Records from 1981 to 2019. Most recent: inspection, 8 January 2019.
Inspection history · 93
8 January 2019
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6607310
29 January 2018
Administrative Inspection · Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6369531
1 March 2017
Annual Inspection · Administrative Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6103236
18 December 2015
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5784492
5 November 2014
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5058252
22 August 2014
Administrative Inspection · Examination of Repairs · Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4996875
12 August 2014
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4952995
21 January 2014
COI Inspection · MTSA Verification · Internal Structural Exam · Administrative Inspection · Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4786956
10 October 2012
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4489517
16 March 2012
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4264884
1 February 2012
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4235805
26 October 2011
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4220753
1 November 2010
Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3882721
22 October 2008
Cargo Tank Internal · COI Inspection · Drydock Exam · Internal Structural Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3349272
2 May 2008
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3198768
14 April 2008
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3183653
18 December 2007
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3117628
15 November 2007
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3098911
1 November 2007
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3090922
9 October 2007
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3075979
7 October 2007
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3086177
7 August 2007
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3020434
4 August 2007
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3054087
3 July 2007
Damage Survey
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2981720
6 October 2006
Damage Survey · Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2806945
21 June 2006
MTSA Verification · Periodic Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2717027
2 May 2006
Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2638725
17 April 2006
Damage Survey · Permit to Proceed
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2626323
17 June 2005
MTSA Verification · Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2459031
23 May 2005
MTSA Verification · Administrative Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2365565
1 April 2005
Administrative Inspection · Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2324622
23 February 2005
Administrative Inspection
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2297715
25 October 2004
Annual Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 2227585
24 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1989228
2 September 2003
Internal Structural Exam · COI Inspection
Physical examination · MIDET WEST DETAIL · USCG Heartland District (CGD-H) · Activity 1894601
4 September 2002
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 1670803
19 June 2002
Periodic Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1633385
2 December 2001
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 504788
21 May 2001
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1068708
3 August 2000
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1455896
29 June 1999
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1404786
13 August 1998
Hull Examination · COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1129619
23 May 1997
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1378061
29 October 1996
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 853376
11 July 1996
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1437125
16 August 1995
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1183357
25 May 1995
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1377429
11 July 1994
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 868422
7 July 1994
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1359858
18 June 1993
Hull Examination · COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 833500
22 March 1993
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1150094
4 March 1993
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 505240
13 January 1993
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 832933
14 July 1992
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 499728
3 June 1992
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 945999
1 April 1992
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1266696
19 December 1991
Examination of Repairs
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 962671
19 July 1991
Type not recorded
No type recorded · MSO HUNTINGTON · USCG Heartland District (CGD-H) · Activity 535631
2 May 1991
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1216189
22 January 1991
Damage Survey
Physical examination · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 918933
10 January 1991
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 514897
9 January 1991
Type not recorded
No type recorded · MSO CHICAGO · USCG Great Lakes District (CGD-GL) · Activity 451148
7 September 1990
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1211270
31 August 1990
Administrative
Administrative · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 921879
25 May 1990
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 923602
6 April 1990
Re-Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1220803
8 November 1989
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1216140
6 November 1989
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 920661
30 October 1989
Administrative
Administrative · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 906130
25 October 1989
Deficiency Check
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1205711
25 July 1989
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1343464
8 May 1989
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1350388
4 October 1988
Hull Examination
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1196797
31 August 1988
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1349188
27 July 1988
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1033585
22 March 1988
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1032539
13 May 1987
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1026527
3 February 1987
Examination of Repairs
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1014762
28 October 1986
Re-Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1323557
30 August 1985
COI Inspection
Physical examination · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1299612
4 April 1985
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 981282
10 December 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 977736
3 December 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 976470
21 September 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1282229
31 May 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1281057
10 January 1984
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 972371
28 September 1983
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1277958
3 September 1983
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 967429
3 September 1983
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 1274576
1 June 1983
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 969401
26 October 1982
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 965651
17 July 1981
Type not recorded
No type recorded · MIO HOUSTON · USCG Heartland District (CGD-H) · Activity 964844
5 May 1981
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1277758
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Piping
Issued 12 August 2014
Resolved
Vessel shall proceed to facility/vessel to offload cargo. Prior to any additional operations, make permanent repairs to #2 port cargo piping pinhole leak to the satisfaction of attending Marine Inspector.
