Records from 2016 to 2024. Most recent: inspection, 5 December 2024.
Everything above is free. The detail below — the inspection history, the deficiency record and the documentation record — is Professional, $39 a month. Sign in.
Professional
Detail on this page
8 inspections, each with its date, unit and type; 10 deficiencies with the resolution recorded against each; the documentation record, as PSIX holds it. The counts in the summary above are the same
counts, and they are free.
$39 a month or $299 a year, every vessel page, cancel any time.
Founding rate $19.99 a month for life, for the first 200 subscribers.
Plans
Sign in
Maury does not score, rate or grade vessels, at any price.
Inspection history · 8
5 December 2024
Administrative Inspection
Administrative · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 8043913
4 December 2024
COE-Administrative
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8043418
4 October 2024
Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8014639
27 August 2024
PSC B · COC-CHEM & TVE Renew
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 7990031
23 August 2024
Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 7987662
8 November 2017
Administrative Inspection · Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6303318
4 September 2017
Ballast Water Examination · COC-CHEM & TVE Annual · ISPS II Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6252635
5 July 2016
ISPS II Exam · Ballast Water Examination · COC-CHEM & TVE Renew
Physical examination · U.S. COAST GUARD FORCES MICRONESIA/SECTOR GUAM · USCG Oceania District (CGD-O) · Activity 5923027
09 - Working and Living Conditions › 092 - Working Conditions › Protection machinery
Issued 27 August 2024
Resolved
THE MACHINERY, BOILERS, AND OTHER PRESSURE VESSELS, ASSOCIATED PIPING SYSTEMS AND FITTINGS SHALL BE OF A DESIGN AND CONSTRUCTION ADEQUATE FOR THE SERVICE FOR WHICH THEY ARE INTENDED AND SHALL BE SO INSTALLED AND PROTECTED AS TO REDUCE TO A MINIMUM ANY DANGER TO PERSONS ON BOARD, DUE REGARD BEING PAID TO MOVING PARTS HOT SURFACES AND OTHER HAZARDS.
PSCO OBSERVED OIL SOAKED LAGGING THROUGHOUT THE ENGINE ROOM.
CITE:74SOLAS(04)II-1/26.1
ACTION CODE: 50BC
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 24 September 2024
Resolved 7 October 2024
Resolution: Deficiency Rectified.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 27 August 2024
Resolved
MEANS SHALL BE PROVIDED TO CONTROL LEAKS OF FLAMMABLE LIQUIDS. PSCO OBSERVED FUEL OIL RETURN LINE DRAIN TO NON-APPROVED CONTAINERS.
CITE: 74SOLARS(04)II-2/4.1.1
ACTION:10C
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 27 August 2024
Resolved 27 August 2024
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 27 August 2024
Resolved
EACH LIFEBUOY SHALL BE MARKED IN BLOCKED CAPITALS OF THE ROMAN ALPHABET WITH THE NAME AND PORT OF REGISTRY OF THE SHIP IN WHICH IT IS CARRIED. PSCO OBSERVED MULTIPLE LIFE BUOY MARKINGS NAME AND PORT OF REGISTRY WERE NOT LEGIBLE.
CITE: 74SOLARS(20)III/7.1.4
ACTION: 10C
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 27 August 2024
Resolved 27 August 2024
14 - Pollution Prevention › 146 - MARPOL Annex VI › Incinerator incl. operations and operating manual
Issued 27 August 2024
Resolved
THE MACHINERY BOILER AND OTHER PRESSURE VESSELS ASSOCIATED PIPING SYSTEMS AND FITTING SHALL BE OF A DESIGN AND CONSTRUCTION ADEQUATE FOR THE SERVICE FOR WHICH THEY ARE INTENDED AND SHALL BE SO INSTALLED AND PROTECTED AS TO REDUCE TO A MINIMUM DANGERS ONBOARD. PSCO OBSERVED INCINERATOR WAS MISSING BRICKS, EXPOSING HOUSING.
CITE: 74SOLAS(04)II-1/26.1
ACTION: 10C
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 27 August 2024
Resolved 27 August 2024
Engineering › Generator (propulsion-electric) › Wiring
Issued 4 September 2017
Resolved
1410-Propulsion main engine-PSCO observed excessive lube oil leak in way of number 2 generator fly wheel. SOLAS 74 (2014) I/11a
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 5 September 2017
Resolution: Received, reviewed and accepted class report from DNV-GL stating the deficiency was rectified. Sump breather was partially blocked causing sump oil to blow into catch pan below flywheel. Breather was clean causing leak to stop.
Engineering › Bilge Water Management System › Not Operational
Issued 4 September 2017
Resolved
1730-Oily-water seperating equipment-PSCO observed oily water seperator was unable to automatically stop when oil content meter had a reading of 15ppm or higher. MARPOL ANNEX I I/14.7
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 5 September 2017
Resolution: Received, reviewed and accepted class report from DNV-GL stating the deficiency was rectified. Vessels engineers conducted maintenace on OWS alarm system. Conducted operational test. All sat.
Fire Fighting › Fixed Deck Foam System › Foam Applicators
Issued 4 September 2017
Resolved
1850-Fire protection cargo deck area-PSCO observed overdue annual foam concentrate documentation. SOLAS 74 (2014) II/2 10.8.1 MSC/CIRC.670
Condition: Invalid
Action required: 705 - Other - as specified
Due 18 September 2017
Resolved 8 November 2017
Resolution: PSC NOLA received a tech report from survitec group satisfying the requirement.
Deck/Cargo › Inert Gas System › Inert Gas Generator (IGG)
Issued 4 September 2017
Resolved
1840-Instrumentation-PSCO observed crew was unable to calibrate IG system. SOLAS 74 (2014) II/2 4.5.5.1.1 FSS CODE 15.2.4.2.5
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 18 September 2017
Resolved 5 September 2017
Resolution: Received, reviewed and accepted class report from DNV-GL stating deficiency was rectified.
Documentation › Certificates/Documents › International Load Line Certificate
Issued 5 July 2016
Resolved
Load Lines - The international Load Line Certificate shall not be delivered to the ship until the officer or surveyor acting under the provisions of article 13 of the Convention has certified that the marks are correctly and permanently indicated on the ship’s sides. The vessels current international load line certificate does not correctly indicate the marks on the ships side. Prior to departur
Condition: Invalid
Action required: 17 - Rectify deficiencies prior to departure
Due 7 July 2016
Resolved 6 July 2016
Resolution: Received copy of new load line certificate and formal letter of copy certification from Class socety for correct load line marking.
Communications › Alarms/Indicators › General Alarm
Issued 5 July 2016
Resolved
1099 - Achemical Tanker shall comply with the requirements of the International Bulk Chemical Code. PSCO observed overflow control visual and audible alarms at cargo control center was inoperative during testing of the remote overflow indicators at cargo tanks. See Form B for full def. SOLAS 2014 cons. ed. VII/10.1
Action required: 705 - Other - as specified
Due 5 July 2016
Resolved 5 July 2016
Resolution: Corrected to the satisfaction of the attending Marine Inspector.