Records from 2015 to 2025. Most recent: inspection, 28 October 2025.
Documentation record
Registered dimensions (L × B × D)381.6 ft × 74.0 ft × 32.0 ft
Registered tonnagegross 6,482 / net 6,482
ITC dimensions (L × B × D)381.6 ft × 74.0 ft × 32.0 ft
ITC tonnagegross 7,093 / net 3,738
BuilderCONRAD SHIPYARD LLC · AMELIA, LA, UNITED STATES · built 2017
Hull materialSteel
PropulsionNot recorded
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portBALTIMORE, MD
Trade endorsementsCoastwise, unrestricted, Registry
DocumentationValid · issued 3 February 2026 · expires 31 March 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it7093 - Convention (Subpart B), Gross Ton
6482 - Regulatory (Subpart C or D), Gross Ton
3738 - Convention (Subpart B), Net Ton
6482 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 12
28 October 2025
Vessel Attendance · MARPOL Annex VI Survey · MTSA Verification · Annual Inspection · Internal Structural Exam
Physical examination · Sector Los Angeles/Long Beach · USCG Southwest District (CGD-SW) · Activity 8204009
17 December 2024
Annual Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 8046712
27 March 2024
Deficiency Check · Annual Inspection
Physical examination · Sector San Francisco · USCG Southwest District (CGD-SW) · Activity 7888677
12 October 2022
Deficiency Check · Internal Structural Exam · COI Inspection · Examination of Repairs · Administrative Inspection · Hull Examination · Cargo Tank Internal
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7563075
29 October 2021
Annual Inspection · MTSA Verification · Deficiency Check · MARPOL Annex VI Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7336550
1 November 2020
MARPOL Annex VI Survey · Internal Structural Exam · Examination of Repairs · Annual Inspection · MTSA Verification · Damage Survey
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 7077650
12 July 2020
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7006106
10 February 2020
In-Service Inspection · Periodic Inspection
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 6899646
1 April 2019
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6702106
6 February 2019
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6621233
3 January 2019
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6605240
7 December 2015
MARPOL Annex VI Survey · MTSA Verification · VRP Drill · COI Inspection · MARPOL Annex I Examination · Construction Oversight · Examination of Repairs · Administrative Inspection
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 6038217
01 - Certificates & Documentation › 013 - Documents › Oil record book
Issued 27 March 2024
Resolved
Every oil tanker of 150 gross tonnage and above and every ship of 400 gross tonnage and above other than an oil tanker shall be provided with an Oil Record Book Part I (Machinery space operations). The Oil Record Book, whether as a part of the ship's official logbook, as an electronic record book which shall be approved by the Administration taking into account the Guidelines developed by the Organization, or otherwise, shall be in the form specified in appendix III to this Annex: Collection of oil residues (sludge). Quantities of oil residues (sludge) retained on board. The quantity should be recorded weekly. IOPP supplement lists port and starboard waste oil tanks under section 3.1. Weekly soundings are only being recorded for port WOT due to non use of starboard WOT. Record weekly soundings for both tanks or work with certificate issuing authority to remove unused tank from IOPP supplement.
MARPOL I/17
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 27 April 2024
Resolved 14 May 2024
Resolution: Received updated IOPP supplement with stbd WOT removed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 23 January 2023
Resolved
The installation of all electrical engineering or interior communications systems, together with the details of design, construction, and installation, must meet the requirements of subchapter J. Each generator must meet the applicable requirements of the ABS steel vessel rules.
Vessels generator must have a Nameplates of corrosion-resistant material.
The nameplate on the #1 generator was worn and unreadable.
46 CFR 32.45-1
46 CFR 111.12-5
ABS Steel Vessel Rules 4-8-3.11.8
Action required: 50 - Rectify deficiencies w/in 30 days
Due 23 February 2023
Resolved 27 January 2023
Resolution: Vessel has procured new generator data plates and has placed a temporary tag in vicinity of gen-sets.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 23 January 2023
Resolved
Each vessel vapor connection flange face must have a permanent stud projecting outward that has a 12.7 millimeter (0.5 inch) diameter and is at least 25.4 millimeters (1 inch) long. It must be located at the top of the flange face, midway between boltholes, and in line with the bolthole pattern.
