Records from 2007 to 2026. Most recent: operational control imposed, 13 May 2026.
Everything above is free. The detail below — the inspection history, the deficiency record, the operational controls, the tow units, the recorded names, the casualty record and the documentation record — is Professional, $39 a month. Sign in.
Inspection history · 25
13 May 2026
Vessel Attendance · Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 8372787
27 March 2026
In-Service Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 8340873
12 March 2026
Administrative Inspection · ACP Additional Oversight – Risk Assessment
Administrative · Marine Safety Unit Port Canaveral · USCG Southeast District (CGD-SE) · Activity 8325225
21 January 2026
Administrative Inspection · COI Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 8299777
8 October 2025
Administrative Inspection
Administrative · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8249515
22 May 2025
Drydock Exam · Internal Structural Exam · Cargo Tank Internal · Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8141614
8 May 2025
Administrative Inspection · Deficiency Check · In-Service Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 8131061
6 May 2025
Administrative Inspection
Administrative · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 8129749
8 May 2024
Periodic Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7908732
16 October 2023
Administrative Inspection
Administrative · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 7809637
31 July 2023
Type not recorded
No type recorded · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7763161
9 June 2023
Drydock Exam · Administrative Inspection
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 7710633
4 May 2023
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7681181
3 May 2023
Administrative Inspection
Administrative · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7680392
21 April 2022
Annual Inspection · Deficiency Check
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7435717
22 March 2021
COI Inspection · MTSA Verification · Deficiency Check
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7157940
29 September 2020
Drydock Exam · Administrative Inspection · Cargo Tank Internal · Internal Structural Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 7067632
21 May 2020
MTSA Verification · Administrative Inspection · Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6957265
5 June 2019
Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6704825
26 October 2018
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6568774
10 July 2018
Administrative Inspection · Internal Structural Exam · Hull Examination · Examination of Repairs
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 6475309
19 April 2018
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6395552
21 April 2017
Annual Inspection · MTSA Verification
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6129806
25 March 2016
MTSA Verification · COI Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5840231
20 January 2016
Administrative Inspection · In-Service Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5818161
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 13 May 2026
Resolved
No repairs or alterations affecting the safety of the vessel with regard to the hull, machinery, or equipment, shall be made without the knowledge of the Officer in Charge, Marine Inspection. The vessel's starboard engine flex coupling failed rendering the engine inoperable. Your vessel is prohibited from transiting any port within the Sector Honolulu COTP Zone without the assistance of a towing vessel of adequate horsepower and maneuverability. The towing vessel shall be under the direction and control of an individual holding a Merchant Marine Credential (MMC) authorizing them to engage in assistance towing under the provisions of 46 CFR Part 11.482. Your vessel is prohibited from departing any port within the Sector Honolulu COTP Zone until satisfactory repair of the vessel is completed, and the proper operation of the propulsion system is demonstrated to the satisfaction of the attending Marine Inspector. 46CFR91.45-1(a)
Condition: Improper/Lack of Maintenance
Action required: 25 - Ship denied entry
Resolved 21 May 2026
Resolution: Replaced Vulcan coupling. Op test SAT.
11 - Life Saving Appliances › N/A - No Subsystem › Inflatable liferafts
Issued 10 February 2026
Resolved
The liferafts must be supplemented with additional liferafts to bring the total capacity of the liferafts available on each side of the vessel to at least 100 percent of the total number of persons on board.
Condition: Improper/Lack of Maintenance
Action required: 60 - Rectify deficiencies prior to movement
Due 10 February 2026
Resolved 18 February 2026
Resolution: 02 extra liferafts added to each side preparing for international route which was above the requirement writen. Total 6 rafts 25 each.
01 - Certificates & Documentation › 011 - Ships Certificates › Load Lines (including Exemption)
Issued 10 February 2026
Resolved
Each vessel subject to load line requirements shall carry a valid certificate. LL11D is not updated with to match hatch modifications.
Condition: Improper/Lack of Maintenance
Action required: 60 - Rectify deficiencies prior to movement
Due 10 February 2026
Resolved 18 February 2026
Resolution: ABS attended updated the LL 11D.
11 - Life Saving Appliances › N/A - No Subsystem › Lifebuoys incl. provision and disposition
Issued 10 February 2026
Resolved
Ring buoys on bridge should, when released, fall to the water directly into the water without striking any part of the vessel. Prove the Bridge buoys can be released and clear the vessel.
