Inspection history · 20
12 December 2025
Periodic Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 8271198
12 November 2025
Cargo Tank Internal · Internal Structural Exam · Drydock Exam · Administrative Inspection · Vessel Attendance
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 8264048
20 October 2025
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 8255568
24 April 2025
Annual Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 8123945
24 April 2024
MARPOL Annex I Examination · MARPOL Annex VI Survey · Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7900588
15 February 2024
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 7867680
26 July 2023
Administrative Inspection · In-Service Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7752627
9 January 2023
Cargo Tank Internal · MTSA/ISPS Verification · Internal Structural Exam · Drydock Exam · COI Inspection · Hull Examination
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7618878
16 March 2022
Deficiency Check · Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7412962
9 February 2022
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7393812
5 February 2021
Annual Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7136240
30 December 2020
Hull Examination · Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7117549
12 February 2020
MTSA/ISPS Verification · Administrative Inspection · Periodic Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6907246
27 February 2019
Annual Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6633125
26 February 2018
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6362066
18 December 2017
Administrative Inspection · COI Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6326149
15 December 2017
Hull Examination · Internal Structural Exam · Administrative Inspection · Cargo Tank Internal
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6324854
18 April 2017
Administrative Inspection
Administrative · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6126982
6 December 2016
Administrative Inspection · Deficiency Check · Annual Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6053211
22 January 2016
Annual Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 5801907
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 12 December 2025
Resolved
The master shall ensure that the vessel's required firefighting equipment is on board in the prescribed location and always ready for use. During CO2 test of ER space with Maritime Safety Solutions, discharge pipe wastage at the base of the discharge pipe bursted releasing CO2 on deck.
Action required: 10 - Deficiency Rectified
Resolved 12 December 2025
Resolution: Witnessed hydro test (1000 psi)of CO2 ER discharge line for 5 minutes. Verified no leaks.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Gauges, thermometers, etc
Issued 12 December 2025
Resolved
In no case must the upper range of the pressure-indicating gage be less than 1.2 times nor more than 2 times the pressure at which the relieving device is set to function. Relief valve was set to 190 and gauge max was 200psi.
Action required: 10 - Deficiency Rectified
Resolved 12 December 2025
Resolution: 300 psi gauges installed.
02 - Structural Conditions › N/A - No Subsystem › Beams, frames, floors-corrosion
Issued 12 November 2025
Resolved
Each OSV must be placed in drydock or hauled out for examination oh the hull and the internal structural members must also be examined at the same interval to assess the safety and seaworthiness of the vessel. During this examination the following worklist items were found:
- The doubler plate installation for the flukes of the anchor must be completed.
- The uppermost corner bracket in the No. 2 Port Ballast tank next to the entry hatch of the space has wasted beyond acceptable limits and must be replaced.
- The starboard bridge wing's support structure must be repaired due to wastage on the underside.
- The starboard side air intake damper must be renewed due to wastage.
- The forepeak reachrod must be made to be functional and operated in the presence of a USCG marine inspector.
- The No. 8 port quick-acting fuel shutoff valve must be made to be functional and operated in the presence of a USCG marine inspector.
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Due 12 December 2025
Resolved 12 December 2025
Resolution: Forepeak reachrod elbows and the valve replaced. Doubler plate installed for anchor flukes and inspected. Corner bracket in the No. 2P blst tank was replaced. Wasted starboard bridge wing supports renewed. Air intake wastage renewed. Fuel shutoff operable
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 24 April 2024
Resolved
Each generator arranged for parallel operation must have reverse power or reverse current trips. Reverse power relay not operating as intended. Bring to proper operation.
– 46 CFR 111.12-11(f)
Action required: 17 - Rectify deficiencies prior to departure
Due 24 April 2024
Resolved 24 April 2024
Resolution: A bad relay was changed out, and the function satisfactorily tested by a technician in the presence of an attending ABS Class Surveyor.
10 - Safety of Navigation › N/A - No Subsystem › Other (navigation)
Issued 24 April 2024
Resolved
All ships of 500 gross tonnage and upwards shall have: A gyro -compass heading repeater visually at the emergency steering position. Repeater was not functioning or cutting on. Fix to proper operation.
– SOLAS (20)V / 19.2.5.2
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 May 2024
Resolved 25 April 2024
Resolution: Repeater has been repaired. Service ticket from Superior Marine provided by vessel rep, see documents.
10 - Safety of Navigation › N/A - No Subsystem › Signalling lamp
Issued 24 April 2024
Resolved
Systems and equipment including back-up arrangements shall conform to appropriate performance standards (resolution MSC.95 (72) 3 spare bulbs not present.
- SOLAS (20) V/18.2 16a
Action required: 16 - Rectify deficiencies w/in 14 days
Due 8 May 2024
Resolved 25 April 2024
Resolution: Proviede invoice and service report stating Superior Marine picked up bulbs on the way to vessel for gyro repair, see documents.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 24 April 2024
Resolved
There must be ground detection for each lighting system and power or lighting distribution panel. Ground detection panel ground detection not working on multiple panels.
- 46 CFR 111.05-21(c)(d)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 24 May 2024
Resolved 25 April 2024
Resolution: Service tech report provided, see documents tab.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 24 April 2024
Resolved
The inspection procedures for marine engineering systems contained in subchapter F of this chapter apply. Starboard main engine non-metallic expansion joints cracked and deteriorated. Replace to good condition.
- 46 CFR 126.470
Action required: 50 - Rectify deficiencies w/in 30 days
Due 24 May 2024
Resolved 30 April 2024
Resolution: Vessel rep provided photo evidence of correction and install or new non-metallic expansion joints.
