Records from 2006 to 2025. Most recent: inspection, 4 February 2025.
Documentation record
Registered dimensions (L × B × D)297.5 ft × 54.0 ft × 12.0 ft
Registered tonnagegross 1,619 / net 1,619
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderTRINITY MARINE PRODUCTS INC · MADISONVILLE, LA, UNITED STATES · built 2006
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portHOUSTON, TX
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 28 May 2026 · expires 30 June 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1619 - Simplified, Net Ton
1619 - Simplified, Gross Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 20
4 February 2025
Damage Survey · Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8074822
28 August 2024
Bulk Liquid Transfer Monitor
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7991406
19 October 2023
Deficiency Check · Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7809847
23 September 2023
Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 7797097
9 May 2023
Administrative Inspection · COI Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7684335
17 January 2023
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7624028
14 March 2019
Annual Inspection · MTSA Verification · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6703375
1 March 2018
Cargo Tank Internal · Examination of Repairs · Internal Structural Exam · MTSA Verification · Drydock Exam · COI Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6361719
13 June 2016
Drydock Exam · Cargo Tank Internal · Internal Structural Exam · Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5900221
14 April 2015
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5099063
7 February 2014
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4793707
24 June 2013
Type not recorded
No type recorded · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4630140
9 February 2012
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4241491
17 August 2010
Annual Inspection
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3826988
17 July 2009
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3537359
17 October 2008
Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3345406
18 October 2007
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3082412
25 September 2006
Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2783986
19 September 2006
Administrative Inspection · Cargo Tank Internal · Initial Construction-Excluding Oversight · COI Inspection · Hull Examination · Internal Structural Exam · MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2686172
15 June 2006
Security Plan Amendment Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 2680325
02 - Structural Conditions › N/A - No Subsystem › Cargo tank vent system
Issued 23 September 2023
Resolved
Cargo tanks in which Grade A, B, or C liquids are to be transported shall be fitted with individual pressure-vacuum relief valves or a venting system connected to a vent header fitted with a pressure-vacuum relief valve. The vessel representative reported two pin-hole leaks in the main vapor line. Vessel is authorized to conduct temporary repairs and transit to VLS Port Arthur to offload cargo and conduct permanent repairs to the satisfaction of the attending Coast Guard Marine Inspector. The main vapor line shall be made available for pressure testing. Repairs shall be completed within 14 days and prior to conducting any cargo operations other than what is described above.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 October 2023
Resolved 19 October 2023
Resolution: Adequate repairs made to main vapor line. Satifactorily inspected repairs and witnessed pressure test of repairs.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Cargo Pump
Issued 19 September 2006
Resolved
Provide proof of Class 1 Div 1 wiring harness on the Cargo Pump Engine. 46 CFR 111.105-31
Due 1 August 2007
Resolved 25 September 2006
Resolution: Vessel has only air start and manual start. Class 1 Div 1 equipment is not required.
Fire Fighting › Portable Dry Chemical Fire Extinguisher › Service
Issued 19 September 2006
Resolved
Provide two (2) seviceable B-II fire extinguishers as required in 46 CFR 34.50-10.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 September 2006
Resolution: Two B-II fire extinguishers onboard.
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 19 September 2006
Resolved
Properly paint required Vapor Control markings as required in 46 CFR 39.20-3 (d).
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 September 2006
Resolution: Vapor Control line properly painted.
Pollution Prevention/Response › Prevention Equipment › Cargo Monitor/Control System
Issued 19 September 2006
Resolved
Install liquid level indicators (rising sticks) as required by 46 CFR 38.10-20.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 September 2006
Resolution: Liquid level indicators installed.
Pollution Prevention/Response › Prevention Equipment › Designated Observation Area
Issued 19 September 2006
Resolved
Provide proof of Benzene regulated (painted area) area as per 46 CFR 197.535 (c). Painted line designating the area.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 September 2006
Resolution: Benzene regulated area posted with a sign.
Construction/Loadline › Markings › Draft Marks/Indicating System
Issued 19 September 2006
Resolved
Draft marks must be painted in contrasting color to the hull. 46 CFR 32.05-1 (f).
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 September 2006
Resolution: Draft marks painted in contrasting color to the hull.
Construction/Loadline › Markings › Vessel Name/Home Port
Issued 19 September 2006
Resolved
Make vessels number or name where it can be seen by either side. 46 CFR 32.05-15
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 September 2006
Resolution: Vessel name painted on stern and both sides.