Records from 1984 to 1995. Most recent: inspection, 26 July 1995.
Inspection history · 29
26 July 1995
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 381211
18 October 1994
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 181150
12 July 1994
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 368506
7 May 1994
Tank Vessel Examination
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1457172
15 November 1992
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 494961
3 October 1992
Deficiency Check
Physical examination · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 1256344
13 August 1992
Certificate of Compliance
Administrative · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 1425273
6 February 1992
Damage Survey
Physical examination · MSO SAN JUAN · USCG Southeast District (CGD-SE) · Activity 1261133
1 January 1992
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 515081
1 January 1992
Damage Survey
Physical examination · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 1362605
31 December 1991
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 117256
31 July 1991
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 345141
31 July 1991
Certificate of Compliance
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 940943
17 July 1990
Certificate of Compliance · MARPOL Annex I Examination
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1231461
21 June 1989
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 1031427
20 March 1989
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 329072
9 February 1989
Certificate of Compliance
Administrative · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 1342965
11 August 1988
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 451950
11 August 1988
Type not recorded
No type recorded · MSO PHILADELPHIA · USCG East District (CGD-E) · Activity 1041301
11 May 1988
Type not recorded
No type recorded · COTP PHILADELPHIA · USCG East District (CGD-E) · Activity 323266
9 May 1988
Type not recorded
No type recorded · COTP PHILADELPHIA · USCG East District (CGD-E) · Activity 323326
16 February 1988
Type not recorded
No type recorded · COTP PHILADELPHIA · USCG East District (CGD-E) · Activity 523565
16 February 1988
Certificate of Compliance
Administrative · MIO PHILADELPHIA · USCG East District (CGD-E) · Activity 1021320
17 April 1987
Certificate of Compliance
Administrative · MSO SAN FRANCISCO BAY · USCG Southwest District (CGD-SW) · Activity 1000431
13 April 1987
Type not recorded
No type recorded · MSO LOS ANGELES/LONG BEACH · USCG Southwest District (CGD-SW) · Activity 315411
24 March 1986
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 307871
24 March 1986
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 999122
20 May 1985
Type not recorded
No type recorded · MIO PHILADELPHIA · USCG East District (CGD-E) · Activity 983329
18 November 1984
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1283249
Lifesaving
Issued 26 July 1995
Resolved
9 GHZ RADAR TRANSPONDER LOCATED ON STARBOARD SIDE OF WHEELHOUSE DID NOT SEND SIGNAL OUT TO BE WITNESSED ON RADAR SCREEN.
Condition: Unknown
Due 6 August 1995
Resolved 3 August 1995
Construction/Loadline
Issued 26 July 1995
Resolved
ODME WAS INOPERABLE.
Condition: Unknown
Due 6 August 1995
Resolved 26 July 1995
Construction/Loadline
Issued 13 August 1992
Resolved
CONDUCT 6 HOUR MONITORING/READINGS FOR LOWER EXPLOSIVE LIMIT ON #3 P & S BALLAST TANKS AND NOTIFY COTP PHILADELPHIA IF READING REACHES 100% LEL.
Condition: Unknown
Due 1 September 1992
Resolved 1 September 1992
Engineering
Issued 13 August 1992
Resolved
PRIOR TO RETURNING TO A U.S. PORT MAKE PERMANENT REPAIRS/REPLACEMENT OF THEABOVE DECK PIPE FOR THE INBOARD VENT FOR THE DIESEL OIL SETTLING TANK. LOCATION: WITHIN THE CONTAINMENT AT THE FORWARD PORT SIDE AREA OF THE AFT DECKHOUSE.
Condition: Unknown
Due 13 August 1992
Resolved 13 August 1992
Lifesaving
Issued 13 August 1992
Resolved
PRIOR TO RETURNING TO U.S. WATERS RENEW WASTED LADDER STEPS ON CENTER CAT_x001C_ WALK IN VICINITY OF THE MID-BODY MAIN DECK AREA.
