← All vessels
CARIBBEAN EXPRESS I
CARIBBEAN EXPRESS I is a 2000 freight ship. The Coast Guard has recorded 35 inspections since 2016, most recently in July 2026, along with 22 deficiencies and 3 operational controls.
Records from 2016 to 2026. Most recent: inspection, 15 July 2026.
- Built
- 2000
- Last inspected
- 15 July 2026
- Documentation
- Not in the documentation file of 10 August 2026
- Deficiencies
- 22 recorded · 0 without a recorded resolution
- Controls
- None recorded without a removal date
Identity
1098540
9233727
V2YG4
9308
Flag
ANTIGUA AND BARBUDA
Maury page id
psix-9308
Inspections, by type
…with no type recorded2
Years with a record
11 calendar years (2016–2026)
The 35 inspections in the strip above, split by the kind of activity the US
Coast Guard recorded. Years with a record are calendar years in which a record exists, not
years in service. What Maury does not do.
Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Ro-Ro Cargo Ship class in Maury's sources begin in 2016.
Documentation record
Tonnage as PSIX records it499 - Convention (Subpart B), Gross Ton
499 - Simplified, Gross Ton
156 - Convention (Subpart B), Net Ton
499 - Simplified, Gross Ton
156 - Convention (Subpart B), Net Ton
This hull's Official Number is not in the NVDC file dated 10 August 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.
One vessel history report for this hull — every record on this page in one dated, citable document — $300, on request.
Inspection history · 35
15 July 2026
PSC B · Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 8438658
17 March 2026
Administrative Inspection
Administrative · Sector Miami · USCG Southeast District (CGD-SE) · Activity 8327376
6 January 2026
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 8290798
14 August 2025
Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 8209999
11 August 2025
PSC B · CCSSC Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 8207260
6 August 2025
Administrative Inspection
Administrative · Sector Miami · USCG Southeast District (CGD-SE) · Activity 8203584
5 February 2025
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 8074486
31 July 2024
PSC B · CCSSC Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7966669
5 June 2024
Type not recorded
No type recorded · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7929224
5 April 2024
Type not recorded
No type recorded · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7890481
25 January 2024
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7855601
24 July 2023
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7750499
23 January 2023
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7625071
19 January 2023
Administrative Inspection
Administrative · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7623933
14 January 2023
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7621522
6 August 2022
Administrative Inspection · Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7525956
8 July 2022
PSC B · Ballast Water Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7499749
5 January 2022
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7375535
23 June 2021
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7232990
17 March 2021
Administrative Inspection
Administrative · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7158012
15 December 2020
PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 7107984
29 May 2020
Administrative Inspection · PSC B
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6963610
5 November 2019
ISPS III Exam · CCSSC Examination · Ballast Water Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6849337
7 May 2019
ISPS III Exam · CCSSC Examination · PII Safety Exam
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6678495
2 April 2019
Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6654267
21 January 2019
Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6612857
13 November 2018
Deficiency Check · Ballast Water Examination · Administrative Inspection · CCSSC Examination · ISPS II Exam · PII Safety Exam
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6579402
16 May 2018
MTSA Verification · Ballast Water Examination · CCSSC Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6414739
16 November 2017
MTSA Verification · CCSSC Examination · Ballast Water Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6308267
19 May 2017
CCSSC Examination · Ballast Water Examination · ISPS II Exam
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6149964
23 February 2017
Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6093231
14 November 2016
CCSSC Examination · MTSA/ISPS Verification
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6040387
17 October 2016
Administrative Inspection
Administrative · Sector Miami · USCG Southeast District (CGD-SE) · Activity 6024070
6 May 2016
ISPS II Exam · CCSSC Examination
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 5870260
19 February 2016
Administrative Inspection · Deficiency Check
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 5818553
Deficiency record · 22
01 - Certificates & Documentation › 013 - Documents › Oil record book
Issued 15 July 2026
Resolved
...Each complete page...shall be signed by the Master of the ship. Complete pages in the ORB have not been signed by the Master since 04MAY2026.
MARPOL I/17.4
15c
01 - Certificates & Documentation › 013 - Documents › Oil record book
Issued 15 July 2026
Resolved
The Oil Record Book shall be completed on each occasion...whenever any of the following machinery space operations take place in the ship: collection and disposal of oil residues(sludge). Since February, three distinct discrepancies in the disposal of sludge are recorded in the ORB. Between 22FEB2026 and 05MAR2026, 0.32m^3(84.5 gallons) of sludge is unaccounted. Between 18MAR2026 and 21MAR2026, 0.04m^3(10.5 gallons) of sludge is unaccounted. Between 22MAY2026 and 17JUN2026, 0.037m^3(9.5 gallons)of sludge is unaccounted. In total, 0.397m^3(105 gallons) of sludge is unaccounted. Vessel must provide 30 days worth of ORB entries on the due date of this deficiency.
