Records from 2016 to 2024. Most recent: inspection, 18 March 2024.
Inspection history · 25
18 March 2024
PSC B
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7880023
2 November 2023
Type not recorded
No type recorded · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7819543
5 September 2023
COC-GAS Annual · PSC B
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7780627
21 August 2023
Type not recorded
No type recorded · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7773838
9 November 2022
COC-GAS Renew · PSC B · Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7592445
24 October 2022
Type not recorded
No type recorded · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7580071
8 August 2022
PSC B
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7528228
26 April 2022
PSC B
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7433501
20 January 2022
Deficiency Check · PSC B
Physical examination · Resident Inspection Office Ponce · USCG Southeast District (CGD-SE) · Activity 7381932
8 November 2021
PSC B · COC-GAS Annual · Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 7345070
9 November 2020
PSC B · COC-GAS Renew
Physical examination · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 7090886
21 August 2020
Type not recorded
No type recorded · Sector Virginia · USCG East District (CGD-E) · Activity 7039216
15 August 2020
Type not recorded
No type recorded · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 7033544
13 August 2020
Administrative Inspection
Administrative · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 7029917
11 August 2020
Type not recorded
No type recorded · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 7029927
24 May 2020
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6959063
10 November 2019
Administrative Inspection · Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6853133
17 October 2019
COC-GAS Annual · ISPS II Exam · Ballast Water Examination
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6835200
7 August 2019
Type not recorded
No type recorded · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6788705
4 June 2019
Deficiency Check
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6703658
7 May 2019
In-Service Inspection
Physical examination · Sector Honolulu · USCG Oceania District (CGD-O) · Activity 6678433
6 October 2018
ISPS II Exam · COC-GAS Renew · Ballast Water Examination
Physical examination · Resident Inspection Office Ponce · USCG Southeast District (CGD-SE) · Activity 6554895
6 October 2018
Type not recorded
No type recorded · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6556067
4 October 2018
Type not recorded
No type recorded · Sector San Juan · USCG Southeast District (CGD-SE) · Activity 6554530
13 October 2016
Ballast Water Examination · COC-GAS Renew · ISPS II Exam
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 6018790
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 9 November 2022
Resolved
The system should be capable of covering all areas mentioned in 11.3.1 with a uniform distributed water spray of at least 10 cubic meters per minute for horizontal surfaces and 4 cubic meters per minute for vertical services. Deck spray nozzles for cargo pump motor room vertical surface did not provide a uniformly distributed water-spray to cover this area of the vessel.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 14 November 2022
Resolution: Class - RINA, provided follow-up report attesting to the repairs of the deck water spray system and its operation to their satisfaction. Deficiency cleared.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 20 January 2022
Resolved
Where operational or structural requirements are such as to make it impossible to comply with the method described in 10.2.4.2, motors of the following certified safety types may be installed of increased safety type with flameproof enclosure. Cargo pump junction boxes on tanks 2 port and starboard and 3 starboard are using red sealant to make gas tight.
-SOLAS74(20 Amend) Chapter VII/Reg. 12 IGC93 ed. 10.2.4.3.1
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 26 January 2022
Resolution: Junction boxes overhauled and sealant removed.
07 - Fire Safety › N/A - No Subsystem › Operation of Fire protection systems
Issued 20 January 2022
Resolved
The system should be capable of covering all areas mentioned in 11.3.1 with a uniform distribution water spray of at least 10L/m^2 per minute. 12 deck spray nozzles were plugged or did not provide a uniform distributed spray.
-SOLAS74(20 Amend) Chapter VII/Reg. 12 IGC93 ed. 11.3.2
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 26 January 2022
Resolution: All spray nozzles were overhauled, cleaned, and flushed.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 20 January 2022
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provision of the present convention. Incinerator door had excessive deterioration on the steel plate and insulation.