Condition: Unknown
Due 13 August 1992
Resolved 13 August 1992
Construction/Loadline
Issued 13 August 1992
Resolved
PRIOR TO RETURNING TO THE U.S. PROVIDE CLASS SOCIETY REPORT IDENTIFYING REPAIRS TO THE COMMON BALLAST PIPING SYSTEM FOR #3 P & S AND BOW BALLAST TANKS. CLEAN AND PRESENT ALL BALLAST TANKS IN A GAS FREED CONDITION WITH AMARINE CHEMIST CERTIFICATE FOR AN INTERNAL EXAMINATION.
Condition: Unknown
Due 13 August 1992
Resolved 13 August 1992
Construction/Loadline
Issued 13 August 1992
Resolved
PRIOR TO DISCHARGING CARGO AT A SHORESIDE FACILITY IN THE PHILADELPHIA CAPTAIN OF THE PORT ZONE PROVIDE A DISCHARGE PLAN TO THE USCG CAPTAIN OF THE PORT BY 1200 14AUG92.
Condition: Unknown
Due 17 August 1992
Resolved 17 August 1992
Lifesaving
Issued 13 August 1992
Resolved
PRIOR TO RETURNING TO U.S. WATERS PROVIDE SPAN GAS FOR CALIBRATION OF COMBUSTIBLE GAS METER.
Condition: Unknown
Due 13 August 1992
Resolved 13 August 1992
Construction/Loadline
Issued 6 February 1992
Resolved
MAKE PERMANENT REPAIRS TO SHELL PLATING IN WAY OF #3 PORT BALLAST TANK TO THE SATISFACTION OF LOAD LINE ISSUING AUTHORITY. VESSEL TO PROVIDE COPY OF DNV REPAIR REPORT AND COMPLETED CG-2692 TO MSO SAN JUAN,PR. TO BE COMPLETEDBY NEXT U.S. PORT CALL.
Condition: Unknown
Due 6 February 1992
Resolved 6 February 1992
Navigation
Issued 1 January 1992
Resolved
MAKE REPAIRS TO A LEAK IN WAY OF A RUDDER POST BLOCK VANE PLUG LOCATED ON THE FORWARD PORTSIDE OF THE BLOCK IN STEERING COMPARTMENT PRIOR TO RETURNING TO A U.S. PORT.
Condition: Unknown
Due 1 January 1992
Resolved 1 January 1992
Construction/Loadline
Issued 31 July 1991
Resolved
AUTOMATIC OVERBOARD SHUTOFF VALVE ON THE OIL/WATER SEPERATOR SYSTEM MUST BEREPAIRED OR REPLACED PRIOR TO RE-ENTRY INTO U. S. WATERS._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 31 July 1991
Resolved 31 July 1991
Deck/Cargo
Issued 9 February 1989
Resolved
VESSEL NEEDS TO REPLACE A SECTION COW LINE #2 ON THE PORT SIDE FORWARD PRIOR TO RETURN TO US WATERS.33CFR157.122
Condition: Unknown
Due 9 February 1989
Resolved 9 February 1989
Navigation
Issued 11 May 1988
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Condition: Unknown
Due 11 May 1988
Resolved 11 May 1988
Navigation
Issued 9 May 1988
Resolved
[withheld — contains personal information; the deficiency system, dates, and resolution status are shown above]
Condition: Unknown
Due 9 May 1988
Resolved 9 May 1988
Fire Fighting
Issued 16 February 1988
Resolved
VESSEL IS IN VIOLATION OF SOLAS 74 CHAP.II-2 AMEND.81 REG.17 VESSEL MUST HAVE ON BOARD FOUR COMPLETE FIREMANS OUTFITS PRIOR TO DEPARTURE OF THE PORTOF PHILADELIPHIA
Condition: Unknown
Due 16 February 1988
Resolved 16 February 1988