Records from 2014 to 2026. Most recent: inspection, 12 July 2026.
Inspection history · 26
12 July 2026
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8436094
31 March 2026
Type not recorded
No type recorded · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 8340211
26 March 2026
PSC B
Physical examination · Marine Safety Unit Savannah · USCG Southeast District (CGD-SE) · Activity 8329598
17 September 2025
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8236328
15 September 2025
PSC B
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8230663
18 March 2024
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7881756
15 August 2022
Administrative Inspection
Administrative · Marine Safety Detachment Massena · USCG Great Lakes District (CGD-GL) · Activity 7533922
7 December 2021
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 7363717
18 January 2021
PSC B
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7125909
7 November 2020
Administrative Inspection
Administrative · Marine Safety Detachment Massena · USCG Great Lakes District (CGD-GL) · Activity 7091287
24 August 2020
Type not recorded
No type recorded · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7041802
29 July 2020
In-Service Inspection
Physical examination · Sector Delaware Bay · USCG East District (CGD-E) · Activity 7019824
13 May 2020
Ballast Water Examination
Physical examination · Marine Safety Detachment Massena · USCG Great Lakes District (CGD-GL) · Activity 6952416
29 December 2019
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6880284
16 July 2019
Ballast Water Examination · ISPS II Exam · NPV Safety Exam
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6742345
22 April 2019
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6668262
17 February 2019
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6627039
9 October 2018
ISPS II Exam
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6555778
18 September 2018
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6543128
8 February 2018
ISPS II Exam
Physical examination · Sector San Diego · USCG Southwest District (CGD-SW) · Activity 6348430
7 October 2017
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6283042
3 February 2017
Administrative Inspection · Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6082447
18 January 2017
PII Safety Exam · ISPS II Exam · Ballast Water Examination
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6069302
7 August 2015
ISPS II Exam · Ballast Water Examination · PII Safety Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5202169
25 August 2014
Administrative Inspection · ISPS I Exam · Enhanced Seaway Inspection (Massena only) · Joint Vessel Security Verification (Massena only) · COE-Dockside
Physical examination · Marine Safety Detachment Massena · USCG Great Lakes District (CGD-GL) · Activity 4965957
28 March 2014
Administrative Inspection · Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4824881
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 29 July 2020
Resolved
The condition of the ship and it's equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. At approximately 2200 on 29JUL2020 Duty Marine Inspector received report the the vessel's controllable pitch propeller had malfunctioned and was stuck in the slow-aft propulsion. Provide Class Report detailing cause of failure and corrective measures taken. Vessel is restricted from moving from the dock.
Action required: 60 - Rectify deficiencies prior to movement
Due 29 July 2020
Resolved 31 July 2020
Resolution: Recieved class report. Could not duplicate issue.
Engineering › Fuel Oil Storage/Transfer System › Piping
Issued 18 January 2017
Resolved
9900 Other (not clearly hazardous) Each loading arm and each transfer pipe system, including each metallic hose, must not leak under static liquid pressure at least 1.5 times the maximum allowable pressure. PSCO observed the test was not conducted with liquid pressure. 33CFR156.170(c)(4)
Condition: Improper/Lack of Maintenance
Action required: 703 - Prior to bunkering operations
Resolved 3 February 2017
Resolution: PSC NOLA received a report from Carisbrooke Shipping LTD satisfying the requirement.
Operations/Management › Cargo Transfer/Lightering › Vessel Transfer Procedures on Hand
Issued 18 January 2017
Resolved
9900 Other (not clearly hazardous)The transfer procedures required by 155.720 must be available for inspection by the COTP or OCMI whenever the vessel is in operation. PSCO observed that there was no written transfer procedures. 33CFR155.740(a)
Condition: Improper/Lack of Maintenance
Action required: 703 - Prior to bunkering operations
Resolved 3 February 2017
Resolution: PSC NOLA received a report from Carisbrooke Shipping LTD satisfying the requirement.