-73/78MARPOL(2017) ANNEX 1 Reg. 6.4.1
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 26 January 2022
Resolution: Steel plate and insulation was replaced in incinerator.
10 - Safety of Navigation › N/A - No Subsystem › Pilot ladders and hoist/pilot transfer arrangements
Issued 20 January 2022
Resolved
The appliances shall be kept clean, properly maintained, and stowed and shall be regularly inspected to ensure that they are safe to use. 01 pilot ladder ladder had excessive fraying on the ropes and excessive play between the steps.
--SOLAS74(20 Amend) Chapter V/Reg. 23.2.1
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 26 January 2022
Resolution: New pilot ladder purchased and onboard.
01 - Certificates & Documentation › 011 - Ships Certificates › Other (certificates)
Issued 20 January 2022
Resolved
Install and operate a ballast water management system(BWMS) that has been approved by the Coast Guard under 46CFR Part 162. Vessel is operating from an outdated BWM tech manual. Coast Guard approval letter has version 2.6.4 dated October 13, 2018.
-33CFR151.2025(a)(1)
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 26 January 2022
Resolution: Vessel received correct tech manual.
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Maintenance of the ship and equipment
Issued 8 November 2021
Resolved
Objective evidence discovered in an expanded ISM examination revealed the following major nonconformity: the vessel failed to fully implement the requirements of the SMS. The vessel failed to fully establish maintenance procedures to ensure the ship is maintained in conformity with the provisions of the relevant rules. This is made evident by deficiencies 02, 03, 04, and 05. Ship's maintenance records state that the gas detectors, the valves measured by the cargo control room indicators, and the deck water spray system, were tested satisfactorily by the ship's crew the day prior to this examination. Deficiency 06 shows that the vessel did not meet the requirement to provide for safe practices in ship operation and a safe working environment. Additionally, deficiency 7 shows that the management of change procedures in Section 2.2 of the SMS, which shall be applied to changes in the operational management of ships, were not properly implemented. An external audit is required.
Condition: Invalid
Action required: 30 - Ship detained
Due 23 November 2021
Resolved 23 November 2021
Resolution: RINA issued an additional non-conformity for crews failure to follow change management procedures, as outlined in their SMS. This, and the previously submitted RINA audit findings, has addressed the substandard conditions found on 08NOV2021.
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 8 November 2021
Resolved
The system should be capable of covering all areas mentioned in 11.3.1 with a uniform distributed water spray of at least 10 l/m2 per minute for horizontal surfaces and 4 l/m2 per minute for vertical services. Many deck spray nozzles were plugged or did not provide a uniform distributed water spray to cover all areas on the vessel mentioned in 11.3.1, including roughly 50% of nozzles on both cargo manifolds and the superstructure, and over 50% of nozzles over the #1 port and starboard cargo tanks.
Condition: Improper/Lack of Maintenance
Action required: 30 - Ship detained
Resolved 14 November 2021
Resolution: Received RINA report attesting to repairs to the deck water spray sysetm. Attended the vessel on 14NOV2021 and confirmed repairs and satisfactory function of system.
09 - Working and Living Conditions › 091 - Living Conditions › Electrical devices
Issued 8 November 2021
Resolved
Where electrical equipment is installed in gas-dangerous spaces or zones as provided in 10.1.4, it should be to the satisfaction of the Administration and approved by the relevant authorities recognized by the Administration for operation in the flammable atmosphere concerned. Multiple certified safe type pieces of equipment in gas-dangerous locations on deck and in the cargo compressor room have issues compromising their intrinsic safety and explosion proof properties, such as improper glands, missing nuts and bolts or improperly sized bolts preventing securing, and loose, improperly terminated electrical conductors.