MARPOL I/17.2.3
50c
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 15 July 2026
Resolved
...Each transfer pipe system, including each metallic hose, must not leak under static liquid pressure at least 1 1/2 times the maximum allowable working pressure. Vessel has not hydrostatically tested their fuel bunker lines since October 2022. A test must be completed prior to bunkering in U.S. waters.
33 CFR 154.170(c)(4)
40bc
11 - Life Saving Appliances › N/A - No Subsystem › Rescue boat inventory
Issued 15 July 2026
Resolved
Life-saving appliances required by this chapter should comply with the technical specifications of the LSA Code. The normal equipment in every rescue boat shall consist of: a searchlight with a horizontal and vertical sector of at least 6deg and a measured luminous intensity of 2500 cd which can work continuously for not less than 3 hours. Rescue boat does not have a searchlight.
CCSSC 4.3.1
LSA 5.1.2.2.11
40bc
03 - Water/Weathertight Conditions › N/A - No Subsystem › Other (load lines)
Issued 15 July 2026
Resolved
The rings, lines, and letters shall be..permanently marked on the sides of the ship to the satisfaction of the administration. Vessel's "F" and "S" marking for the Freshwater and Summer Line are not permanently marked on either side of the vessel.
ILLC (PROT 88) Reg 8
40bc
14 - Pollution Prevention › 147 - Anti-Fouling › Other (AFS)
Issued 15 July 2026
Resolved
Vessels with ballast water tanks operating in U.S. waters must...remove fouling organisms from the vessel's hull...on a regular basis and dispose of any removed substances. The vessel's hull has significant marine growth on the stern, port quarter, and starboard quarter.
33 CFR 151.2050(F)
40bc
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 6 January 2026
Resolved
Subject to the provisions of 3.16.1.2 and 3.16.1.3, The fire safety requirements of bulkheads, decks, doors and stairways should, as far as practicable and reasonable in the opinions of the administration, comply with the applicable requirements of the 1974 SOLAS convention for such bulkheads, doors and stairways. In addition to complying with the specific provisions for fire integrity of bulkheads and decks of cargo ships, the minimum fire integrity of bulkheads and decks shall be as prescribed in tabled 9.5 and 9.6. PSCO observed fire boundaries for bridge, galley, accommodation spaces, and engine room do not comply with the provisions of table 9.5 of 1974 SOLAS II-2.
CCSSC(97) 3.16.1.1
74 SOLAS (20) II-2/9.2.3.3.1
17bc reduced to 50bc
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 6 January 2026
Resolved
Ventilation systems of each of the following groups of spaces should be entirely separated from each other: 1. Machinery Spaces, 2. Galleys, 3. Cargo spaces and accommodation spaces and control stations. The arrangement of each ventilation system should be such that fire in one space should not readily spread to other spaces. PSCO observed the ship only has one ventilation system to supply all compartments on board.
CCSSC (97) 3.16.6.1
17bc reduced to 50bc
01 - Certificates & Documentation › 011 - Ships Certificates › Document of Compliance Dangerous Goods
Issued 6 January 2026
Resolved
The Administration shall provide the ship with an appropriate document as evidence of compliance of construction and equipment with the requirements of this regulation. Certification for dangerous goods...is not required for those cargoes specified as class 6.2 and 7 and dangerous goods in limited quantities and expected quantities. PSCO observed the vessel's document of Compliance for the Carriage of Dangerous Goods does not accurately reflect the proper loading locations for the dangerous goods.
74SOLAS(20) II-2/19.4
50bc
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 6 January 2026
Resolved
Subject to the provisions of 3.16.1.2 and 3.16.1.3, The fire safety requirements of bulkheads, decks, doors and stairways should, as far as practicable and reasonable in the opinions of the administration, comply with the applicable requirements of the 1974 SOLAS convention for such bulkheads, doors and stairways. In addition to complying with the specific provisions for fire integrity of bulkheads and decks of cargo ships, the minimum fire integrity of bulkheads and decks shall be as prescribed in tabled 9.5 and 9.6. PSCO observed fire boundaries for bridge, galley, accommodation spaces, and engine room do not comply with the provisions of table 9.5 of 1974 SOLAS II-2.
CCSSC(97) 3.16.1.1
74 SOLAS (20) II-2/9.2.3.3.1
50bc
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 6 January 2026
Resolved
Ventilation systems of each of the following groups of spaces should be entirely separated from each other: 1. Machinery Spaces, 2. Galleys, 3. Cargo spaces and accommodation spaces and control stations. The arrangement of each ventilation system should be such that fire in one space should not readily spread to other spaces. PSCO observed the ship only has one ventilation system to supply all compartments on board.
