MAURY USCG vessel records
← All vessels

EARL L MILAN

Built
1974
Last inspected
11 April 2025
Documentation
Case Pending · NVDC file of 10 August 2026
Controls
None recorded without a removal date

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Research Ship class in Maury's sources begin in 2016.

Inspection record

Last inspected 11 April 2025
…with no type recorded2
Operational controls None recorded without a removal date
Years with a record 10 calendar years (2016–2025)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Identity

WDG2537
130539
Flag
UNITED STATES
Maury page id
psix-130539

Documentation record

Registered dimensions (L × B × D)45.0 ft × 15.3 ft × 5.4 ft
Registered tonnagegross 26 / net 17
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderARAMCO HARDWARE INC · GALVESTON, TX, UNITED STATES · built 1974
Hull materialAluminum
PropulsionDiesel Reduction
Hull shapeUNSPECIFIED
Hull configurationUNSPECIFIED
Hailing portGALVESTON, TX
Endorsements, as the file codes themcw_un
DocumentationCase Pending · issued 14 November 2025 · expires 31 October 2026
Service, as the file records itResearch Vessel
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it26 - Regulatory (Subpart C or D), Gross Ton
17 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Professional
The full record for this vessel

Behind this panel: 20 inspections, each with its date, unit and type; 9 deficiencies with the resolution recorded against each; operational controls, none recorded without a removal date; 1 other vessel inspected with it; no other recorded names; the documentation record: dimensions, tonnage, builder, hailing port and endorsements. Every line is a record the Coast Guard wrote; the counts above are the same counts as in the summary, and they are free.

Professional is $39 a month or $299 a year, or $19.99 a month locked for life at the founding rate, for the first 200 subscribers. It unlocks every detail section on every vessel page, fleet watch tied to your account, and ownership records on request. Already a subscriber? Sign in.

Maury does not score, rate or grade vessels, at any price.

Vessel history report
Every record for this hull, in one document — $299

Every recorded inspection, 1972 to 2026, in one chronology · every deficiency, with system, dates and resolution · operational controls imposed and removed · every name this hull has been recorded under · the vessels it was inspected alongside, and when · how its record compares with hulls of similar age and size, as a fact about the population and never a judgement about this vessel.

Read one first, in full: a forty-year chronology · a hull that changed operators four times · the sparse case, shown as an example, not for sale.

This report is in development and is not for sale yet. There is no date, and nothing is charged. Leave an email and we will tell you when it exists, once.

Inspected as a tow unit · 1

The Coast Guard recorded this vessel and the following in the same inspection activity — normally a tug and the barges in its tow. A recreational or unclassed hull in the same activity is held and not published, so it does not appear here: these lists are a floor, not a complete manifest.

MAERSK DAKAR Freight Ship · MISLE 724807 · 8 October 2018 · activity 6568882

Inspection history · 20

11 April 2025 In-Service Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8110142
24 March 2025 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8098700
16 December 2024 Internal Structural Exam · Drydock Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8047935
11 March 2024 Annual Inspection · Internal Structural Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7877172
20 December 2023 Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7841216
7 February 2023 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7633495
7 February 2022 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7392082
13 December 2021 Drydock Exam · Internal Structural Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7367199
17 March 2021 COI Inspection · Deficiency Check · Administrative Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7157796
29 April 2020 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6945629
9 December 2019 COE-Administrative · Drydock Exam · Examination of Repairs
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6870601
16 April 2019 Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6663357
12 April 2019 Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6675305
4 April 2019 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6656093
8 October 2018 Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6568882
16 April 2018 Examination of Repairs · Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6399791
5 March 2018 Annual Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6365847
6 December 2017 Drydock Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6319656
1 June 2017 Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6166714
15 March 2016 Simplified Stability Test · Administrative Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5818309

