MAURY USCG vessel records Sign in
← All vessels

JAL SIDDHI

JAL SIDDHI is a 2006 tank ship. The Coast Guard has recorded 19 inspections since 2008, most recently in December 2025, along with 18 deficiencies — 2 with no resolution recorded — and 8 operational controls.

Records from 2008 to 2025. Most recent: operational control imposed, 22 December 2025.

Built
2006
Last inspected
14 December 2025
Documentation
Not in the documentation file of 10 September 2026
Controls
None recorded without a removal date

Identity

9323778 View on MarineTraffic leaves Maury; a third-party site, nothing from it is stored here
9V6279
940551
Flag
SINGAPORE
—
Maury page id
psix-940551

Inspections, by type

…with no type recorded10
Years with a record 6 calendar years (2008–2025)
The 19 inspections in the strip above, split by the kind of activity the US Coast Guard recorded. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Coast Guard record current through 13 September 2026, retrieved 18 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Tank Ship class in Maury's sources begin in 1980.

Documentation record

Tonnage as PSIX records it11615 - Convention (Subpart B), Gross Ton
11615 - Simplified, Gross Ton
19805 - Dead Weight, Ton
14907 - Displacement, Ton
6202 - Convention (Subpart B), Net Ton
6202 - Simplified, Net Ton
This hull's Official Number is not in the NVDC file dated 10 September 2026 as served by NOAA Fisheries, so no documentation record is shown. Absence from that file is a fact about the file, not about the hull.

Radio station licence

No FCC ship-station licence is recorded against this Official Number in the file of 6 September 2026. That is a fact about the licence file, not about the radio.

Inspection history · 19

14 December 2025 Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8283745
13 December 2025 Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8283185
26 November 2025 Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8274558
13 November 2025 Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8268373
13 November 2025 Type not recorded
No type recorded · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8270060
24 October 2025 COC-CHEM & TVE Renew · Administrative Inspection · PSC B
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8257642
18 August 2023 Deficiency Check
Physical examination · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 7771401
2 August 2023 PSC B · COC-CHEM Annual
Physical examination · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 7754793
18 May 2023 Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7691687
7 July 2022 COC-CHEM & TVE Renew · PSC B
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 7495738
19 March 2010 Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3699013
8 January 2010 Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3660952
7 April 2009 ISPS II Exam · COC-CHEM Annual
Physical examination · Sector North Carolina · USCG East District (CGD-E) · Activity 3444968
26 September 2008 Type not recorded
No type recorded · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3333202
10 September 2008 Type not recorded
No type recorded · Sector Mobile · USCG Heartland District (CGD-H) · Activity 3321613
24 May 2008 Type not recorded
No type recorded · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3216094
13 May 2008 Deficiency Check
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3205713
28 March 2008 Type not recorded
No type recorded · Marine Safety Unit Wilmington · USCG East District (CGD-E) · Activity 3171658
22 March 2008 Ballast Water Examination · COC-CHEM Renew · ISPS II Exam · MARPOL Annex V Examination · MARPOL Annex I Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 3169288

