Inspection history · 79
10 September 2018
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 6555605
7 August 2017
Deficiency Check
Physical examination · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 6234028
13 July 2017
Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 6208154
23 June 2016
Type not recorded
No type recorded · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 5916568
9 June 2016
Annual Inspection
Physical examination · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 5903023
1 February 2016
Administrative Inspection
Administrative · Sector Lower Mississippi · USCG Heartland District (CGD-H) · Activity 5807666
11 June 2015
MTSA Verification · Deficiency Check · Damage Survey · COI Inspection · Administrative Inspection · Examination of Repairs · Cargo Tank Internal · Internal Structural Exam
Physical examination · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 5150528
12 May 2015
Administrative Inspection
Administrative · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 5126093
9 June 2014
Administrative Inspection · MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 4884842
26 September 2013
Type not recorded
No type recorded · Marine Safety Unit Pittsburgh · USCG Heartland District (CGD-H) · Activity 4736921
5 October 2012
Annual Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 4457910
30 December 2011
Damage Survey
Physical examination · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 4218027
30 December 2011
Type not recorded
No type recorded · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 4218304
25 July 2011
Examination of Repairs · Deficiency Check
Physical examination · Sector Upper Mississippi River · USCG Heartland District (CGD-H) · Activity 4094078
21 July 2011
Damage Survey
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4090743
1 July 2011
COI Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 4064257
16 July 2010
Deficiency Check
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3797357
15 June 2010
Administrative Inspection · Internal Structural Exam · Annual Inspection
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3767378
16 May 2010
Administrative Inspection · Damage Survey
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3740250
6 January 2010
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3659771
16 September 2009
Deficiency Check
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3591930
31 August 2009
Damage Survey
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3583631
11 August 2009
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3562448
10 July 2009
Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3528931
3 July 2009
Damage Survey
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3522251
29 June 2009
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3518508
23 June 2009
Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3513715
17 April 2009
Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3451854
28 October 2008
Examination of Repairs · Periodic Inspection · MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3349997
3 July 2008
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3255641
26 June 2008
Administrative Inspection
Administrative · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3248848
24 June 2008
Examination of Repairs · Damage Survey
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3247481
11 June 2008
MTSA Verification · Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3233793
4 June 2008
Damage Survey
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3226991
15 May 2008
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3207119
17 March 2008
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3165907
13 March 2008
Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3159870
22 February 2008
Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3151755
19 February 2008
Examination of Repairs · Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3149732
13 February 2008
Damage Survey
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3146710
13 December 2007
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3115111
19 October 2007
Administrative Inspection
Administrative · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 3082999
23 August 2007
Type not recorded
No type recorded · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 3043152
24 February 2007
Type not recorded
No type recorded · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 2877156
6 September 2006
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 2771073
28 August 2006
Examination of Repairs
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2762258
27 August 2006
Damage Survey
Physical examination · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 2760923
31 October 2005
COI Inspection · MTSA Verification
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 2525713
4 February 2005
Examination of Repairs · COI Inspection · MTSA Verification · Internal Structural Exam · Hull Examination
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 2290565
23 January 2004
Annual Inspection
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 1991644
8 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1961018
19 February 2003
Periodic Inspection
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 1746435
13 February 2002
Annual Inspection
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 1486096
7 February 2001
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1373327
17 May 2000
Deficiency Check · Damage Survey
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1433662
30 March 2000
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 766233
30 March 2000
Damage Survey
Physical examination · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 1048412
29 March 2000
Type not recorded
No type recorded · MSO Corpus Christi · USCG Heartland District (CGD-H) · Activity 204607
18 February 2000
COI Inspection · Hull Examination · Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 813894
18 February 2000
Deficiency Check
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 815416
30 November 1999
Type not recorded
No type recorded · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 486439
14 January 1999
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 186979
11 January 1999
COI Inspection
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1336836
16 April 1998
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1396902
10 April 1998
Type not recorded
No type recorded · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 77456
10 April 1998
Damage Survey
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1123586
6 January 1998
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1116961
21 January 1997
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1447670
22 January 1996
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1425681
5 January 1996
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 185411
26 March 1995
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 178045
27 January 1995
COI Inspection · Hull Examination
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1145674
27 April 1994
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1168984
7 April 1994
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1169207
3 March 1994
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 854510
10 March 1993
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 833524
19 February 1992
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1366719
26 June 1991
Examination of Repairs
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1224608
29 March 1991
Initial Construction-Excluding Oversight · Initial Certification · Hull Examination
Physical examination · MSO LOUISVILLE · USCG Heartland District (CGD-H) · Activity 932631
Construction/Loadline › Structures › Cofferdam
Issued 13 July 2017
Resolved
TWO BONDO PATCHS FOUND ON STARBOARD SIDE CONTAINMENT COMBING ABOVE #3 TANK. CROP OUT DAMAGED AREA TO GOOD METAL AND RENEW TO ORIGIONAL CONDITION.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 27 August 2017
Resolved 11 August 2017
Resolution: Corrected to the satisfaction of the attending marine inspector.