07 - Fire Safety › N/A - No Subsystem › Fire pumps and its pipes
Issued 9 January 2023
Resolved
The fire pump must be capable of delivering a single stream of water from the highest hydrant at a pressure of 50 psi. Could not test the main fire pump due to seafloor conditions being too muddy and fire pump unable to hold suction. ABS will test main fire pump during FMEA trials.
46 CFR 132.120(a)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 10 February 2023
Resolution: RO rectified deficiency during FEMA trials.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Doors
Issued 17 March 2022
Resolved
Each watertight door must make proper seal with watertight gasket to be watertight. (02) Watertight door gaskets were not sealing properly as designed. Replace gaskets to make watertight.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 21 March 2022
Resolved 21 March 2022
Resolution: Attending Marine Inspectors observed the deficiency was rectified.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 17 March 2022
Resolved
Visible and audible alarms must be installed to indicate a fire in the engine room. Engine room fire alarm was inoperable and general alarm audible was not audible. Replace or repair.
Condition: Invalid
Action required: 17 - Rectify deficiencies prior to departure
Due 21 March 2022
Resolved 21 March 2022
Resolution: Attending Marine Inspectors observed the deficiency was rectified.
04 - Emergency Systems › N/A - No Subsystem › Emergency, lighting, batteries and switches
Issued 16 March 2022
Resolved
Survival craft in a the area where it is to be launched must be illuminated by emergency power. Emergency lights by survival craft were not illuminated. Repair or replace lights as designed.
Condition: Invalid
Action required: 17 - Rectify deficiencies prior to departure
Due 21 March 2022
Resolved 21 March 2022
Resolution: Attending Marine Inspectors observed the deficiency was rectified.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 16 March 2022
Resolved
Each fixed fire-extinguishing system installed must comply with part 95. A Master or person in charge must make sure that the lock-out valve is locked open at all times. Secure valve as designed.
Condition: Design Flaw
Action required: 17 - Rectify deficiencies prior to departure
Due 21 March 2022
Resolved 21 March 2022
Resolution: Attending Marine Inspectors observed the deficiency was rectified.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 16 March 2022
Resolved
Each machinery space must be free of fire hazards. Stbd generator had soot and oil residue on top of cylinder head. Clean generator of soot and oil residue.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 21 March 2022
Resolved 21 March 2022
Resolution: Attending Marine Inspectors observed the deficiency was rectified.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 16 March 2022
Resolved
Each ring buoy must be in good material condition and serviceable. Stbd side main deck ring buoy grab line unserviceable. Repair or replace ring buoy.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 16 April 2022
Resolved 21 March 2022
Resolution: Attending Marine Inspectors observed the deficiency was rectified.
07 - Fire Safety › N/A - No Subsystem › Fire control plan
Issued 16 March 2022
Resolved
Each vessel must have updated fire and safety plan in accordance with their vessel. Vessel had two emergency lights on the boat deck which were absent on the fire safety plan. Add emergency lights to fire and safety plan.
Condition: Design Flaw
Action required: 50 - Rectify deficiencies w/in 30 days
Due 16 April 2022
Resolved 31 March 2022
Resolution: Fire and safety plan received and verified.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 16 March 2022
Resolved
MSD Type II must be operational as designed. MSD blower was inoperable. Repair MSD to operate as designed by the manufacture's instructions.
Condition: Invalid
Action required: 50 - Rectify deficiencies w/in 30 days
Due 16 April 2022
Resolved 21 March 2022
Resolution: Attending Marine Inspectors observed the deficiency was rectified.
01 - Certificates & Documentation › 013 - Documents › Records of seafarers' daily hours of work or rest
Issued 12 February 2020
Resolved
The work rest log does not capture properly when the crew is working or resting. Log every work period even when not on watch.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 11 March 2020
Resolution: Proper logs are now being kept.
14 - Pollution Prevention › 144 - MARPOL Annex IV (Not Applicable to PSC Exams conducted in the U.S.) › Sewage treatment plant
Issued 12 February 2020
Resolved
The vessel had a problem with the treatment system and by-passed the MSD to the sewage holding tank without treating it. Ensure vessel treats and discharges sewage IAW 33CFR159.53
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 11 March 2020
Resolution: Sewage properly treated.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 12 February 2020
Resolved
Hoses for aux engines must meet 58.60. The start air hoses for the port generator were cracked and unserviceable. Replace hose and test.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 11 March 2020
Resolution: Hoses replaced.
01 - Certificates & Documentation › 013 - Documents › Unattended Machinery Spaces (UMS) Evidence
Issued 12 February 2020
Resolved
Periodic tests must be conducted at intervals specified by the Coast Guard. The PSTP’s were last conducted 3 years ago. Ensure tests are conducted and logged annually.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 11 March 2020
Resolution: 3rd party conducted PSTP'S.
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 6 December 2016
Resolved
Provide Calibration certificate for Oil Content Meter.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 12 December 2016
Resolved 9 December 2016
Resolution: Calibration certificate provided.
Engineering › Fuel Oil Service System › Piping
Issued 6 December 2016
Resolved
Flexible F/O lines on the Port Generator not serviceable.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 7 December 2016
Resolved 9 December 2016
Resolution: Flexible F/O lines replaced
Communications › Alarms/Indicators › Steering Failure Alarm System
Issued 22 January 2016
Resolved
Vessel's motor power failure alarm on navigational bridge was inoperable.
-46 CFR 58.25
Action required: 705 - Other - as specified
Due 22 February 2016
Resolved 28 January 2016
Resolution: Vessel representative provided documentation satisfying the deficiency