Action required: 705 - Other - as specified
Due 12 September 2014
Resolved 22 August 2014
Resolution: Gouged and welded the weld seam on #2 port cargo piping Conducted a visual exam and hydro test of repair. Test satisfactory.
Construction/Loadline › Hull › Bottom Plating
Issued 1 February 2012
Resolved
D08 Self reported TBSIP def. Make Permanent repairs to 1/8" HOLE LOCATED 1ST BAY TO THE PORT SIDE OF CENTER LINE OF BOW VOID 1' FROM FLOOR 5TH FRAME.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 14 March 2012
Resolved 16 March 2012
Resolution: Verified repairs were made to hole in fwd end of vessell.
Construction/Loadline › Hull › Bottom Plating
Issued 14 April 2008
Resolved
Vessel reports 1 1/2" x 1/8" wide fracture on stbd side bilge knuckle.
Condition: Unknown
Action required: 705 - Other - as specified
Due 19 April 2008
Resolved 2 May 2008
Construction/Loadline › Hull › Hull Plating
Issued 9 October 2007
Resolved
Vessel reported a 8" X 1/32" fracture on the gunwale on port bow corner. Installed temp repair.
Condition: Unknown
Action required: 705 - Other - as specified
Due 22 November 2007
Resolved 1 November 2007
Resolution: Examined welds and witnessed satisfactory air test of 10'' x 7'' x 1/2” section of gunnel knuckle in way of #1 port wing void.
Construction/Loadline › Hull › Hull Plating
Issued 3 July 2007
Resolved
2 1/2" x 1/4" fracture on bow void, 20" from stbd side, 20" from bottom.
Condition: Unknown
Action required: 705 - Other - as specified
Due 13 August 2007
Resolved 7 August 2007
Resolution: Conducted repair check. Examined welds and witnessed satisfactory air test of 8'' x 22" x 3/8" insert to the bow void.
Deck/Cargo
Issued 7 July 1994
Resolved
MAKE VAPOR COLLECTION HEADER AND PIPING SYSTEM AVAILABLE FOR INTERNAL EXAMINATION BY USCG INSPECTOR.
Condition: Unknown
Due 7 July 1994
Resolved 7 July 1994
Construction/Loadline
Issued 22 March 1993
Resolved
CROP AND RENEW DAMAGE/ WASTED HULL PLATE IN WAY OF THE BOW VOID, STARBOARD BOTTOM CORNER.
Condition: Unknown
Due 22 March 1993
Resolved 22 March 1993
Construction/Loadline
Issued 25 October 1989
Resolved
REPAIR LEAK IN STERN VOID.
Condition: Unknown
Due 25 October 1989
Resolved 25 October 1989
Construction/Loadline
Issued 31 August 1988
Resolved
MAINTAIN TEMPORARY REPAIRS TO SIDE SHELL UNTIL VESSEL IS DRYDOCKED AND PERMANENT REPAIRS ARE MADE TO THE SATISFACTION OF THE ATTENDING MARINE INSPECTOR AND THE COGNIZANT OCMI.
Condition: Unknown
Due 31 August 1988
Resolved 31 August 1988
Deck/Cargo
Issued 31 August 1988
Resolved
PROVIDE SUITABLE COVER AND ADEQUATE GUARDS FOR DIESEL CARGO PUMP ENGINE TO THE SATISFACTION OF THE ATTENDING CG MARINE INSPECTOR AND COGNIZANT OCMI.
Condition: Unknown
Due 31 August 1988
Resolved 31 August 1988