Vessels Port side vapor line did not have a stud on the flange face.
46 CFR 39.2001(j)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 February 2023
Resolved 24 January 2023
Resolution: Vessel drilled and added a stud to the vapor recovery system.
01 - Certificates & Documentation › 013 - Documents › Oil record book
Issued 23 January 2023
Resolved
Each operation described in paragraphs (d), (e) and (f) of this section shall be fully recorded without delay in the Oil Record Book so that all the entries in the book appropriate to that operation are completed.
Vessel Oil Record Book Part I did had missing information on log entries when conducting internal tank transfers for the amount of oil being retained in the tank after each operation was complete.
33 CFR 151.25(h)
Action required: 10 - Deficiency Rectified
Due 23 January 2023
Resolved 23 January 2023
Resolution: Conducted training with the crew on proper ORB entries.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 23 January 2023
Resolved
The installation of all electrical engineering or interior communications systems, together with the details of design, construction, and installation, must meet the requirements of subchapter J. Each generator arranged for parallel operation must have reverse-power or reverse-current trips.
Vessel was unable to demonstrate reverse-power trips on the #3 generator when paralleled with either the #1 or #2 generators.
Vessel must not parallel the #3 generator until satisfactory test witnessed by a CG marine inspector.
46 CFR 32.45-1
46 CFR 111.12-11(f)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 7 February 2023
Resolved 24 January 2023
Resolution: Vessel demonstrated proper operation of the #3 generator.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 29 October 2021
Resolved
The owner, master, or person-in-charge of a tank vessel must ensure that portable extinguishers are inspected and maintained in accordance with NFPA 10.
A 120 B:C portable fire extinguisher in the generator house was undercharged.
46 CFR 31.10-18(a)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 November 2021
Resolved 1 November 2021
Resolution: Vsl rep replaced undercharged fire extinguisher with a new, fully charged 120 B:C fire extinguisher.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 29 October 2021
Resolved
Each vessel vapor connection flange face must have a permanent stud projecting outward, located at the top of the flange face.
The stud of the port manifold vapor connection flange was located at the bottom of the flange face.
46 CFR 39.2001(j)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 November 2021
Resolved 1 November 2021
Resolution: Vsl rep relocated the stud to the top of the flange.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 29 October 2021
Resolved
The ring, lines and letters shall be painted in white or yellow on a dark ground or in black on a light ground.
The load line and deck line on both sides of the vessel were corroded and no longer white or yellow on a dark background as intended.
46 CFR 31.25-1 & 46 CFR 42.13-40(a)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 12 November 2021
Resolved 1 November 2021
Resolution: Vsl rep had the load line and deck line on both sides repainted in white with a black background.
02 - Structural Conditions › N/A - No Subsystem › Beams, frames, floors-op. damage
Issued 3 November 2020
Resolved
Identified port bow rake set in 0-1" over an area of 45" in width by 20" in height, located between frames 0-1 at the 10'-11' draft mark. Operator to crop and renew as original.
Action required: 705 - Other - as specified
Due 9 November 2020
Resolved 9 November 2020
Resolution: The operator cropped and renewed the identified area found with structural damage. The repairs were witnessed by USCG.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 15 January 2019
Resolved
Thermal fluid heater units must be in a safe and satisfactory condition. Witnessed smoke during operation and visually saw heat spots on the forward thermal fluid heater unit. Use of the forward thermal fluid heater unit is restricted until you provide tech report. Tech report must verify replacement of external lagging/insulation providing adequate protection to prevent exhaust leaks and verification that tests were conducted to prove proper operation. 46 CFR 31.30-15 16c
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 January 2019
Resolved 22 February 2019
Resolution: Received tech report from vessel rep [name withheld], Inc. conducted maintenance and successfully ran unit for 20 mins without issues or leaks. Tests and shutdown alarms were conducted with satisfactory results; TFH unit was operating properly.