MAURY USCG vessel records
← All vessels

SEA SCOUT

SEA SCOUT is a 1953 freight ship. The Coast Guard has recorded 25 inspections since 2016, most recently in April 2026, along with 41 deficiencies, 5 operational controls and 1 casualty investigation in 2020.

Records from 2016 to 2026. Most recent: inspection, 8 April 2026.

Built
1953
Last inspected
8 April 2026
Documentation
Valid · documentation file of 10 August 2026
Controls
None recorded without a removal date

Everything above is free. The detail below — the inspection history, the deficiency record, the operational controls, the casualty record and the documentation record — is Professional, $39 a month. Sign in.

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the General Dry Cargo Ship class in Maury's sources begin in 2016.

Inspection record

Last inspected 8 April 2026
…with no type recorded2
Operational controls None recorded without a removal date
Years with a record 11 calendar years (2016–2026)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Identity

WDJ5661
815496
Flag
UNITED STATES
Maury page id
psix-815496

Documentation record

Registered dimensions (L × B × D)73.5 ft × 21.0 ft × 9.3 ft
Registered tonnagegross 96 / net 76
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderHIGGINS INCORPORATED · NEW ORLEANS, LA, UNITED STATES · built 1953
Hull materialSteel
PropulsionDiesel
Hull shapeShip
Hull configurationMonohull
Hailing portLOS ANGELES, CA
Trade endorsementsCoastwise, unrestricted, Registry
DocumentationValid · issued 4 December 2025 · expires 31 December 2026
Service, as the file records itFreight Ship
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it96 - Simplified, Gross Ton
76 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Professional
Detail on this page

25 inspections, each with its date, unit and type; 41 deficiencies with the resolution recorded against each; 5 operational controls with the dates imposed and removed; 1 casualty investigation, with date and classification; the documentation record: dimensions, tonnage, builder, hailing port, endorsements, dates. The counts in the summary above are the same counts, and they are free.

$39 a month or $299 a year, every vessel page, cancel any time. Founding rate $19.99 a month for life, for the first 200 subscribers. Plans Sign in

Maury does not score, rate or grade vessels, at any price.

Vessel history report
Every record for this hull, in one document — $299

Every recorded inspection, 2016 to 2026 for this class, in one chronology · every deficiency, with system, dates and resolution · operational controls imposed and removed · every name this hull has been recorded under · the vessels it was inspected alongside, and when · how its record compares with hulls of similar age and size, as a fact about the population and never a judgement about this vessel.

Read one first, in full: a forty-year chronology · a hull that changed operators four times · the sparse case, shown as an example, not for sale.

This report is in development and is not for sale yet. There is no date, and nothing is charged. Leave an email and we will tell you when it exists, once.

Inspection history · 25

8 April 2026 Drydock Exam · Internal Structural Exam
Physical examination · Sector San Diego · USCG Southwest District (CGD-SW) · Activity 8325382
13 March 2026 Administrative Inspection
Administrative · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8325718
28 October 2025 Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8249633
17 September 2025 Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8135266
28 August 2025 Administrative Inspection
Administrative · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8220091
30 September 2024 Annual Inspection · Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7982163
31 January 2024 Examination of Repairs · Internal Structural Exam · Drydock Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7816762
26 October 2023 Annual Inspection · Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7784870
12 October 2022 Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7546739
12 January 2022 Drydock Exam · Internal Structural Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7379682
2 August 2021 COI Inspection · Deficiency Check
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7270609
12 July 2021 Administrative Inspection
Administrative · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7253694
8 October 2020 Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7074123
30 September 2020 Administrative Inspection
Administrative · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7068498
25 June 2020 Damage Survey
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6993974
23 June 2020 Type not recorded
No type recorded · Sector San Diego · USCG Southwest District (CGD-SW) · Activity 7128304
22 June 2020 Type not recorded
No type recorded · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 7279337
3 February 2020 Internal Structural Exam · Drydock Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6866488
24 September 2019 Periodic Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6820210
23 September 2019 In-Service Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6819095
12 September 2019 In-Service Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6751243
14 September 2018 Annual Inspection
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6538445
3 January 2018 Deficiency Check · Hull Examination
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 6327994
5 September 2017 Annual Inspection
Physical examination · Sector San Diego · USCG Southwest District (CGD-SW) · Activity 6260164
15 June 2016 COI Inspection · DAPI Audit
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 5896377