CCSSC (97) 3.16.6.1
50bc
07 - Fire Safety › N/A - No Subsystem › Fire prevention structural integrity
Issued 11 August 2025
Resolved
Bulkheads forming boundaries between cargo spaces and machinery spaces of category A shall be insulated to "A-60" standard. PSCOs ovserved lack of required A-60 insulation in machinery space below stowage of dangerous goods.
74SOLAS(01) II-2/54.28
11 - Life Saving Appliances › N/A - No Subsystem › Launching arrangements for rescue boats
Issued 11 August 2025
Resolved
Life-saving appliances required by this chapter shall comply with the technical specifications of the LSA code and National Regulations as appropriate. Structural members and all blocks, falls, padeyes, links, fastenings and all other fitting used in connection with launching equipment shall be designated with a factor of safety on the basis of the maximum working load assigned and the ultimate strengths of the materials used for construction. A minimum factor of safety of 4.5 shall be applied to all structural members and a minimum factor of safety of 6 shall be applied to falls, suspensions, chains, links, and blocks.
PSCO's observed the the rescue boat weighing 700 lbs with the launching apparaus being aed for a S.W.L. of 1.1 tons, this not meeting safety factors required by the CCS and LSA code.
CCS Code 4.3.1
LSA Code 6.1.1.6
01 - Certificates & Documentation › 013 - Documents › Oil record book
Issued 31 July 2024
Resolved
Every oil tanker of 150 gross tonnage and above and every ship of 400 gross tonnage and above other than an oil tanker shall be provided with an oil record bok part I. The oil record book, whether as a part of the ship's official loogbook or otherwise shall be in form specified in appendix III of this Annex. PSCO's observed weekly soundings were not recorded in the oil record book. MARPOL ANNEX I Reg 17.1
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 14 January 2023
Resolved
If the Coast Guard determine that the VRP meet an requirement all requirement of this subpart, this Coast Guard will notify the vessel owner or operator with an approval letter. The VRP will be valid for a period of 5 years from the date of approval...PSCO's discovered the vessels VRP was expired.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 6 August 2022
Resolved
The owner or Master of every ship to which this code applies shall ensure that: the condition of the ship and its equipment is maintained to conform with the provisions of this code to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship, persons on board, or the environment. Main port side engine experienced loose valve gear in cylinder number 1 while underway.
CCSSC 1.11.1
11 - Life Saving Appliances › N/A - No Subsystem › Launching arrangements for rescue boats
Issued 13 November 2018
Resolved
0635 - Launching Appliances for Rescue boats - Falls shall be of rotation-resistant steel wire rope. PSCO noticed falls on rescue boat davit tangled to create a "birds nest" and require replacement. - CCSSC CH.4.3.1 , LAS Code 6.1.2.3
01 - Certificates & Documentation › 011 - Ships Certificates › Load Lines (including Exemption)
Issued 13 November 2018
Resolved
0120 - Load Line - The international Load Line Certificate (1966) shall not be delivered to the ship until the offer or suveryor acting under the provisions of Article 13 of the present convention has certified that the marks are correctly and permanently indicated on the ships sides. Starboard side load line is marked incorrectly and is not in line witht he plimsoll mark. - ICLL 66/68 Annex 1 reg 9
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 13 November 2018
Resolved
9900- other (non hazardous) - The strength and construction of hull, machinery casing...shall be sufficient to withstand all foreseeable conditions of the intedned service. Port Side shaft seal leaking 1 gallon every 4 minutes. - CCSSC Ch. 2.4.1
Ship to rectify deficiency during dry dock scheduled for January 2019.
Communications › Alarms/Indicators › Rudder Angle Indicator
Issued 16 November 2017
Resolved
The position of the rudder, if power operated, shall be indicated at the navigation bridge. Conning position on the brige has 02 rudder angle indicators that show different readings of up to 6 degrees off from each other.
Lifesaving › Lifebuoys › Self-igniting Lights
Issued 16 November 2017
Resolved
In ships of 50M in length and over at least two of the lifebuoys provided with self-igniting lights IAW 4.12.2 shall also be provided with self activating smoke signals. Port and Starboard lifebuoys fitted with smoke signals had the self-igniting lights removed.
Fire Fighting › Emergency Fire Pumps › Arrangement
Issued 17 October 2016
Resolved
03 - 0740 - CCSSC CHAP 3.3.10.1 AN EMERGENCY FIRE PUMP SHALL BE POSITIONED OUTSIDE THE ENGINE ROOM AND PERMANENTLY CONNECTED TO THE FIREMAINS. THE USE OF PORTABLE FIRE PUMPS SHALL BE AVOIDED. SHIP DOES NOT HAVE FIXED EMERGENCY FIRE PUMP.
Ownership record
The Coast Guard's documentation record for this hull -- the Abstract of Title,
with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National
Vessel Documentation Center, files it here with its date, and every reader of this page gets it.