Condition: Improper Installation
Action required: 60 - Rectify deficiencies prior to movement
Due 10 February 2026
Resolved 18 February 2026
Resolution: Vessel representative took video of buoy and a jug in place of the smoke being deployed.
11 - Life Saving Appliances › N/A - No Subsystem › Line-throwing appliance
Issued 10 February 2026
Resolved
Four service lines, cleaning brush, and instructions are required for a line throwing appliance. Kit is incomplete IAW CFR, bring line throwing kit to compliance.
18FEB26- 04 New Impulse onboard missing the 160.040-4 02 Buoyant type and 199.170(c)(2) 1500 ft of line. Only 600 ft onboard.
Condition: Improper/Lack of Maintenance
Action required: 60 - Rectify deficiencies prior to movement
Due 10 February 2026
Resolved 19 February 2026
Resolution: Buoyant type and 1500 feet of line onboard.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 10 February 2026
Resolved
Electric installations on vessels must ensure protection of crew from electrical hazards. Control switch in the bow thruster escape trunk was open exposing personnel to electrical hazard.
Action required: 60 - Rectify deficiencies prior to movement
Due 10 February 2026
Resolved 18 February 2026
Resolution: Control switch latch corrected allowing it to be closed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 10 February 2026
Resolved
Marine Inspector shall test machinery to check safe operation. During PSTP testing of the port M/E the high RMP Low oil pressure should alarm at 40 PSI, didn’t alarm until 20 which is the setting for low RPM.
Condition: Invalid
Action required: 60 - Rectify deficiencies prior to movement
Due 10 February 2026
Resolved 18 February 2026
Resolution: WItnessed the low L/O alarms for low and high RPM on both MDE's
09 - Working and Living Conditions › 092 - Working Conditions › Protection machines/parts
Issued 10 February 2026
Resolved
All machinery shall be provided with adequate guards or covers. The OWS pump motor missing junction cover and fan guard.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 10 February 2026
Resolved 18 February 2026
Resolution: Guard and Juntion box cover installed
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 10 February 2026
Resolved
It is the duty of the Chief Engineer when assuming charge of machinery of a vessel to examine thoroughly if any items are bad they shall be reported to the Master [name withheld] on the #3 generator leaking oil.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 10 February 2026
Resolved 19 February 2026
Resolution: CAT tech installed new seal and tested no leaks.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 10 February 2026
Resolved
Gages on pressure vessels shall be 1.2 but not more than 2 times the setting of the PRV. Valves set to 275 psi gages for the center and port air receivers are 0- 600 psi.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 10 February 2026
Resolved 18 February 2026
Resolution: Gages installed 0-400 psi.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 10 February 2026
Resolved
Oil strainers and other equipment subject to normal leakage must be fitted with drip pans. Fuel oil strainers in the engine room did have drip pans.
Condition: Invalid
Action required: 17 - Rectify deficiencies prior to departure
Due 10 February 2026
Resolved 18 February 2026
Resolution: Drip pans installed.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 10 February 2026
Resolved
Where fire extinguishing equipment is installed but not required it must meet the requirements of this part. Galley window auto closure for control of the spread of a fire is not functioning.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 10 February 2026
Resolved 18 February 2026
Resolution: Link replaced and put back on track.
07 - Fire Safety › N/A - No Subsystem › Fixed fire extinguishing installation
Issued 10 February 2026
Resolved
A fixed CO2 or other approved system must be installed in all paint lockers. Large paint locker did not have CO2 system installed.
Condition: Placed in Improper Service
Action required: 17 - Rectify deficiencies prior to departure
Due 10 February 2026
Resolved 18 February 2026
Resolution: Large paint locker removed.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 10 February 2026
Resolved
Instructions and illustrations must be posted with information on the donning of life jackets. Additional life jackets did not have donning instructions posted for multiple types onboard.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Due 10 February 2026
Resolved 18 February 2026
Resolution: Both lifejacket instructions posted.
02 - Structural Conditions › N/A - No Subsystem › Ballast, fuel and other tanks
Issued 8 May 2025
Resolved
In general, compliance with the standards established
by the American Bureau of Shipping, see subpart 90.35
of this subchapter, will be considered as satisfactory
evidence of the structural efficiency of the vessel.
