Records from 2008 to 2025. Most recent: inspection, 29 November 2025.
A report is not offered for this hull: Its record holds only 2 of the seven kinds of material a report is built from: inspections, deficiencies, operational controls, tow-unit appearances, casualty records, dimensions and documentation. That is a statement about the record, not about the vessel. Reports.
Inspection history · 19
29 November 2025
COC-TVE Renew · PSC B
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8274526
26 July 2024
COE-Administrative
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7967728
23 October 2023
COC-TVE Renew · PSC B
Physical examination · Marine Safety Unit Lewes · USCG East District (CGD-E) · Activity 7811023
27 February 2022
COC-TVE Renew · PSC B
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 7400696
2 March 2021
COC-TVE Annual · PSC B
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7144894
28 March 2020
COC-TVE Renew · PSC B
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6928656
1 December 2018
ISPS II Exam · Ballast Water Examination · COC-TVE Renew
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6586828
27 March 2018
In-Service Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 6379733
9 January 2018
COE-Dockside · COC-TVE Annual · ISPS II Exam · Ballast Water Examination
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6329889
11 December 2016
COE-Dockside
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6055796
28 October 2016
ISPS II Exam · COC-TVE Renew · Ballast Water Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6031433
18 April 2016
COE-Administrative
Administrative · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5853654
15 April 2016
COE-Administrative
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5855107
2 September 2015
Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5233443
28 August 2015
ISPS II Exam · COC-TVE Annual · Ballast Water Examination
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5223235
9 August 2014
ISPS II Exam · COC-TVE Renew · Ballast Water Examination
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 4943547
24 December 2008
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3384697
23 June 2008
ISPS II Exam · Administrative Inspection
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3235195
9 March 2008
COC-TVE Renew · MARPOL Annex V Examination · MARPOL Annex I Examination · ISPS II Exam · Ballast Water Examination
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3156183
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 29 November 2025
No resolution recorded
IN TANKERS, ELECTRICAL EQUIPMENT, CABLES AND WIRING SHALL NOT BE INSTALLED IN HAZARDOUS LOCATIONS UNLESS IT CONFORMS WITH STANDARDS NOT INFERIOR TO THOSE ACCEPTABLE TO THE ORGANIZATION.
PSCO OBSERVED 01 CRACKED LIGHT AND APROXIMITLY 13 LIGHTS WITH CABLE GLANDS PACKED WITH PUDDY RATHER THAN BLANKING CAPS IN THE CARGO PUMPROOM.
74SOLAS(20) II-I/45.11
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 23 October 2023
Resolved
Each incinerator on a ship...shall meet the requirements contained in appendix IV to this annex. Each incinerator subject to this paragraph shall be approved by the administration taking into account the standard specification for shipboard incinerators developed by the Organization. The materials used in the individual parts of the incinerator are to be suitable for the intended application with respect to heat resistance. PSCO found gasket to be damaged on incinerator.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 6 November 2023
Resolved 2 November 2023
Resolution: Per class report, incinerator was repaired.
Construction/Loadline › Penetrations › Gasket
Issued 28 August 2015
Resolved
1820 The purpose of this regulation is to prevent the ignition of combustilble materials or flammable liquids. A gas tight cable/piping run passing through the cargo pump room to the engine room is improperly installed allowing unauthorized opening in the required gas tight bulkhead.
74SOLAS(04 Cons) II-2/Part B 4.1.5 34ac prior to discharging
Condition: Improper Installation
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 2 September 2015
Resolution: MSU Port Arthur received class survey report stating that the deficiency has been rectified and tested to function properly.
Deck/Cargo › Holds/Tanks › Fixed Gas Detection
Issued 9 August 2014
Resolved
1840 - Instrumentation - Where the atmosphere in double hull spaces cannot be measured using flexible gas sampling hoses, such spaces shall be fitted with permanent gas sampling lines. The vessels fixed gas detection system is producing multiple fault alarms. 74 SOLAS 2009 CONS. II-2 REG 4.5.7.2.2 / 40c
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 22 September 2014
Resolved 22 September 2014
Resolution: Witnessed satisfactory test of gas detection panel detector with Iso-Butane span gas. Also witnessed low flow alarms to the No.6 (S), No. 5 (S), and No. 4 (S) water ballast tanks gas detection system.