Deficiency record · 18

07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 24 October 2025 Resolved
Fire doors in main vertical zone bulkheads, galley boundaries and stairway enclosures other than power-operated watertight doors and those which are normally locked shall satisfy the following requirements:the doors shall be self-closing and be capable of closing with an angle of inclination of up to 3.5 degrees opposing closure. PSCO identified more than 8 self-closing doors that did not meet the self-closing requirement including doors in the engine room, the laundry room, and the crew fire locker on the main deck. 74 SOLAS (04) II-2 /9.4.1.1.4 17ac
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 15 November 2025
Resolution: Class attended vessel and verified doors are now able to self-close, after adjustments to the closing devices.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 24 October 2025 Resolved
Electrical installations shall be such that the safety of passengers , crew and ship from electrical hazards will be ensured. PSCO observed exposed wiring going to the AC unit for the wheelhouse. 74 SOLAS (04) II-1/40 17ac
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 15 November 2025
Resolution: Recieved class report exposed wiring was renewed and connected, all sat.
09 - Working and Living Conditions › 092 - Working Conditions › Machinery
Issued 24 October 2025 Resolved
The machinery, boilers, and other pressure pressure vessels, associated piping systems and fittings shall be of a design and construction adequate for the service for which they are intended and shall be installed and protected as to reduce to a minimum any danger to persons on board. PSCO identified a leak in the steam system for jacketwater heating for the main engine. 74 SOLAS (04) II-1 /26.1 40ac
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 15 November 2025
Resolution: Received class report, heater was overhauled and heating plates were replaced with new plates and gaskets. All sat.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 24 October 2025 No resolution recorded
The first non-return device shall be a deck seal of the wet, semi-wet, or dry type or a double block and bleed arrangement. Two shut off valves in series with a venting valve in between, may be accepted provided: the operation of the valve is automatically executed. Signals for opening/closing are to be taken from the process directly and alarm for the faulty operation of the valves is provided. PSCO identified the actuator valves for the nitrogen generator double block and bleed to be severely corroded and operational only manually. The valves could not be automatically executed. 74 SOLAS (04) II-2/4.5.5 FSS 15.2.2.3.1.2 40ac
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 24 October 2025 Resolved
Cylinders must always be secured and, when not in use, they must be stowed in a rack in an upright position, with the valve protection cap in place. PSCO observed full oxygen and acetylene cylinders in store rooms and medical oxygen in the hospital space improperly stored on directly on the deck and fastened with rope. 46 CFR 147.60(b)(1) 40ac
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 15 November 2025
Resolution: Received class report, cylinders were placed on mats and secured using metallic brackets, all sat.
02 - Structural Conditions › N/A - No Subsystem › Ballast, fuel and other tanks
Issued 24 October 2025 Resolved
Following installation, the master, owner, operator, agent, or person in charge of the vessel must properly maintain the BWMS in accordance with all manufacturer specifications. Vessel's ballast water management system is inoperable. Vessel shall not discharge ballast water into U.S. waters. 33 CFR 151.2025(a)1 40ac
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 23 December 2025
Resolution: Received class report stating the satisfactory repair of the BWTS, MI verified the details of the report stating that the BWTS had received repairs and the BWTS was working as intended.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 24 October 2025 No resolution recorded
In addition to the requirements contained elsewhere in the present regulations, ships shall be designed, constructed and maintained in compliance with the structural, mechanical and electrical requirements of a classification society which is recognized by the Administration in accordance with the provisions of regulation XI/1, or with applicable national standards of the Administration which provide an equivalent level of safety. PSCO observed extensive corrosion on exterior decks, bulkheads, ladder ways, guardrails, closures, and piping. PSCO identified temporary patches and wastage on the cargo tank steam lines, tank cleaning lines, and the eyewash station water supply lines. 74 SOLAS (04) II-1/3-1 40ac
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
11 - Life Saving Appliances › N/A - No Subsystem › Operational readiness of lifesaving appliances
Issued 24 October 2025 Resolved
After any survey of the ship under regulations 7,8,9, or 10 has been completed, no change shall be made in the structural arrangements, machinery, equipment and other items covered by the survey, without the sanction of the Administration. PSCO observed designated lifebuoy bracket without lifebuoy. Vessel replaced the lifebouy. Deficiency rectified. 74 SOLAS (20) I/11(b) 40ac