Vessel informed OCMI that there is a pinhole leak in
the slop tank leading to water ingress into the engine
room.
Condition: Improper Installation
Action required: 17 - Rectify deficiencies prior to departure
Resolved 22 May 2025
Resolution: MI inspected the vessel in dry dock and witnessed successful repair and NDT test.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 21 April 2022
Resolved
The general construction of the vessel shall be such as to minimize fire hazards insofar as is reasonable and practicable. Marine Inspector observed the stairwell landing on the 01 Deck is required to meet structural fire protection standards, however a new electrical cable installed through the multi-cable transit was not properly fitted; compromising the fire protection integrity of the space. A plan on how to complete this repair is to be developed and submitted within 30 days. 46 CFR 92.07-10(d)(2)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 21 May 2022
Resolved 4 May 2022
Resolution: A satisfactory repair proposal was submitted and accepted.
04 - Emergency Systems › N/A - No Subsystem › Emergency, lighting, batteries and switches
Issued 21 April 2022
Resolved
The following emergency lights must be supplied from a distribution panel on the navigating bridge: Emergency lights on the navigating bridge. Marine Inspector observed one emergency light not working in the navigating bridge.46 CFR 112.43-7(a)(4)(ii)
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 5 May 2022
Resolved 21 April 2022
Resolution: Emergency lights were fixed.
11 - Life Saving Appliances › N/A - No Subsystem › Rescue boats
Issued 22 March 2021
Resolved
Before the vessel leaves port and at all times during the voyage, each lifesaving appliance must be in working order and ready for immediate use. Marine Inspectors observed that the port side rescue boat was able to launch and maneuver approximately 50 yards away from the vessel before the engine on the rescue boat became inoperable. Effect permanent repairs to the effected equipment to the satisfaction of the attending US Coast Guard Inspectors.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 5 April 2021
Resolved 25 March 2021
Resolution: Witnessed a sat. op. test of the engine.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 22 March 2021
Resolved
If two or more voice communication stations are near each other, there must be a means that indicate the station called. Marine Inspectors attempted to contact one sound powered phone station on the bridge from another sound powered phone station on the bridge, and could not clearly hear the audible indicator emitting from the sound powered phone being hailed. Effect permanent repairs to all of the effected sound powered phone stations through out the vessel exhibiting the same issue to the satisfaction of the attending US Coast Guard Inspector.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 5 April 2021
Resolved 25 March 2021
Resolution: Witnessed a sat. op. test of the two sound powered phone units on the bridge.
07 - Fire Safety › N/A - No Subsystem › Division - decks, bulkheads and penetrations
Issued 22 March 2021
Resolved
The boundary bulkheads and decks separating the accommodations and control stations from cargo and machinery spaces, galleys, main pantries, and storerooms, other than small service lockers, shall be of "A" Class construction. Marine Inspectors observed a 3 FT. by 3 FT. panel of insulation had been removed from the bulkhead in order to conduct maintenance. Effect permanent repairs to the "A" Class boundary to the satisfaction of the US Coast Guard attending Marine Inspectors.
Condition: Placed in Improper Service
Action required: 16 - Rectify deficiencies w/in 14 days
Due 5 April 2021
Resolved 25 March 2021
Resolution: Foam panel inserted back into place.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 22 March 2021
Resolved
The spring in a relief valve for pressures greater than 250 psi, the spring shall not be reset for any pressure more than 5 percent above that for which the valve is marked. Marine Inspectors were unable to verify proper operation of 2 relief valves on air receivers. The valves were marked for 275psi and did not relieve when the gauge read over 285 psi. Operator replaced relief valves and corrected the issue on the spot.
Condition: Improper/Lack of Maintenance
Action required: 10 - Deficiency Rectified
Due 22 March 2021
Resolved 22 March 2021
Resolution: Operator replaced relief valves and corrected the issue on the spot.
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 26 October 2018
Resolved
inset to side shell which also serves as #4 cargo tank bulkhead. also damage to the deck/tank top in the form of crushed metal. see attached pics.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 29 October 2018
Resolution: ABS surveyor witnessed NDT of the inset and deck weld seal and creased metal and determined the damaged area does not currently effect vessel integrity. USCG MI requiring at next dry dock the crushed deck area and side shell inset be repaired.