Records from 2011 to 2023. Most recent: inspection, 10 October 2023.
Documentation record
Registered dimensions (L × B × D)300.0 ft × 54.0 ft × 12.0 ft
Registered tonnagegross 1,632 / net 1,632
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderTRINITY MARINE PRODUCTS INC · ASHLAND CITY, TN, UNITED STATES · built 2011
Hull materialSteel
PropulsionUNSPECIFIED
Hull shapeBox
Hull configurationMonohull
Hailing portWILMINGTON, DE
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 16 July 2026 · expires 31 August 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1632 - Simplified, Gross Ton
1632 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 21
10 October 2023
Bulk Liquid Transfer Monitor
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7806236
18 October 2021
Examination of Repairs · Drydock Exam · Internal Structural Exam · MTSA Verification · Cargo Tank Internal · COI Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7331000
20 September 2018
Bulk Liquid Transfer Monitor
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6545559
20 July 2018
Administrative Inspection · Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6485382
3 July 2018
Examination of Repairs · Periodic Inspection · MTSA Verification · Deficiency Check · Administrative Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6459892
24 June 2018
Administrative Inspection
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6453595
23 June 2018
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6512188
3 November 2017
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 6301440
4 August 2017
Annual Inspection · Administrative Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6267799
31 August 2016
Examination of Repairs · Internal Structural Exam · COI Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5980814
11 August 2016
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5969917
26 August 2015
Administrative Inspection · Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5881464
25 August 2015
Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5224747
30 September 2014
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5058348
23 May 2014
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 4868380
27 October 2013
Administrative Inspection · Damage Survey · Deficiency Check
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 4741919
2 July 2013
Administrative Inspection · Periodic Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4647161
17 July 2012
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4463307
14 September 2011
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 4146297
10 August 2011
Deficiency Check · Administrative Inspection · Examination of Repairs
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4111636
27 July 2011
Internal Structural Exam · Initial Construction-Excluding Oversight · Administrative Inspection · Initial Certification · Cargo Tank Internal · Hull Examination · MTSA Verification
Physical examination · Marine Safety Detachment Nashville · USCG Heartland District (CGD-H) · Activity 4096196
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Cargo operation
Issued 6 July 2018
Resolved
Thermal Fluid Heater operational tests must be conducted at the COI and Periodic Inspection. Thermal Fluid Heater was not able to be tested during the Periodic Exam.
Vessel required to lock and tag out Thermal Fluid Heater system and lock supply fuel line from generator to system. Vessel not authorized to carry cargo that use heating system until system placed back into service and satisfactorily tested.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 6 August 2018
Resolved 11 July 2018
Resolution: System locked out & tagged out. Thermal Fluid Heater endorsement removed from COI.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 3 July 2018
Resolved
Nonmetallic flexible hose must be in accordance with SAE J1942 when installed on fuel systems. Prime mover for cargo pump engine found to have SAE J 1402 Air Brake lines in place of SAE J1942 Fuel Lines.
Condition: Placed in Improper Service
Action required: 17 - Rectify deficiencies prior to departure
Due 1 August 2018
Resolved 6 July 2018
Resolution: Verified correct lines were installed.
14 - Pollution Prevention › 141 - MARPOL Annex I › Oil fuel tank protection
Issued 3 July 2018
Resolved
Bolts and studs must extend completely through the nuts. Foundation securing bolts for the diesel fuel tank were found wasted and missing.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 1 August 2018
Resolved 6 July 2018
Resolution: Attending Marine Inspector verified quantity of foundation bolts that were serviceable were sufficient enough to maintain integrity of diesel fuel oil tank.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 3 July 2018
Resolved
Non-metallic expansion joints must conform to the standards in 46 CFR 50.60-1(b) (table). The coolant line return from radiator on the cargo pump engine was found to be collapsed on itself, damaged, and causing an obstruction for the flow of coolant in the system.
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Due 1 August 2018
Resolved 6 July 2018
Resolution: Expansion joint had been renewed and was no longer causing obstruction.
Electrical › Electric Generation Source (service) › Generator
Issued 27 October 2013
Resolved
Repair generator to satisfaction of Coast Guard Marine Inspector prior to cargo operations due to generator fire and damage to generator windings.
Action required: 705 - Other - as specified
Due 4 November 2013
Resolved 28 October 2013
Resolution: New generator unit installed in kind, operation test completed satisfactory. Operational Control removed on this date.
Construction/Loadline › Hull › Bottom Plating
Issued 27 July 2011
Resolved
Void 7 Starboard- Very aft end of the tank renew: 1) 1 section of knuckle full height x 4' 4" long 2) 1 Bottom Plate 3' 10" long X 5' 4" wide
Action required: 705 - Other - as specified
Due 28 August 2011
Resolved 12 August 2011
Resolution: Air/soap tested repairs. All sat
Construction/Loadline › Hull › Longitudinal Frame
Issued 27 July 2011
Resolved
Void 7 Starboard- Very aft end of the tank, renew: 1) 1 Floor Angle 5" X 3" X 5/16" X 6' 4" long. 2) 1 Floor Angle 5" X 3" X 5/16" X 4' 4".
Action required: 705 - Other - as specified
Due 28 August 2011
Resolved 12 August 2011
Resolution: All repairs complete.
Construction/Loadline › Hull › Bracket
Issued 27 July 2011
Resolved
Void 7 Starboard- Very aft end of the tank, renew: 3 Gusset Plates 12" X 5/16" X 12"
Action required: 705 - Other - as specified
Due 28 August 2011
Resolved 12 August 2011
Resolution: All repairs complete.
Engineering › Diesel Engine (auxiliary) › Piping (air intake)
Issued 27 July 2011
Resolved
Demonstrate proper operation of emergency shut down of cargo pump engine.
Action required: 705 - Other - as specified
Due 28 August 2011
Resolved 12 August 2011
Resolution: Ran cargo pump engine and witnessed proper operation of emergency shutdown.
Construction/Loadline › Hull › Bottom Plating
Issued 27 July 2011
Resolved
Void 1 Starboard- Very aft end of the tank, renew: 1 Knuckle full height x 5' 4-3/4" long
Action required: 705 - Other - as specified
Due 28 August 2011
Resolved 12 August 2011
Resolution: Air/soap tested repairs. All sat.
Construction/Loadline › Hull › Longitudinal Frame
Issued 27 July 2011
Resolved
Void 1 Starboard- Very aft end of the tank,
renew: 1 Floor Frame full height X 4' 5" long
Action required: 705 - Other - as specified
Due 28 August 2011
Resolved 12 August 2011
Resolution: Repair complete.
Construction/Loadline › Hull › Bracket
Issued 27 July 2011
Resolved
Void 1 Starboard- Very aft end of the tank,
renew: 1 Gusset Plate 12" X 5/16" X 12"
Action required: 705 - Other - as specified
Due 28 August 2011
Resolved 12 August 2011
Resolution: Repair complete.