Deficiency record · 41

07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 17 September 2025 Resolved
If natural ventilation is provided for in a space protected by a clean agent extinguishing system, the ventilation must be capable of being easily and effectively closed off. Multiple vent louvers on ventilation to engine room unable to close or be secured. Repair louvers and provide means to secure vents closed.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 8 October 2025
Resolution: Vessel proved proper operation of (06) ventilation closures
02 - Structural Conditions › N/A - No Subsystem › Decks - corrosion
Issued 17 September 2025 Resolved
In general, compliance with the standards established by the American Bureau of Shipping, see subpart 90.35 of this subchapter, will be considered as satisfactory evidence of the structural efficiency of the vessel. Found an approximately three (03) inch in diameter wastage/hole in aft deck, creating down flooding hazard into the lazarette. Submit repair plan for MI approval.
Action required: 60 - Rectify deficiencies prior to movement
Resolved 8 October 2025
Resolution: Previous MI was able to attend the crop out, fit up and first pass for the repair on both the aft Port & Stbd main deck. Attending MI visually inspected final weld as well as completed a satisfactory NDT test.
11 - Life Saving Appliances › N/A - No Subsystem › Distress flares
Issued 17 September 2025 Resolved
Each vessel must—(1) Carry not less than 12 rocket parachute flares approved under approval series 160.136. Flares onboard are not the approved rocket parachute flares. Replace flares with rocket parachute flares.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 8 October 2025
Resolution: Vessel had onboard (12) approved rocket parachute flares.
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 17 September 2025 Resolved
The minimum luminous intensity of lights shall be calculated by using the formula (Table 84.14(b)). Stern light luminous range calculated to be substandard. Vessel restricted to daytime operations until light is replaced.
Action required: 705 - Other - as specified
Resolved 8 October 2025
Resolution: Stern light renewed.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 17 September 2025 Resolved
No more than 19 liters (five gallons) of flammable liquids may be stowed in any machinery space. The flammable liquids must be in containers of 3.8 liters (one gallon) or less. Vessel found with multiple hydraulic and lube oil containers larger than 5 gallons in the Engine room. Remove excessive combustible liquids.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2025
Resolved 8 October 2025
Resolution: Excess hydraulic and lube oil containers were removed from E/R.
09 - Working and Living Conditions › 092 - Working Conditions › Obstruction/slipping, etc.
Issued 17 September 2025 Resolved
All crew spaces are to be constructed and arranged in a manner suitable to the purpose for which they are intended and so that they can be kept in a clean, workable, and sanitary condition. Galley fridge not secured to deck or bulkhead creating a potential safety hazard to crew. Properly secure fridge to deck or bulkhead.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2025
Resolved 8 October 2025
Resolution: Galley fridge was properly secured.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 17 September 2025 Resolved
Electric installations on vessels must ensure, protection of passengers, crew, other persons, and the vessel from electrical hazards. Outlet on center support in engine room found without a cover. Install cover.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2025
Resolved 8 October 2025
Resolution: outlet cover in E/R renewed.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 17 September 2025 Resolved
In general, connections and terminations to all conductors must retain the original electrical, mechanical, flame-retarding, and, where necessary, fire-resisting properties of the cable. All connecting devices must be suitable for copper stranded conductors. Dead end cables identified under operating station. Remove or secure dead end cables.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2025
Resolved 8 October 2025
Resolution: dead end cables removed.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 17 September 2025 Resolved
With the exception stated in paragraph (a)(2) of this section, it shall be the responsibility of the master to assure himself that all exposed cargo hatches and other openings in the hull of his vessel are closed, made properly watertight by the use of tarpaulins, gaskets or similar devices, and in all respects properly secured for sea before leaving protected waters. Port cover for #2 void found damaged and unable to properly close. Repair or replace cover.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 October 2025
Resolved 8 October 2025
Resolution: Vessel made new cover for #2 void
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 17 September 2025 Resolved
A pipe joint or a hose connection fitting that has a gasket must be electrically bonded. Port and Stbd fuel tank pipes on top of the tanks found with flexible hose in line with no bonding. Provide bonding to fuel tank piping.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 October 2025
Resolved 8 October 2025
Resolution: Port & Stbd fuel tank pipes were properly bonded.
11 - Life Saving Appliances › N/A - No Subsystem › Radio life-saving appliances
Issued 17 September 2025 Resolved