Condition: Improper Installation
Action required: 30 - Ship detained
Resolved 27 November 2021
Resolution: Sector Honolulu received Class survey report and numerous emails with photographic evidence indicating that all called out electrical hazards have been addressed.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Atmosphere testing instruments
Issued 8 November 2021
Resolved
Gas detection equipment should be so designed that it may readily be tested. During examination both redundant systems were inoperable, and troubleshooting and cleaning could only make two of the nine sample points operable.
Condition: Improper/Lack of Maintenance
Action required: 30 - Ship detained
Resolved 23 November 2021
Resolution: Sector Honolulu received attended the vessel on 14NOV2021 after receiving RINA report of repair. Received email on 22NOV2021 attesting to identification of the cause of the failure and rectification of the fixed gas detection system.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 8 November 2021
Resolved
The condition of the ship and its equipment should be maintained to conform with the provisions of the code to ensure the ship will remain fit to proceed to sea without danger to the ship or persons onboard. Three temperature sensors and numerous vapor and liquid line control valve remote indicators are inoperable.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 November 2021
Resolution: Received RINA report attesting to repairs of the control valve indicators. RINA imposed requirement to rectify inoperable temperature sensors during drydock. Attended the vessel on 14NOV2021 and confirmed repairs and satisfactory function of indicators.
15 - Safety Management Systems (ISM) › N/A - No Subsystem › Shipboard operations
Issued 8 November 2021
Resolved
Ships in which the carriage of flammable products is intended should be fitted with fixed dry chemical powder type extinguishing systems for the purpose of fighting fire on the deck in the cargo area and bow or stern cargo handling areas if applicable. The system and the dry chemical powder should be adequate for this purpose and satisfactory to the Administration. Several dry-chemical powder extinguishing systems' relief valve hand lifting devices have been wire tied shut, preventing manual activation of the relief valve.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 November 2021
Resolution: Received RINA report attesting to repairs to the dry chemical powder handles. Attended the vessel on 14NOV2021 and confirmed the removal of the zip-ties that prevented manual operation.
01 - Certificates & Documentation › 011 - Ships Certificates › Liquefied Gases in Bulk (ICoF/IGC Code)
Issued 8 November 2021
Resolved
Only the indirect system described in 7.2.4.2 should be used. The vessel’s nitrogen bottle bank, which is used for indirect cooling of propylene oxide, was removed. The vessel’s crew stated that propylene oxide would not be carried until all required equipment was reinstalled and the vessel had received flag state authorization for carriage of the cargo, but the vessel’s International Certificate of Fitness currently lists propylene oxide as a cargo the vessel is authorized to carry. Rectify prior to the carriage of propylene oxide.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 December 2021
Resolved 23 November 2021
Resolution: On 22NOV2021 Sector Honolulu received an updated ICOF and NLS certificate from RINA prohibiting the carriage of Propylene Oxide onboard the vessel.
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 8 November 2021
Resolved
Firefighting systems and appliances shall be kept in good working order and readily available for immediate use. The vessel's port side dry chemical monitor above the cargo motor room was inaccessible and not ready for immediate use. Furthermore, the port number 2 cargo tank dry chemical powder hose activation handle is not in a serviceable condition.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 14 November 2021
Resolution: Received RINA report attesting to repairs to the dry chemical powder activation handles and removal of barrels blocking the starboard monitor. Attended the vessel on 14NOV2021 and confirmed repairs.
14 - Pollution Prevention › 141 - MARPOL Annex I › Pumping, piping and discharge arrangements
Issued 8 November 2021
Resolved
Provisions should be made by the use of offsets, loops, bends, mechanical expansion joints such as bellows, slip joints and ball joints or similar suitable means to protect the piping, piping system components and cargo tanks from excessive stresses due to thermal movement and from movements of the tank and hull structure. Where mechanical expansion joints are used in piping they should be held to a minimum and, where located outside the cargo tanks, should be of the bellows type. The mechanical expansion joints on top of the number 1, 2, and 3 port and starboard cargo tanks were found to be missing hardware and unevenly tightened.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 December 2021
Resolved 23 November 2021
Resolution: On 22NOV2021 Sector Honolulu received documentation attesting to the installation of all mechanical expansion joints in accordance with manufacture specifications.