Deficiency record · 9

11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 7 February 2023 Resolved
Each item of lifesaving equipment determined by the marine inspector to not be in serviceable condition must be repaired or replaced. Ring buoy at operating station found with severed/degraded grab lines and water light line. Replace lines.
Condition: Improper/Lack of Maintenance
Action required: 701 - Prior to carriage of passengers/cargo
Due 7 February 2023
Resolved 8 February 2023
Resolution: Ring buoy replaced along with all lines and light.
05 - Radio Communications › N/A - No Subsystem › Main installation
Issued 7 February 2023 Resolved
Every vessel subject to Part III of Title III of the Communications Act must have a detailed inspection of the radio installation by an FCC-licensed technician in accordance with § 80.59 once every five years.If the ship passes the inspection, the technician will issue a Communications Act Safety Radiotelephony Certificate. Certificate found expired. Renew Certificate. 47 CFR 80.903
Condition: Invalid
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 February 2023
Resolved 13 February 2023
Resolution: Received copy of newly issued bridge to bridge certificate
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 7 February 2023 Resolved
Fire extinguishers shall be inspected either manually or by means of an electronic monitoring device/system at a minimum of 30-day intervals. No record of inspection found onboard. Inspect all portable fire extinguishers, record appropriately, and provide evidence of inspection to the Coast Guard. NFPA 10/7.2.1.2
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 February 2023
Resolved 13 February 2023
Resolution: Received photographs indicating extinguishers have been inspected and properly recorded.
14 - Pollution Prevention › 144 - MARPOL Annex IV (Not Applicable to PSC Exams conducted in the U.S.) › Sewage treatment plant
Issued 7 February 2023 Resolved
When operating a vessel on a body of water where the discharge of untreated sewage is prohibited by the Environmental Protection Agency under 40 CFR 140.3, the operator must secure each Type III device in a manner which prevents discharge of sewage. Acceptable methods of securing the device include - (1) Closing each valve leading to an overboard discharge and removing the handle; (2) Padlocking each valve leading to an overboard discharge in the closed position; or (3) Using a non-releasable wire-tie to hold each valve leading to an overboard discharge in the closed position. Marine Inspector could not verify position of the valve as open or closed. Provide evidence to confirm valve is closed and secured.
Condition: Placed in Improper Service
Action required: 16 - Rectify deficiencies w/in 14 days
Due 21 February 2023
Resolved 8 February 2023
Resolution: Overboard valve closed, labeled, and secured via wire.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 17 March 2021 Resolved
46 CFR 179.320(c) The number of penetrations in a watertight bulkhead must be minimized. A penetration in a watertight bulkhead must be as high and as far inboard in the bulkhead as practicable, and made watertight. There are 02 bulkhead penetrations from the engine room to the next space aft that are not made permanently watertight.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 April 2021
Resolved 5 April 2021
Resolution: Vessel installed temporary patches in the bulkhead penetrations. Will affect permanent weld repairs in next drydock. Entered into special notes.
07 - Fire Safety › N/A - No Subsystem › Fire pumps and its pipes
Issued 17 March 2021 Resolved
46 CFR 181.120(a) Fire extinguishing equipment installed on a vessel in excess of the requirements of 46 CFR 181.400 and 181.500 must be designed, constructed, installed, and maintained in accordance with a recognized industry standard acceptable to the Commandant (CG-ENG-4). The installed fire pump is inoperable. Any equipment installed, must be in proper working order.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 April 2021
Resolved 5 April 2021
Resolution: Vessel installed new fire pump.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 17 March 2021 Resolved
46 CFR 179.360 Each hatch exposed to the weather must be watertight. The forward emergency exit hatch will not fully seat, allowing for the chance for down flooding.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 April 2021
Resolved 26 April 2021
Resolution: Witnessed operation of forward emergency exit escape hatch fully seating and locking.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 17 March 2021 Resolved
46 CFR 182.455(b)(4) Shutoff valves, installed so as to close against the fuel flow, must be fitted in the fuel supply lines, one at the tank connection and one at the engine end of the fuel line to stop fuel flow. The port side fuel shutoff valve will not fully close when the emergency fuel shutoff handle is actuated.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 April 2021
Resolved 5 April 2021
Resolution: Witnessed operation of fuel shutoff valve after adjustments were made, allowing the valve to fully close.
10 - Safety of Navigation › N/A - No Subsystem › Electronic charts (ECDIS)
Issued 17 March 2021 Resolved
46 CFR 184.420(a)(1) As appropriate for the intended voyage, a vessel must carry adequate and up-to-date: (1) Charts of large enough scale to make safe navigation possible. Vessel utilizes electronic charts as primary navigation source. Current electronic charts are out of date.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 April 2021
Resolved 26 April 2021
Resolution: Witnessed operation of electronic chart system and verified that electronic charts were up to date.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.