To enhance protection of life and property it is mandatory that each 406.0-406.1 MHz EPIRB be registered with NOAA before installation and that information be kept up-to-date. EPIRB registered to wrong call sign. Update EPIRB registration.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 October 2025
Resolved 8 October 2025
Resolution: Vessel EPIRB was properly registered with proper call sign on COI.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 17 September 2025 Resolved
You must contact the cognizant Officer in Charge, Marine Inspection to schedule an inspection at a time and place which he or she approves. No written application is required. MI unable to complete annual inspection. Vessel must clear the three (03) action code 60c and the one (01) action code 17c prior rescheduling annual inspection and the carriage of passengers/cargo.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 9 October 2025
Resolution: Vessel cleared (03) 60's & (01) 17 & scheduled annual inspection for 28OCT25.
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 30 September 2024 Resolved
Attachments and fittings. Lifejackets must have the following attachments and fittings:(i) Each lifejacket must have a lifejacket light approved under approval series 161.112 securely attached to the front shoulder area of the lifejacket. Life jacket lights were either inoperable or had expired batteries.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 14 October 2024
Resolved 22 October 2024
Resolution: New lights installed.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Railing, gangway, walkway and means for safe passage
Issued 30 September 2024 Resolved
All vessels shall have efficient guard rails or bulwarks on decks and bridges. The height of rails or bulwarks shall be at least 39.5 inches from the deck except that where this height would interfere with the normal operation of the vessel, a lesser height may be approved by the Commandant. At exposed peripheries of the freeboard and superstructure decks, the rails shall be in at least three courses, including the top. The opening below the lowest course shall not be more than 9 inches. The courses shall not be more than 15 inches apart. Section of railing in aft port quarter, aft midship are broken and or missing courses. Also, hand rail on wheelhouse roof fractured at base on afterside.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 14 October 2024
Resolved 22 October 2024
Resolution: All rails repaired.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Doors
Issued 30 September 2024 Resolved
The stairways, corridors, and doors shall be so arranged as to permit a ready and direct access to the various lifeboat embarkation areas. Port side railing is bent inward in way of port side main cabin emergency exit door. This, combined with the bent outside door lever, restricts the opening to just 14 inches.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 14 October 2024
Resolved 22 October 2024
Resolution: Proper operation witnessed.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 26 October 2023 Resolved
During the term of the vessel's certificate of inspection, the vessel must be in compliance with its conditions. Deficiencies 2, 3, 5, 6, 7, and 9 provide objective evidence that the vessel is substandard and not pro-actively managing technical and operational requirements. Vessel must complete a satisfactory COI re-inspection prior to any movement.
Action required: 30 - Ship detained
Resolved 2 November 2023
Resolution: Attended vessel. Verified the proper operation of the vessel to remove Port State Detention for substandard vessel.
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 26 October 2023 Resolved
Each arrangement for the storage, distribution, and use of oil in a pressure-lubrication system must as well as comply with § 56.50–80, be such as to ensure the safety of the vessel and all persons aboard. All 04 fuel filter housings supplying fuel to both MDE's are leaking fuel with fuel accumulating on the deck plates and bilge.
Action required: 30 - Ship detained
Resolved 2 November 2023
Resolution: Verified fuel leaks have been corrected.
04 - Emergency Systems › N/A - No Subsystem › Fire drills
Issued 26 October 2023 Resolved
Every crewmember with emergency duties assigned on the muster list must be familiar with their assigned duties before the voyage begins. Crewmembers were unfamiliar with their duties during emergency drills.
Action required: 30 - Ship detained
Resolved 2 November 2023
Resolution: Conducted drills. Verified crewmember familiarity with procedures.
02 - Structural Conditions › N/A - No Subsystem › Closing devices/watertight doors
Issued 26 October 2023 Resolved
For each watertight door which is in a required subdivision bulkhead, an indicator light must be installed in the pilothouse and at each other vessel operating station from which the door is not visible. The indicator must show whether the door is open or closed. Indicator light in the pilot house does not recognize if the watertight door is open or closed.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 November 2023
Resolved 9 November 2023
Resolution: Master esnure alarms on bridge were operable
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance and inspections
Issued 26 October 2023 Resolved
Each inflatable lifesaving appliance and marine evacuation system must be serviced within 12 months of each subsequent servicing. Liferaft annual service lapsed on 12OCT2023.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 2 November 2023
Resolution: Life raft has been sent out for service. Vessel has a loaner from the servicing company that has proper annual certification.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 26 October 2023 Resolved