Condition: Damaged By Earlier Event
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 24 October 2025
Resolution: Vessel replaced the life bouy. Deficiency rectified.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 2 August 2023 Resolved
A' class doors shall be constructed as to be capable of preventing the passage of smoke and flame. Stairwell self-closing door was found to be non-self-closing.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 2 August 2023
Resolved 2 August 2023
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo operation
Issued 2 August 2023 Resolved
Each vapor collection flange must have a stud projecting outward located at the top of the flange face. Vapor lines on port/starboard manifolds lack required stud.
Condition: Improper Installation
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 18 August 2023
Resolution: See attached
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo operation
Issued 2 August 2023 Resolved
The last meter of vapor piping must be painted in the sequence of red/yellow/red. Vapor lines on port/starboard manifolds lack required markings.
Condition: Improper Installation
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 18 August 2023
Resolution: See attached
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 7 July 2022 Resolved
Means shall be provided to control leaks of flammable liquids. PSCO observed accumulation of oil around #1 piston head on the #1 generator. Vessel is aware of inoperable gasket, requisition order submitted. 74SOLAS(09)II-2/4.1.1
Action required: 17 - Rectify deficiencies prior to departure
Due 8 July 2022
Resolved 8 July 2022
Resolution: Vessel replaced inoperable gasket and conducted operational test.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 7 July 2022 Resolved
All steering gear components and the rudder stock shall be of sound and reliable construction to the satisfaction of the adiministration. PSCO observed hydraulic oil leaks from both pumps of steering gear system, with unknown source. 74SOLAS(04)II-1/29.2.1
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Due 8 August 2022
Resolved 18 May 2023
Resolution: PSC NOLA RECEIVED A CLASS REPORT SATISFYING THE STEERING GEAR COMPONENT.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 7 July 2022 Resolved
The fire integrity of the divisions shall be maintained at openings and penetrations. PSCO observed 02 self closing doors that were not capable of closing on their own. 74SOLAS(09)II-2/9.1.3
Action required: 10 - Deficiency Rectified
Due 7 July 2022
Resolved 7 July 2022
Resolution: The fire doors are now capable of closing on their own.
Lifesaving › Rescue Boat › Construction
Issued 20 March 2010 Resolved
Cargo ships shall carry at least one rescue boat complying with LSA 5.1 .Repair damage sustained during life boat/ rescue boat drill (to fiberglass hull) to the satisfaction of certificate issuing authority prior to departure from Port Arthur COTP zone. SOLAS 2004 CONS. CH. III REG 31-2
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 21 March 2010
Resolution: Received NKK Class report #10UH0042 dated 21MAR2010 along with a tech report attesting to satisfactory repairs made to the Rescue Boat’s hull and temp repairs to the Sprinkler system with SAT test results, (See note regarding sprinkler head).
Navigation › Collision/Grounding Avoidance › Radar
Issued 20 March 2010 Resolved
A second 9 GHZ radar which is functionally independent required by SOLAS V , REG 19-2.2. Radar functions intermittently. Repair to the satisfaction of Certificate issuing authority prior to departure from MSU Port Arthur COTP Zone . SOLAS 2004 CONS. CH V REG. 19-2.7
Condition: Unknown
Action required: 17 - Rectify deficiencies prior to departure
Resolved 21 March 2010
Resolution: Received NKK Class report #10UH0042 dated 21MAR2010 along with a tech report. Attesting to Satisfactory Repair and calibration made to the second 9 GHZ radar . Deficiency clear 21MAR201
Fire Fighting › Fixed Pressure Water-Spraying Fire Extinguishing System › Nozzles
Issued 20 March 2010 Resolved
Cargo ships shall carry at least one rescue boat complying with LSA 5.1 .Repair damage sustained during life boat/ rescue boat drill (to fire sprinkler system heads) to the satisfaction of certificate issuing authority prior to departure from Port Arthur COTP zone. SOLAS 2004 CONS. CH. III REG 31-2
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Resolved 21 March 2010
Resolution: Received NKK Class report #10UH0042 dated 21MAR2010 along with a tech report attesting to satisfactory repairs made to the Rescue Boat’s hull and temp repairs to the sprinkler system with SAT test results, (See note regarding sprinkler system).
Fire Fighting › Remote Fuel Shutoff › General
Issued 22 March 2008 Resolved
Fuel tank in way of emergency generator has capacity of 510 liters and situated above double bottom. Fuel tank found not capable of being closed from outside the space. Rectify the same to the satisfaction of the vessel's classification society. SOLAS 2004 Cons. Ed. II-2/4.2.2.3.4
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 12 May 2008
Resolution: Received letter from technical manager of vessel, V-Ships Asia PTE LTD attesting that the fuel tank in way of emergency generator actually has capacity of 480 L. However, shutoff valve will be installed on vessel.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.