Documentation › Manuals/Policy Documentation › Tank Vessel Loading Information
Issued 9 June 2016
Resolved
Missing Benzene Plan
Action required: 705 - Other - as specified
Due 9 July 2016
Resolved 24 June 2016
Resolution: Revieed benzene plan provided by the o/o. Sat.
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 11 June 2015
Resolved
Provide MSC approval letter for renewed vapor control piping. 46CFR39.10-13(a)
Due 30 August 2015
Resolved 26 August 2015
Documentation › Certificates/Documents › Certificate of Inspection
Issued 11 June 2015
Resolved
Make name change to approved CAA to reflect actual barge name 46CFR151.04-1(c).
Due 30 August 2015
Resolved 26 August 2015
Documentation › Certificates/Documents › Certificate of Inspection
Issued 12 May 2015
Resolved
Over due for Dry Dock exam
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 July 2015
Construction/Loadline › Hull › Hull Plating
Issued 22 July 2011
Resolved
Barge has a pin hole leak in the #4 wing void.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 22 August 2011
Resolved 25 July 2011
Resolution: The pin hole leak to the bottom plate in the #4 stbd void was repaired with a 18 inch by 18 inch insert while in drydock at Mike''s Marine in Woodriver, IL. The viod was air tested. The void was entered and the weld was observed from the inside.
Documentation › Safety/Response Plans/Programs › Vessel Response Plan
Issued 15 June 2010
Resolved
Vessel Response plan not onboard.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 1 July 2011
Documentation › Manuals/Policy Documentation › Transfer Procedures
Issued 15 June 2010
Resolved
Transfer procedures not onboard
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 1 July 2011
Deck/Cargo › Holds/Tanks › Liquid Level Gaging
Issued 15 June 2010
Resolved
Max Gauging not permanently marked at ullage or sounding tubes.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 16 July 2010
Resolution: Max gauging punched into deck and painted.
Electrical › Lighting (service) › Lighting Fixture
Issued 15 June 2010
Resolved
Navigational light stanchions broken.
Action required: 705 - Other - as specified
Due 13 August 2010
Resolved 16 July 2010
Resolution: Light Stanchions renewed.
Construction/Loadline › Structures › Longitudinal Bulkhead
Issued 6 January 2010
Resolved
Complete Internal Structural Examination prior to loading cargo but no later tha expiration of COI (01 NOV 2010).
Action required: 701 - Prior to carriage of passengers/cargo
Due 1 November 2010
Resolved 13 July 2010
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 3 July 2009
Resolved
Pinhole leak on the vapor recovery pipeline at the weld seam connecting the main trunk with the line that branches off to the #2 cargo tank.
Condition: Unknown
Action required: 705 - Other - as specified
Due 3 August 2009
Resolved 10 July 2009
Resolution: Replaced Vapor line branch to #2 Cargo tank. Witnessed satisfactory hydro test to 188psi.
Construction/Loadline › Hull › Weld
Issued 23 June 2009
Resolved
Vessel had discovered a hole in #3 port cargo tank which was caused by metal wastage. The hole was was on upper trunk of cargo tank and leaking VGO Low sulfur diesel on to deck.
Action required: 705 - Other - as specified
Due 25 June 2009
Resolved 29 June 2009
Resolution: Conducted repair check. Examined welds and witnessed satisfactory air test of 18"x3''x5/16" insert on the #3 cargo tank.
Construction/Loadline › Hull › Hull Plating
Issued 24 June 2008
Resolved
Received report from Sec NOLA that barge crewmembers discovered a pinhole leak, at deck level, portside between tanks 3 & 4. Duty MI attended barge and verified that the reported pinhole was temporarily repaired. An 835 was issued by Sector NOLA to make the barge available for inspection when in Houma's AOR. Another 835 was issued by Houma to be cleared once barge arrives at West Lake, LA.
Action required: 705 - Other - as specified
Resolved 3 July 2008
Resolution: Conducted repair check. Examined welds and witnessed satisfactory air test of an 18" x 24" x 3/8" cargo tank top insert to #4 cargo tank port side.
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 3 June 2008
Resolved
Crack in VCS stack line on number 1 cargo tank.