Approved portable fire extinguishers and semi-portable fire extinguishing systems must be installed in accordance with Table 95.50–10(a) of this section. The location of the equipment must be to the satisfaction of the Officer in Charge, Marine Inspection. Portable fire extinguishers are not installed with the required brackets identified on the fire extinguisher.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 2 November 2023
Resolution: Verified E/R fire extinguisher is mounted with required bracket.
11 - Life Saving Appliances › N/A - No Subsystem › On board training and instructions
Issued 26 October 2023 Resolved
Every crewmember must participate in at least one abandon-ship drill and one fire drill every month. MI observed no entries in log book indicating drills are being conducted.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 2 November 2023
Resolution: Verified monthly drills are being documented.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 26 October 2023 Resolved
Each panelboard must have a circuit directory cardholder that has the circuit designation of each circuit. Multiple breakers in the engine room 110v panel do not have labels identifying the equipment being served.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 2 November 2023
Resolution: Verified all breakers are labeled in E/R panel.
11 - Life Saving Appliances › N/A - No Subsystem › Maintenance of Life Saving Appliances
Issued 26 October 2023 Resolved
The following types of retro-reflective material are approved under this specification: Type II—Weather resistant material used on continuously exposed rigid surfaces. MI observed 02 life ring buoys with weather-deteriorated type II retro-reflective tape.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 2 November 2023
Resolution: Verified type II retro tape was replaced on 02 life rings.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 12 October 2022 Resolved
The registers used in connection with cargo gear certification must have all required entries fully completed as of the dates indicated, shall be kept current, and shall include the following: Register of the cargo handling machinery and the gear accessory thereto, certification of the testing and examination of winches, derrecks, and their accessory gear; certification of the wire rope. Master provided 2017 Crane certificate (CAL-OSHA) indication quadriennial test due OCT (correction AUG 1) 2021, with annual checks between. No record of Quadriennial test in 2021 provided. Annual tests through 2019 provided, and wire rope and socket data provided. Quadriennial test data sticker provided for OCT 11, 2022, but not information as to the weight tests completed. (705c, prior to operation of crane)
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Resolved 13 October 2022
Resolution: Vessel provided evidence of crane inspection on 11 OCT 2022.
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 12 October 2022 Resolved
Fire hazards to be minimized. Hydraulic oil on lazarette deck plates and in engine room.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 13 October 2022
Resolution: Hydraulic oil leak was repaired and area cleaned
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 12 October 2022 Resolved
Multiple cables should be supported in metal hangers or trays, arranged as far as practicable. Mettalic band stripping used for all cable support should be steel and corrosion treated if not in corrosion resistant material. The support for all cables should be such to prevent undue sag, but in no case should exceed the distance between frames or 610 mm, whichever is less. Wiring cable above the port engine was supported by plastic cables.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 13 October 2022
Resolution: proper supports were installed.
11 - Life Saving Appliances › N/A - No Subsystem › Stowage and provision of Lifeboats
Issued 2 August 2021 Resolved
Each survival craft must be stowed in a secure and sheltered position...six-man life raft found loose with securing line able to slip off raft.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 16 August 2021
Resolved 4 August 2021
Resolution: Secured liferaft with new line and added bracket/turnbuckle to properly seat the raft on the mount.
09 - Working and Living Conditions › 091 - Living Conditions › Medical Equipment
Issued 2 August 2021 Resolved
Medical chest and first aid kit found expired.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 16 August 2021
Resolved 4 August 2021
Resolution: Renewed first aid kit with new stock.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 12 July 2021 Resolved
Your vessel may not be operated without having on board a valid U.S. Coast Guard Certificate of Inspection. Your Certificate of Inspection, valid for 5 years from 15JUN2016 - 15JUN2021, has expired. Vessel must complete a satisfactory COI Inspection, prior to departure.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 12 July 2021
Resolved 2 August 2021
Resolution: Def Cleared, Completed Exam
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 30 September 2020 Resolved
YOUR VESSEL MUST UNDERGO AN ANNUAL INSPECTION WITHIN THE 3 MONTHS BEFORE OR AFTER EACH ANNIVERSARY DATE. VESSEL IS OVERDUE FOR AN ANNUAL INSPECTION. VESSEL MUST COMPLETE AN ANNUAL INSPECTION PRIOR TO CONDUCTING CARGO.
Action required: 701 - Prior to carriage of passengers/cargo
Due 30 September 2020
Resolved 8 October 2020
Resolution: Annual examination conducted.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 12 September 2019 Resolved
It shall be the duty of the Master or other Person in Charge of the vessel to see that all provisions of the COI are strictly adhered to. Vessel failed periodic COI inspection. 46 CFR 97.50-1 (a)
