Records in 2019. Most recent: inspection, 11 April 2019.
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Other (ISM)
Issued 11 April 2019
Resolved
The company should establish procedures to ensure that the ship is maintained in conformity with the provisions of the relevant rules and regulations and with any additional requirements which may be established by the company. In meeting these requirements, the company should ensure that: Inspections are held at appropriate intervals; any non conformity is reported, with its possible cause, if known; appropriate corrective action is taken; and records of activities are maintained. Objective evidence discovered during the COC inspection revealed the following non-conformities which contributed to a serious systematic failure and lack of implementation of the SMS policy onboard in the areas of training, familiarization, record keeping, and maintenance.
-Vessel's PMS, code 20126, for Fire Fighters Outfit Inspection requires "Check all Fireman's Outfits are in place, properly arranged, and is in serviceable condition." Vessel is required to have four firefighting outfits; three on board were discovered to be no longer serviceable due to delamination of heat radiating and water resistant foil. Firefighting outfit’s were documented as being satisfactory on 07MAR2019. -As per Ship's Cargo Operations Manual 6.4: "It is important that the integrity of the cargo tanks and venting system is maintained to prevent loss of inert gas or ingress of air. Any reported leaks must be repaired at the earliest opportunity..." PSCOs observed a clamp-type patch approximately 3"x3" on the vessels inert gas distribution line. Inert Gas is escaping from the patch and can be heard hissing from the vessel’s raised catwalk and port walkway. The vessel’s [name withheld] reported that the patch had been there for approximately 3-4 months. There is no record of deterioration to the pipe or application of the temporary repair, and there is no documentation attesting to a plan for permanent repair.
-Page 41 of the Vessels training manual has a time requirement and training standard of two minutes. During the abandon ship drill it was discovered that crew members had not been adequately trained in the use of the immersion suits on board the vessel. Only two crew members were able to properly don the on board immersion suit and required life jacket. After further training and instruction, crew demonstrated proper donning of immersion suits and life jackets but exceeded training manual time requirement by five minutes. Vessel recorded conducting a successful abandon ship drill on 08APR2019.
-Vessel PMS Code 256 “Cargo Line and Manifold Inspection” requires a monthly inspection of the cargo deck equipment to include: “Check the Cargo Line Electrical Bonding for integrity.” Bonding lines on the hazardous area of the deck were discovered to be improperly repaired (1) and detached (1). PMS was completed and the system was documented to be satisfactory 25MAR19.
Condition: Placed in Improper Service
Action required: 17 - Rectify deficiencies prior to departure
Due 26 April 2019
Resolved 15 April 2019
Resolution: Received ISM audit report. CG witnessed satisfactory abandon ship drill.
04 - Emergency Systems › N/A - No Subsystem › Emergency source of power - Emergency generator
Issued 11 April 2019
Resolved
Where the emergency source of electrical power is a generator, it shall be: Started automatically upon failure of the main source of electrical power supply unless a transitional source of emergency electrical power in accordance with paragraph 3.1.3 is provided. While testing the emergency generator with the Electrician and Chief Engineer, the emergency generator failed after two seconds of operation. Upon further examination of the system and the fuel tank supply line, it was observed that the fuel shut off valve was in the closed position. No crew member knew why or how long the fuel valve had been in the closed position.
Action required: 17 - Rectify deficiencies prior to departure
Due 26 April 2019
Resolved 12 April 2019
Resolution: Vessel examined EG and ensured all machinery was immediately ready for operation. CG witnessed satisfactory test.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo transfer - Tankers
Issued 11 April 2019
Resolved
For tankers of 20,000 tonnes deadweight and upwards, the protection of the cargo tanks shall be achieved by a fixed inert gas system in accordance with the requirements of the Fire Safety Systems Code, materials used in inert gas systems shall be suitable for their intended purpose. PSCOs observed an unapproved clamp-type patch (3"x3") on the vessel's inert gas system. Inert gas is escaping from the patch and can be heard hissing from the vessel's raised catwalk and port walkway. The vessel's third mate reported that the patch had been there for approximately 3-4 months. No further documentation was available. Neither the vessel's Captain or Chief Mate were aware of the patch.