Condition: Unknown
Action required: 705 - Other - as specified
Due 18 June 2008
Resolved 11 June 2008
Resolution: cropped out section of pipe and stub out.
Construction/Loadline › Penetrations › Pipe Flange
Issued 3 June 2008
Resolved
Stand pipe for number 5 cargo tank has running crack completely around pipe.
Action required: 705 - Other - as specified
Due 18 June 2008
Resolved 11 June 2008
Resolution: Renewed the 2" stub out for the restricted gauging.
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 3 June 2008
Resolved
Test cargo tanks and vapor control system to ensure integrity of barge.
Action required: 705 - Other - as specified
Due 18 June 2008
Resolved 11 June 2008
Resolution: Witness sat vapor tightness test
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 22 February 2008
Resolved
Vsl has 4in fracture in vapor line IWO #5 cargo tank. Crop and renew as new
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 March 2008
Resolution: Vessel Vapor drop piping C/R 4'' X 8" pipe flange on #5 cargo tank.
Deck/Cargo › Holds/Tanks › Liquid Level Gaging
Issued 22 February 2008
Resolved
Small pin hole In closed guaging pipe IWO #4 cargo tank. Crop and renew as new.
Condition: Unknown
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 17 March 2008
Resolution: 2'' x2'' x 5/16" tank top #4 cargo tank air tested all satisfactory.
Construction/Loadline › Hull › Hull Plating
Issued 13 February 2008
Resolved
Repair area IWO aft rake main deck mooring bitt.
Action required: 705 - Other - as specified
Due 20 February 2008
Resolved 19 February 2008
Resolution: Witnessed installation of deck bits on the port and starboard deck located on the stern box.
Deck/Cargo › Vapor Control Systems › Piping/Hoses
Issued 27 August 2006
Resolved
Fracture in way of #5 vapor header pipe.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 28 August 2006
Resolution: Rewelded and tested satisfactorily.
Deck/Cargo › Holds/Tanks › Liquid Level Gaging
Issued 27 August 2006
Resolved
FRACTURE TO #4 CARGO TANK CLOSED GAUGING COLLAR.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 28 August 2006
Resolution: Rewelded and tested satisfactorily.
Navigation › Collision/Grounding Avoidance
Issued 23 January 2004
Resolved
Nav screens are faded, instructed tankerman to re-paint flat black. LEGACY COMPONENT DESC: Navigation Lights
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 26 January 2004
Resolved 26 January 2004
Construction/Loadline › Hull
Issued 23 January 2004
Resolved
4 inch deep by 15 inch wide inset at sheer strake, continues downward approx 5 feet. Damage needs to be assesed for repair during 2005 internal hull examination LEGACY COMPONENT DESC: Sheerstrake
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 18 February 2005
Resolved 27 January 2004
Resolution: Def was moved to a special note.
Deck/Cargo
Issued 30 March 2000
Resolved
PROVIDE #1 CARGO TANK & STERN RAKE IN GAS FREE CONDITION FOR INTERNAL EXAMINATION BY ATTENDING MARINE INSPECTOR PRIOR TO CONDUCTING ANY FURTHER CARGO OPERATIONS.
Condition: Unknown
Due 30 March 2000
Resolved 30 March 2000
Construction/Loadline
Issued 11 January 1999
Resolved
MAKE PERMANENT REPAIRS TO APPX 144 SQFT INSET IN PORT BOW RAKE SIDESHELL, ADJACENT GUNWALE, AFFECTED STRUCTURAL MEMBERS, AND AFFECTED DECK PLATE TO THE SATISFACTION OF AN ATTENDING USCG MARINE INSPECTOR.
Condition: Unknown
Due 11 January 1999
Resolved 11 January 1999
Deck/Cargo
Issued 10 April 1998
Resolved
MAKE PERMANENT REPAIRS TO STEAM HEATER SYSTEM FOR #4 HOLDING TANK, DUE TO SUPPECTED HOLE IN STEAM COIL PIPING. THE WHOLE STEAM SYSTEM IS TO BE PRESSURE TESTED TO ASCERTAIN THAT NO OTHER HOLES ARE PROBLEMS EXIST.
Condition: Unknown
Due 22 April 1998
Resolved 22 April 1998
Engineering
Issued 6 January 1998
Resolved
Provide mechanical plug for engine fuel tank drain valve.
Condition: Unknown
Due 6 January 1998
Resolved 30 January 1998
Deck/Cargo
Issued 21 January 1997
Resolved
HYDRO TEST CARGO PIPING / PRESSURE GAUGES IAW 33 CFR 156.170_x001C_
Condition: Unknown
Due 1 February 1997
Resolved 1 February 1997