Records from 2014 to 2026. Most recent: inspection, 22 May 2026.
Inspection history · 38
22 May 2026
PSC B · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8378359
22 May 2026
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8378415
20 May 2025
PSC B
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8139542
7 May 2025
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8130488
22 February 2025
PSC B
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8080855
14 September 2024
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 8002350
1 July 2024
PSC B
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7943657
30 January 2024
PSC B
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7853620
31 May 2023
PSC B
Physical examination · Sector Jacksonville · USCG Southeast District (CGD-SE) · Activity 7697070
14 January 2023
Deficiency Check
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 7621426
7 December 2022
PSC B
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 7604750
7 December 2022
Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 7605629
29 November 2022
Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 7601372
9 July 2022
Type not recorded
No type recorded · Sector Jacksonville · USCG Southeast District (CGD-SE) · Activity 7503836
8 July 2022
Type not recorded
No type recorded · Sector Jacksonville · USCG Southeast District (CGD-SE) · Activity 7505772
29 September 2020
Administrative Inspection
Administrative · Sector North Carolina · USCG East District (CGD-E) · Activity 7067466
1 May 2020
Administrative Inspection
Administrative · Sector North Carolina · USCG East District (CGD-E) · Activity 6946688
29 January 2020
PSC B
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6898486
6 April 2019
Type not recorded
No type recorded · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6660313
3 April 2019
ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6647996
3 April 2019
Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6655341
2 April 2019
Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6654909
16 March 2018
Type not recorded
No type recorded · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6374976
1 March 2018
PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6363754
28 February 2018
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6363444
24 February 2018
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6360823
29 December 2017
Administrative Inspection
Administrative · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6330063
15 December 2017
Administrative Inspection
Administrative · Sector New York · USCG Northeast District (CGD-NE) · Activity 6324877
5 January 2017
In-Service Inspection
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 6066566
13 December 2016
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6057508
9 December 2016
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6055241
30 September 2016
Administrative Inspection
Administrative · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6013007
28 September 2016
PII Safety Exam · Ballast Water Examination · ISPS II Exam
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 6011231
27 September 2016
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6011167
23 September 2016
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 6007738
1 August 2014
ISPS II Exam
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 4933445
29 March 2014
PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector New York · USCG Northeast District (CGD-NE) · Activity 4824199
28 March 2014
Type not recorded
No type recorded · Sector New York · USCG Northeast District (CGD-NE) · Activity 4825034
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 22 May 2026
Resolved
The purpose of this regulation is to prevent the ignition of combustible materials or flammable liquids. For this purpose, the following functional requirements shall be met: means shall be provided to control leaks of flammable liquids.
PSCO observes oil accumulation in engine room under main engine, in purifier room, and under #4 generator.
74SOLAS(09) II-2/4.1.1
Condition: Improper/Lack of Maintenance
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 10 July 2026
Resolution: Received Class report attesting to the rectification of the deficiency. All oil accumulation has been satisfactorily cleaned.
07 - Fire Safety › N/A - No Subsystem › Oil accumulation in engine room
Issued 1 July 2024
Resolved
74SOLAS(20)II-2/4.1.1 - The purpose of this regulation is to prevent the ignition of combustible materials or flammable liquids. For this purpose, the following functional requirements shall be met: .1 means shall be provided to control leaks of flammable liquids. PSCO observed excessive lube oil accumulation in engine room on top of main engine cylinder heads in addition to polling under multiple auxiliary generators.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Resolved 1 July 2024
Resolution: PSCO observed removal of excess oil before departure.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 1 July 2024
Resolved
74SOLAS(20)II-2/4.3 - In spaces where penetration of oil products is possible, the surface of insulation shall be impervious to oil or oil vapors. PSCO observed lube oil soaked lagging under fuel oil relief valves on multiple auxiliary generators.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Resolved 1 July 2024
Resolution: PSCO observed new lagging installed on relief valves on the auxiliary generators.
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Company verification, review and evaluation
Issued 7 December 2022
Resolved
Every company should develop, implement and maintain a safety management system which includes the following functional requirements: instructions and procedure to ensure safe operation of ships and protection of the environment in compliance with relevant international and flag state legislation. The vessel reported a discharge of oil into the water originating from a leak in cargo hold number 3.
COTP MSU Savannah request a review of the cargo hold ballast and bilge discharge procedures to prevent the discharge of pollution into the environment.
ISM Code 1.4.2
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 14 January 2023
Resolution: DNV Report submitted of ISM Audit attesting to satisfactory review of cargo hold ballast and bilge discharge procedures
Engineering › Diesel Engine (propulsion-direct drive) › Valve, Pilot (air start)
Issued 5 January 2017
Resolved
Vessel unable to bring their main engine propulsion system online during pre-departure checks.
Action required: 17 - Rectify deficiencies prior to departure
Due 6 January 2017
Resolved 6 January 2017
Resolution: Received class survey report, deficiency resolved
Engineering › Diesel Engine (auxiliary) › Cylinder
Issued 28 September 2016
Resolved
The purpose of this regulation is to prevent the ignition of combustible materials or flammable liquids. For this purpose, the following functional requirements shall be met: .1 means shall be provided to control leaks of flammable liquids. Diesel generator #3 had excessive oil accumulation on inboard side.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 28 September 2016
Resolved 28 September 2016
Resolution: Chief Engineer sufficiently cleaned up oil accumulation on Diesel Generator #3.
Engineering › Fuel Oil Service System › Filter
Issued 28 September 2016
Resolved
The purpose of this regulation is to prevent the ignition of combustible materials or flammable liquids. For this purpose, the following functional requirements shall be met: .1 means shall be provided to control leaks of flammable liquids. Oil filter for main engine had excessive oil accumulation with a drip pan in place.
Condition: Improper/Lack of Maintenance
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 13 December 2016
Resolution: Class attended vessel and attested to repairs being complete.
Electrical › Lighting (service) › Lighting Fixture
Issued 28 March 2014
Resolved
0950 - Electrical Equipment in General - No electrical equipment shall be installed in paint lockers of a type which will ignite the mixture concerned. The light fixture in the paint locker's lens is cracked in multiple places. 74 SOLAS 04 Cons II-1/45.10
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 30 July 2014
Resolution: Received class report attesting to repairs
Fire Fighting › Structural Fire Protection - General › Cooking Area
Issued 28 March 2014
Resolved
0750 - Fire Prevention - Fire doors in the galley boundaries shall be self-closing with an angle of inclination of up to 3.5 degrees of opposing closure. Three fire doors in the galley do not self-close. 74 SOLAS 04 Cons. II-2/9.4.1.1.4
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 30 July 2014
Resolution: Received Class report attesting to repairs.