Condition: Improper/Lack of Maintenance
Action required: 60 - Rectify deficiencies prior to movement
Resolved 23 September 2019
Resolution: Completed periodic inspection.
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 12 September 2019 Resolved
Periodic inspection. Your vessel must undergo a periodic inspection within 3 months before or after the second or third anniversary of the date of your vessel's Certificate of Inspection. This periodic inspection will take the place of an annual inspection. Vessel shall be a Periodic Inspection. 46 CFR 91-27.1 (b)
Condition: Improper/Lack of Maintenance
Action required: 60 - Rectify deficiencies prior to movement
Resolved 23 September 2019
Resolution: Completed Periodic Inspection
11 - Life Saving Appliances › N/A - No Subsystem › Distress flares
Issued 12 September 2019 Resolved
Distress signals. Each vessel must carry not less than 12 rocket parachute flares approved under approval series 160.136; and stow the flares on or near the vessel's navigating bridge. Vessel only had 04 hand night flares and 3 day smokes signals onboard. 46 CFR 199.60 (c)
Condition: Placed in Improper Service
Action required: 60 - Rectify deficiencies prior to movement
Resolved 23 September 2019
Resolution: Vessel has 12 rocket flares onboard stowed in the pilot house.
07 - Fire Safety › N/A - No Subsystem › Remote Means of control (opening,pumps,ventilation,etc.) Machinery spaces
Issued 12 September 2019 Resolved
Shutoff valves. Shutoff valves shall be installed in the fuel supply lines, one as close to each tank as practicable, and one as close to each fuel pump as practicable. Remote fuel shutdown for FWD starboard fuel tank was inoperable. 46 CFR 56.50-75 (b) (4)
Condition: Improper/Lack of Maintenance
Action required: 60 - Rectify deficiencies prior to movement
Resolved 23 September 2019
Resolution: FO remote shutdowns tested for all (04) fuel tanks, all sat.
01 - Certificates & Documentation › 013 - Documents › Log-books/compulsory entries
Issued 12 September 2019 Resolved
The actions and observations noted in this section shall be entered in the official log book. This section contains no requirements which are not made in other portions of this subchapter, the items being merely grouped together for convenience. (a) Onboard training, musters, and drills: held in accordance with subchapter W (Lifesaving appliances and Arrangements) of this chapter. There no records of current drills and training being conducted onboard. 46 CFR 97.35-5
Condition: Invalid
Action required: 60 - Rectify deficiencies prior to movement
Resolved 23 September 2019
Resolution: Vessel has logged and perfromed required monthly drills.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 12 September 2019 Resolved
All other openings to a protected space must be capable of being closed. Doors, shutters, or dampers must be installed for openings in the lower portion of the space. Openings in the upper portion of the space must be capable of being closed off either by permanently installed means or by the use of canvas or other material normally carried on the vessel. Cable penetrations from the battery spaces to the engine room were found to be completely unsealed. 46 CFR 95.16-30 (c)
Condition: Improper Installation
Action required: 60 - Rectify deficiencies prior to movement
Resolved 23 September 2019
Resolution: Penetrations sealed with foam fire block.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Bilge pumping arrangements
Issued 12 September 2019 Resolved
The respective piping systems installed on ships and barges shall have the necessary pumps, valves, regulation valves, for safe and efficient operation of the vessel. Bilge suction lines STBD FWD fuel tank void were found to be leaking from flexible joints. 46 CFR 56.01-1 (b)
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 23 September 2019
Resolution: Operationally tested all bilge suctions(09), all sat.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Ventilators, air pipes, casings
Issued 12 September 2019 Resolved
Nothing in this subpart shall be construed as limiting the inspector from making such tests or inspections as he deems necessary to be assured of the safety and seaworthiness of the vessel. Cable penetrations on FWD bulkhead of battery room are unsealed and not weathertight. 46 CFR 91.25-50 (a)
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Resolved 23 September 2019
Resolution: Penetrations sealed with foam fire block.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 12 September 2019 Resolved
Flexible hose connections should maintain metallic contact between the sections of the fuel-supply lines; however, if they do not, the fuel tank must be grounded. FWD fuel tanks have flexible hoses installed and do not have bonding between filling and tank. 46 CFR 56.50-70 (b) (2)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 27 September 2019
Resolved 23 September 2019
Resolution: Electrical bonding cable added to both FWD fuel tanks.
Lifesaving › Rigid Liferafts › Carriage Requirement
Issued 5 September 2017 Resolved
Provide LR/IBA prior to operating beyound a LBS route.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 6 October 2017
Resolved 4 January 2018

Casualty record · 1

22 June 2020Routine · role: Involved in a Marine Casualty · activity 7279337
Each line is an incident investigation the Coast Guard recorded with this hull among the vessels involved, with the date and the classification the Coast Guard gave it. Involvement is not fault. The investigation narrative is not published. Source: IIR, through 2026.

Ownership record