Records from 2008 to 2025. Most recent: inspection, 22 July 2025.
Documentation record
Registered dimensions (L × B × D)42.2 ft × 18.0 ft × 5.7 ft
Registered tonnagegross 44 / net 30
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
Builderbuilder not recorded · ST. LOUIS, MO, UNITED STATES · built 1971
Hull materialSteel
PropulsionDiesel
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portKANSAS CITY, MO
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 2 June 2026 · expires 31 July 2027
Service, as the file records itTowing Vessel
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it44 - Regulatory (Subpart C or D), Gross Ton
30 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 10
22 July 2025
TPO Audit
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8196549
23 April 2025
Administrative Inspection
Administrative · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 8118055
9 September 2022
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7613800
16 June 2022
TPO Audit
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7482672
10 September 2021
Initial Certification · Administrative Inspection · Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7309003
7 January 2013
Type not recorded
No type recorded · Station New Orleans · USCG Heartland District (CGD-H) · Activity 4515759
7 January 2013
Type not recorded
No type recorded · Station New Orleans · USCG Heartland District (CGD-H) · Activity 4516677
7 April 2011
Industry Initiated Exam · DAPI Audit
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3982155
9 January 2009
Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3390719
18 December 2008
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3382109
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 1 August 2022
Resolved
All fire-detection systems must be inspected or tested at least once every 12 months. Vessel did not have documentation attesting to the annual testing of the fire detection system. Provide documentation attesting to satisfactory annual servicing of the fire detection system to the satisfaction of the TPO or Coast Guard. 46 CFR 142.240(a).
Action required: 60 - Rectify deficiencies prior to movement
Resolved 9 August 2022
Resolution: Vessel produced fire detection inspection report performed by certified third party.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 1 August 2022
Resolved
Electrical systems and equipment must function properly and minimize system failures and fire and shock hazards. The vessel's 12V electrical system in the vicinity of the battery bank forward in the engine room was not installed properly, allowing several loose leads. Vessel must have a marine electrician verify proper wiring and that battery back-up for required systems is properly functioning to the satisfaction of the TPO or Coast Guard. 46 CFR 143.400(a)
Action required: 60 - Rectify deficiencies prior to movement
Resolved 9 August 2022
Resolution: Vessel provided inspection report from third party marine electrician. All wiring now properly installed.
10 - Safety of Navigation › N/A - No Subsystem › Charts
Issued 1 August 2022
Resolved
Each towing vessel must carry on board and maintain marine charts or maps of the areas to be transited that are of a large enough scale and have enough detail to make safe navigation of the areas possible, and are current editions or currently corrected editions. Vessel did not have current or updated charts on board. Provide evidence of current or updated charts on board to the satisfaction of the TPO or Coast Guard. 33 CFR 164.72(b)(1).
Action required: 60 - Rectify deficiencies prior to movement
Resolved 9 August 2022
Resolution: Vessel produced current/updated charts.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 1 August 2022
Resolved
Each lifebuoy on a towing vessel must be approved under approval series 160.050 or 160.150 and at least one lifebuoy must have a lifeline, secured around the body of the lifebuoy. If more than one lifebuoy is carried, at least one must not have a lifeline attached and the water light must be attached by the lanyard with a corrosion-resistant clip to allow the water light to be quickly disconnected from the lifebuoy. Lifebuoys had faded retro-reflective tape and both lifebuoys had lights improperly attached. Replace retro-reflective tape and attach water lights with lanyard around the body of the lifebuoy. Attach at least one light around the lifebuoy with a corrosion resistant clip to allow for quick disconnect. Correct to the satisfaction of the TPO or Coast Guard. 46 CFR 141.360 (b)(1),(c)(1), (c)(2).
Action required: 60 - Rectify deficiencies prior to movement
Resolved 9 August 2022
Resolution: Ring buoy now has quick disconnect clip around mid body.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 1 August 2022
Resolved
Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons on board under normal and emergency conditions. The generator fuel supply line was an approximately 10ft long non-metallic flexible hose. Vessel must determine whether the installed hose is properly rated for fuel service. Correct to the satisfaction of the TPO or Coast Guard. 46 CFR 143.205 (a)
Action required: 60 - Rectify deficiencies prior to movement
Resolved 9 August 2022
Resolution: Vessel installed metallic piping w/ < 30 inches of flexible hose.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 1 August 2022
Resolved
Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons on board under normal and emergency conditions. The bilge suction line did not have a means to prevent backflood into the space or means to strain bilge water. Correct to the satisfaction of the TPO or Coast Guard.
46 CFR 143.205 (a).
Action required: 60 - Rectify deficiencies prior to movement
Resolved 9 August 2022
Resolution: Vessel installed a check/foot valve with a strainer.
09 - Working and Living Conditions › 092 - Working Conditions › Machinery
Issued 1 August 2022
Resolved
Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons on board under normal and emergency conditions. The vessel was unable to swing the flanking rudders smoothly from hard port to hard starboard. Vessel must determine the cause of the loud popping and correct to the satisfaction of the TPO or Coast Guard. 46 CFR 143.205 (a).
Action required: 60 - Rectify deficiencies prior to movement
Resolved 9 August 2022
Resolution: Vessel discovered and repaired a worn bushing on the mechical to hydraulic connection.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 1 August 2022
Resolved
Piping and machinery components that exceed 220 °C (428 °F), including fittings, flanges, valves, exhaust manifolds, and turbochargers, must be insulated. Both main diesel engines had approximately one foot of exhaust piping that was not insulated. Correct to the satisfaction of the TPO or Coast Guard. 46 CFR 143.220(b)
Action required: 50 - Rectify deficiencies w/in 30 days
Due 31 August 2022
Resolved 9 August 2022
Resolution: Vessel installed lagging.
09 - Working and Living Conditions › 092 - Working Conditions › Machinery
Issued 1 August 2022
Resolved
The following systems must be equipped with gauges at the machinery location: main engine lubricating oil pressure and main engine RPM. The RPM gauge was reading an error message. Correct to the satisfaction of the TPO or Coast Guard. 46 CFR 143.230(c)(1).
Action required: 50 - Rectify deficiencies w/in 30 days
Due 31 August 2022
Resolved 9 August 2022
Resolution: Vessel had third party onboard fix the malfunctioning sensor.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 19 July 2022
Resolved
All owners and operators of an existing towing vessel must have on board a valid COI prior to the specified phase-in period. This vessel has not scheduled an inspection or obtained a valid COI. The vessel shall be made available for a Coast Guard COI Inspection immediately and the vessel may no longer be permitted to operate.
46 CFR 136.202
Condition: Invalid
Action required: 60 - Rectify deficiencies prior to movement
Due 19 July 2022
Resolved 9 August 2022
Resolution: Issued COI.