 1994
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 866688
6 May 1994
Hull Examination · Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1409129
19 August 1993
Deficiency Check
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1154666
9 June 1993
Examination of Repairs
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1440706
7 May 1993
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1137018
29 April 1993
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 836915
13 April 1993
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1143850
12 March 1993
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1150166
21 February 1992
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 959504
28 August 1991
Hull Examination
Physical examination · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1353261
13 March 1991
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1236402
9 May 1990
Re-Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1218071
10 May 1989
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 899138
25 April 1989
COI Inspection · Hull Examination
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1031432
2 April 1984
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1280961
30 December 1981
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 969819
30 December 1981
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1280790
Construction/Loadline › Markings › Load Line Mark
Issued 1 February 2007
Resolved
Loadline and deck line must be marked and painted in accordance with International Loadline Certificate.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 2 February 2007
Resolution: Loadline has been marked and painted.
Engineering › Steering Gear System › Rudder Angle Indicator
Issued 1 February 2007
Resolved
Rudder angle indicator between navigational bridge and steering compartment was approx. 15 degrees apart.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 2 February 2007
Resolution: USCG inspectors witnessed steering test and noted everything satisfactory.
Engineering
Issued 30 August 2000
Resolved
PROVE PROPER OPERATION OF PRESSURE RELIEF VALVES TO CLASS.
Condition: Unknown
Due 30 August 2000
Resolved 31 August 2000
Lifesaving
Issued 30 August 2000
Resolved
PROPERLY CONNECT WEAK LINK TO SEA PAINTER.
Condition: Unknown
Due 30 August 2000
Resolved 31 August 2000
Documentation
Issued 11 September 1996
Resolved
PROVIDE APPROVED PLANS FOR P-TANK VOID CONVERSIONS, USE AS F/O TANK NOT AUTHORIZED UNTIL APPROVED PLANS RECEIVED AND VERIFIED.
Condition: Unknown
Due 11 September 1996
Resolved 11 September 1996
Documentation
Issued 11 September 1996
Resolved
SUBMIT AUTOMATION TEST PROCEDURE TO [name withheld] FOR APPROVAL.
Condition: Unknown
Due 11 September 1996
Resolved 11 September 1996
Navigation
Issued 9 June 1993
Resolved
MAKE VESSEL AVAILABLE FOR INSPECTION OF REPAIRS TO STARBOARD RUDDER, STOCK,AND INSERT ON BOTTOM PLATE AROUND STARBOARD RUDDER STOCK AREA, OR PROVIDE SATISFACTORY ABS REPORT OF REPAIRS._x001C_
Condition: Unknown
Due 9 June 1993
Resolved 9 June 1993
Electrical
Issued 12 March 1993
Resolved
INSTALL BLANKS OVER EMPTY CIRCUIT BREAKERS ON MAIN SWITCH BOARD.
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993
Engineering
Issued 12 March 1993
Resolved
ADJUST PACKING GLAND ON FUEL OIL TRANSFER PUMP TO REDUCE EXCESSIVE LEAKAGE.
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993
Unknown
Issued 12 March 1993
Resolved
OBTAIN AND POST MANUFACTURERS LABEL AND OPERATIONG INSTRUCTIONS ON MSD TANK.
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993
Engineering
Issued 12 March 1993
Resolved
REPAIR/ REPLACE STRB ENG SHAFT ENG SHAFT TACH AND PROVE PROPER OPERATION INAHEAD AND ASTEARN THROTTLE.
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993
Construction/Loadline
Issued 12 March 1993
Resolved
DEMONSTRATE PROPER OPERATION OF THE FORWARD ENGINE RM BILGE ALARM
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993
Electrical
Issued 12 March 1993
Resolved
PROVE PROPER OPERATION OF THE PORT AND STRB SSDG OVERSPEED TRIP.
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993
Lifesaving
Issued 12 March 1993
Resolved
LABEL LIFE JACKET LOCKER.
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993
Fire Fighting
Issued 12 March 1993
Resolved
REPLACE FIRE PUMP GAGE ON BRIDGE AND PROVE PROPER OPERATION.
Condition: Unknown
Due 12 March 1993
Resolved 12 March 1993