12 - Dangerous Goods › N/A - No Subsystem › Other (tankers)
Issued 8 November 2021
Resolved
After any survey of the ship under 1.5.2 has been completed, no change should be made in the structure, equipment, fittings, arrangements and material covered by the survey without the sanction of the Administration, except by direct replacement. The deck tank cargo vapor to mast riser valve's hydraulic actuator has been removed and the starboard number 2 cargo tank upper spray rails system's pneumatic activation line has been cut and is inoperable.
Condition: Improper Installation
Action required: 40 - Rectify deficiencies prior to next US port after sailing foreign
Resolved 20 January 2022
Resolution: PSC-B conducted 20JAN22. Deficiency rectified.
09 - Working and Living Conditions › 092 - Working Conditions › Cleanliness of engine room
Issued 8 November 2021
Resolved
Where pumps and compressors are driven by shafting passing through a bulkhead or deck, gastight seals with efficient lubrication or other means of ensuring the permanence of the gas tight seal should be fitted in way of the bulkhead or deck. The #1 compressor's gastight seal is worn and weeping hydraulic oil.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 December 2021
Resolved 14 November 2021
Resolution: Received RINA report attesting to repairs to the seal. Attended the vessel on 14NOV2021 and confirmed seal filled with fluid and no visible leaks.
07 - Fire Safety › N/A - No Subsystem › Fire doors/openings in fire-resisting divisions
Issued 8 November 2021
Resolved
In fire doors in main vertical zone bulkheads, galley boundaries and stairway enclosures other than power-operated watertight doors and those which are normally locked, hold back hooks not subject to central control station release are prohibited. A galley "A Class" door was found tied back in the open position with a rope.
Condition: Improper Installation
Action required: 10 - Deficiency Rectified
Resolved 8 November 2021
Resolution: The rope was removed from the galley "A Class" door.
09 - Working and Living Conditions › 092 - Working Conditions › Other (accident prevention)
Issued 8 November 2021
Resolved
Cylinders must always be stowed in a rack in an upright position, with the valve protection cap in place. Six cylinders were found tied with a rope directly on the deck in the aft cylinder storage area.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 8 December 2021
Resolved 14 November 2021
Resolution: Received RINA report attesting to proper stowage of bottles. Attended the vessel on 14NOV2021 and confirmed proper stowage of bottles.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 9 November 2020
Resolved
Each separate circuit shall be protected against short circuit and against overload, except as permitted in regulations 29 and 30 or where the Administration may exceptionally otherwise permit. Twenty-two circuit breakers, located on circuit breaker panel in integrated bridge control panels, taped in the closed (on) position, overriding the circuit protection provided by the breakers.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 25 November 2020
Resolved 13 November 2020
Resolution: Class, RINA, provided follow-up report which showed that tape was removed to their satisfaction. Def cleared.
09 - Working and Living Conditions › 092 - Working Conditions › Lighting (Working spaces)
Issued 17 October 2019
Resolved
The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulations to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons onboard. The lighting for the trunk leading to the emergency fire pump space and the lighting in the emergency fire pump space is not operational.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 31 October 2019
Resolved 8 November 2019
Resolution: Recieved Class report attesting to repair
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 7 May 2019
Resolved
6199 – The condition of the ship and its equipment shall be maintained to conform with the provisions of the present regulation to ensure that the ship in all respects will remain fit to proceed to sea without danger to the ship or persons on board. PSCO observed that the vessel’s port side cargo heat exchanger was leaking product. Vessel restricted from using port side heat exchanger until source of discharge is corrected to the satisfaction of class. 74 SOLAS (14) I/11
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 4 June 2019
Resolution: Class attended vessel, identified and corrected 02 leaking sea water pipes in port side cargo heater.