Condition: Improper/Lack of Maintenance
Action required: 60 - Rectify deficiencies prior to movement
Due 26 April 2019
Resolved 15 April 2019
Resolution: Class report received.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo transfer - Tankers
Issued 11 April 2019
Resolved
A cargo tank of the tank vessel connected to a vapor collection system must be equipped with a permanent or portable cargo gauging device that — is a closed type as defined in 46 CFR 151.15.10(c) that does not require opening the tank to the atmosphere during cargo transfer. In the CCR, PSCOs found displays for tank level readings for tanks 3S ,4S, and 7S to be malfunctioning.
Action required: 60 - Rectify deficiencies prior to movement
Due 26 April 2019
Resolved 15 April 2019
Resolution: Class report received. Witnessed new display in satisfactory performance.
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 11 April 2019
Resolved
Where cables which are installed in hazardous areas introduce the risk of fire or explosion in the event of an electrical fault in such areas, special precautions against such risk shall be taken to the satisfaction of the Administration. PSCO found multiple wires on deck not connected to the ship’s wire bonded grounding system along with wires that had exposed conductor/metal.
Action required: 60 - Rectify deficiencies prior to movement
Due 26 April 2019
Resolved 12 April 2019
Resolution: Crew fixed wire bondings. CG observed all observed electrical bonding to be intact.
07 - Fire Safety › N/A - No Subsystem › Personal equipment for fire safety
Issued 11 April 2019
Resolved
Personal equipment shall consist of the following: protective
clothing of material to protect the skin from the heat
radiating from the fire and from burns and scalding by steam.
Vessel is required to have 4 firefighting outfits; 4 are
on board but three are no longer serviceable due to delamination
of heat radiating and water resistant foil.
Action required: 17 - Rectify deficiencies prior to departure
Due 26 April 2019
Resolved 12 April 2019
Resolution: Vessel received 4 new fire-fighter's outfits. CG observed crew in new fire-fighter's outfits. Old suits to be used for training.
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 11 April 2019
Resolved
The hull, superstructure, and deckhouses in way of accomodation and service spaces shall be subdivided into main vertical zones by "A" class divisions. Wire runs are being passed through "A" class boundaries without proper intumescent material.
Action required: 17 - Rectify deficiencies prior to departure
Due 26 April 2019
Resolved 12 April 2019
Resolution: Crew filled cable pentrations. CG observed satifactory fire boundaries.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 11 April 2019
Resolved
Means shall be provided to control leaks of flammable liquids.PSCOs observed hydraulic oil in the vicinity of the vessel's foam testing tank. Hydraulic oil covered the floor of the containment and coated the nearby bulkhead up to 5 inches off the deck. Exact source of leak is unknown.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 May 2019
Resolved 15 April 2019
Resolution: Class report received.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 11 April 2019
No resolution recorded
The machinery, boilers, and other pressure vessels, associated piping systems and fittings shall be of a design and construction adequate for the service for which they are intended and shall be so installed and protected as to reduce to a minimum any danger to persons on board, due regard being paid to moving parts, hot surfaces and other hazards. PSCO observed water dripping (multiple drops a second) from Main Engine Jacket Preheater and the Fresh Water pump. According to Chief Engineer [name withheld] Preheater gasket and the Fresh Water pump mechanical seal are failing and need to be replaced. No records of the issue were available.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 May 2019 — due date passed with no resolution recorded
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 11 April 2019
Resolved
Means shall be provided to control leaks of flammable liquids. PSCOs observed pooling of fuel oil underneath the vessel's #3 generator.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 May 2019
Resolved 15 April 2019
Resolution: Class report received.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 11 April 2019
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. PSCOs onboard observed an unapproved clamp-type patch on the galley's AC raw water intake.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 11 May 2019
Resolved 15 April 2019
Resolution: Class report received. Vessel was given a timeline that matches their scheduled dry-dock.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 11 April 2019
Resolved
Use of combustible materials shall be restricted. PSCOs observed a gear locker containing some required life-saving equipment and some spare equipment being stored in a locker with
oil camping lamps and flammable adhesives.
Action required: 10 - Deficiency Rectified
Due 12 April 2019
Resolved 12 April 2019
Resolution: Resolved to satisfaction of PSCO.
07 - Fire Safety › N/A - No Subsystem › Means of escape
Issued 11 April 2019
Resolved
Escape routes shall be maintained in a safe condition, clear of obstacles. PSCOs observed 02 exterior weather-tight doors unable to open as designed. Doors required two crew members to open them.
Action required: 10 - Deficiency Rectified
Due 12 April 2019
Resolved 12 April 2019
Resolution: Deficiency resolved to satisfaction of PSCO.