Fire Fighting › Fixed CO2 Fire Extinguishing System › Piping
Issued 6 November 2017
Resolved
Each piping in a CO2 must be securely supported and protected from damage. CO2 piping for turbine # 2 is dry rotted and cracked. Replace/repair to original condition.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 13 November 2017
Resolved 17 November 2017
Resolution: Received email with several pictures showing that the hoses had been properly replaced.
Electrical › Electrical Distribution System (service) › Wiring
Issued 6 November 2017
Resolved
Several cable installations improperly installed, spliced, or terminated throughout the facility. Systemic improper wiring installations. Go over wiring and remove dead-end cables, improperly spliced wiring and power strips used as a permanent installation. Replace/repair to original design.
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 6 December 2017
Resolved 20 November 2017
Resolution: Received email with several pictures showing that the electrical issues that were found including multiple power strips had been properly repaired or removed.
Documentation › Certificates/Documents › Permit, Other
Issued 6 November 2017
Resolved
While repair or other work being performed on equipment, proper lock out tag out to be performed. Several incorrect lock out tag out entries in book. Audit entire log book and make corrections, remove permanently uninstalled equipment tags.
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Due 6 December 2017
Resolved 27 November 2017
Resolution: Received email from OIM stating that the Lock Out Tag Out log had been audited and updated.
Fire Fighting › Structural - A Class Divisions › Machinery Spaces
Issued 6 November 2017
Resolved
Each boundary of a space containing an emergency power source must be an A-Class boundary. Portable air-conditioner unit permanently installed into the Emergency Generator enclosure bulkhead. Large cut-out for this installation. Work with Class (ABS) to prove that the affected bulkhead still meets A-0 class fire boundary requirements in accordance with NVIC-09-97 Ch.1
Condition: Improper Installation
Action required: 705 - Other - as specified
Due 20 November 2017
Resolved 28 November 2017
Resolution: Received email from ABS Class Surveyor [name withheld] (full email in narrative) who stated that the air conditioner installation was in full ABS Compliance.
Operations/Management › Vessel Safety Management › Safety/Environmental Protection Policy
Issued 6 November 2017
Resolved
Before personnel enter an atmosphere specificied under ANSI 288.2 requiring the use of equipment, the persons shall ensure that procedures are followed, personnel are trained, respiratory protection is approved. Crew regularly handles hexane and has no protection equipment, procedures in place, or training. Follow all requirements in 33CFR142.39(b).
Condition: Placed in Improper Service
Action required: 705 - Other - as specified
Due 20 November 2017
Resolved 30 November 2017
Resolution: Received email from the OIM stating that all the crew have received fit tests for the respitory equipment and received proper training for handling of the chemicals to be used onboard.
Electrical › Electrical Distribution System (emergency) › Switchboard
Issued 1 February 2017
No resolution recorded
Transfer of power to emergency power source shall occur within 45 seconds of loss of power. EDG did not supply emergency buss when emergency bustie breaker in the EDG space was opened. Prove proper operation IAW 46 CFR 112.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 3 March 2017 — due date passed with no resolution recorded
Electrical › Lighting (emergency) › Lighting Fixture
Issued 1 February 2017
No resolution recorded
Lighting for survival craft launching, including muster station, embarkation stations, the survival craft, its launching appliance and the area of the water where it is to be launch shall be supplied by the emergency power source. Inadequate e-lighting was installed for lifeboat #3, liferaft stations, and water below survival craft. Install emergency light to illuminate the aforementioned areas.
Condition: Design Flaw
Action required: 705 - Other - as specified
Due 3 March 2017 — due date passed with no resolution recorded
Lifesaving › Launching Appliances › Release Mechanism
Issued 30 January 2017
Resolved
Each lifeboat must be provided w/ a launching appliance...capable of launching and recovering the lifeboat. Lifeboat #3 was unable to be launched/lowered. Take lifeboat #3 out-of-service, notify crew as appropriate, restrict POB to 21 persons.
Condition: Improper/Lack of Maintenance
Due 13 February 2017
Resolved 7 February 2017
Resolution: Received servicing report from SOS stating the brake band was too tight and has since been repaired.
Operations/Management › Lifesaving › Op Readiness/Maintenance/Inspection
Issued 30 January 2017
No resolution recorded
Lifeboat maintenance: Monthly inspections: Each lifesaving appliance, including lifeboat equipment, must be inspected monthly using the checklists required under paragraph (b) [manufacture's instruction] of this section to make sure it is complete and in good
working order. Lifeboat #2 emergency steering inoperable, excessive discolored
liquid in bilge, inop boat drain, EPIRB registration exp
Condition: Improper/Lack of Maintenance
Due 13 February 2017 — due date passed with no resolution recorded
Resolution: Follow manufacturers
instructions to complete satisfactory self-inspection. All lifesaving appliances shall
be in good working order and ready for immediate use.
Fire Fighting › Fire Pumps › Power Source
Issued 30 January 2017
Resolved
A fire main system must have at least two independently driven
fire pumps. Fire pump bravo's prime mover ran away and tripped offline by
overspeed protection. Fire pumps have been unsat as per Class and USCG
during previous survey/inspection.
Condition: Improper/Lack of Maintenance
Due 13 February 2017
Resolved 1 February 2017
Resolution: USCG witnessed fire pump operation. USCG examined corroded 120% overspeed jumper that prevented proper operation.
Operations/Management › Drills/Instruction › Launching/Recovery of Survival Craft
Issued 30 January 2017
No resolution recorded
Instructions for the operation of a fixed fire
extinguishing system must be posted next to a fire apparatus described in
paragraph (a) of [108.631]. Each unit must have posters or signs displayed in the
vicinity of each survival craft and the survival craft's launching controls that
illustrate the purpose of controls, illustrate the procedures for operating the
launching device, give relevant
Condition: Improper/Lack of Maintenance
Due 13 February 2017 — due date passed with no resolution recorded
Resolution: Two lifeboats, both liferafts, and fixed CO2 system serving
HP flare scrubber instructions need to be IAW w/ cited regs.
Fire Fighting › Fire Pumps › Gland Sealing
Issued 17 August 2016
Resolved
Packing glands on both firepumps were leaking excessive amounts of water. Repair to original.
Due 17 September 2016
Resolved 17 September 2016
Resolution: Received email from vessel rep stating deficiency was cleared.
Fire Fighting › Fire Pumps › Pressure
Issued 17 August 2016
Resolved
"A" Firepump is leaking water from its relief valve. Renew relief valve.
Due 17 September 2016
Resolved 21 August 2016
Resolution: Received email from vessel rep stating deficiency was cleared.
Fire Fighting › Fire Pumps › Casing
Issued 17 August 2016
Resolved
"A" firepump is leaking jacket water through cracked piping near J/W cooler. Renew to original.
Due 17 September 2016
Resolved 18 August 2016
Resolution: Received email from vessel rep stating deficiency was cleared.
Fire Fighting › Structural Fire Protection - General › Accommodation Space Protection
Issued 17 August 2016
Resolved
Structural fire protection in galley was missing two sections. Repair to original.
Due 17 September 2016
Resolved 17 September 2016
Resolution: Received email from vessel rep stating deficiency was cleared.