Records from 1981 to 2003. Most recent: inspection, 9 February 2003.
Inspection history · 61
9 February 2003
Administrative Inspection
Administrative · Activities Europe · Activity 1617831
1 September 2002
Annual Inspection
Physical examination · Activities Europe · Activity 1656644
9 February 2002
Type not recorded
No type recorded · Activities Europe · Activity 1775196
28 December 2001
COI Inspection
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 1475222
17 May 2001
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1064443
4 August 2000
COI Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1384533
22 March 2000
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1049193
14 January 2000
Deficiency Check
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1046552
18 October 1999
Re-Inspection
Physical examination · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1424831
30 September 1998
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 801378
20 August 1998
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 795779
17 August 1998
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1381316
14 August 1998
Deficiency Check · Examination of Repairs
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1440026
8 April 1998
Deficiency Check · Hull Examination
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1457569
10 March 1998
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1122121
4 February 1998
Damage Survey
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1427460
1 February 1998
COI Inspection
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1400714
26 January 1998
Administrative
Administrative · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1117096
16 September 1997
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 230918
21 May 1997
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1103204
27 February 1997
Re-Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1466997
12 August 1996
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 674221
8 August 1996
Examination of Repairs
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1088668
24 July 1996
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 109797
2 June 1996
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 177782
25 January 1996
COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1438401
3 October 1995
Type not recorded
No type recorded · MSO Mobile · USCG Heartland District (CGD-H) · Activity 215721
27 September 1995
Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 1187260
11 September 1995
COI Inspection · Hull Examination
Physical examination · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 884111
13 April 1995
Re-Inspection · Examination of Repairs
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1398231
11 August 1994
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 147399
22 March 1994
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1166122
10 February 1994
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 674214
7 February 1994
Type not recorded
No type recorded · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 57341
1 February 1994
COI Inspection
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1467853
3 March 1993
Re-Inspection · Deficiency Check · Hull Examination
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 837420
14 January 1993
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 652692
12 January 1993
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 29870
6 March 1992
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1264038
6 February 1992
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 955201
20 February 1991
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1230500
8 November 1990
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 956591
8 November 1990
Hull Examination
Physical examination · MSO MORGAN CITY · USCG Heartland District (CGD-H) · Activity 1296059
1 May 1990
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1214227
5 April 1990
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1217396
2 February 1990
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1232895
25 April 1989
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1034701
2 March 1989
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1198168
29 June 1988
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 894100
19 May 1988
Deficiency Check
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1042310
5 May 1988
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1037256
29 February 1988
Administrative
Administrative · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1331767
1 February 1988
COI Inspection · Hull Examination
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 1015776
12 December 1986
Administrative
Administrative · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1019189
22 January 1986
Deficiency Check
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 984968
12 December 1985
COI Inspection · Credit Drydock
Physical examination · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 997631
7 March 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1287373
6 February 1985
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1285612
20 August 1984
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1282041
13 December 1983
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 971702
10 June 1981
Type not recorded
No type recorded · MIO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 963770
Lifesaving › Rescue Boat › Carriage Requirement
Issued 1 September 2002
Resolved
Provide a Rescue Boat that complies with MIO EUROPE Marine Safety Information Bulletin 02-02.
Condition: Unknown
Action required: 705 - Other - as specified
Due 4 October 2002
Resolved 9 February 2003
Resolution: Vessel Reflagged
Operations/Management › Drug and Alcohol Testing › Testing, Random
Issued 1 September 2002
Resolved
Provide proof of compliance with required Drug Testing Program in accordance with 46CFR Part 16.
Due 4 October 2002
Resolved 9 February 2003
Resolution: Vessel Reflagged
Communications › Radio Communications
Issued 28 December 2001
Resolved
Provide third lifeboat handheld radio. LEGACY COMPONENT DESC: Radiotelephone Transveiver (2-4 MHz)
Due 28 December 2001
Resolved 28 December 2001
Navigation › Collision/Grounding Avoidance › Navigation Lights
Issued 28 December 2001
Resolved
Replace extinguished nav lights.
Due 28 January 2002
Resolved 28 December 2001
Engineering › Diesel Engine (propulsion-reduction gear)
Issued 28 December 2001
Resolved
Provide operating propulsion shaft tachs.
Due 28 January 2002
Resolved 28 December 2001
Accommodation/Occupational Safety › Occupational Safety
Issued 28 December 2001
Resolved
Remove gear from emergency escape in engine room.
Due 28 January 2002
Resolved 28 December 2001
Lifesaving
Issued 4 August 2000
Resolved
CHOOSE AND PROVE DRILL FOR MAN OVERBOARD TO THE SATISFACTION OF THE MARINE INSPECTOR. VESSEL HAS RESCUE BOAT BUT NO APPROVED LAUNCHING APPLIANCE. VESSEL HAS JASON'S CRADLE BUT UNABLE TO DEMONSTRATE IN PORT AREA IN BRAZIL.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Engineering
Issued 4 August 2000
Resolved
PROVIDE VALVE HANDLE FOR DECK FUEL OIL MANIFOLD.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Electrical
Issued 4 August 2000
Resolved
REMOVE DEAD END WIRING FROM DECK GENERATOR AND BEHIND #1 AIR COMPRESSOR.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Unknown
Issued 4 August 2000
Resolved
PROVE PROPER OPERATION OF AIR RECEIVER RELIEF VALVES AT OR BELOW 200 PSI MAWP.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Lifesaving
Issued 4 August 2000
Resolved
PROVE PROPER OPERATION OF ENGINE ROOM GENERAL ALARM BELLS.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Construction/Loadline
Issued 4 August 2000
Resolved
MAKE PERMANENT REPAIRS TO BOTTOM LONGS THAT ARE HOLED IN STEERING COMPARTMENT.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Deck/Cargo
Issued 4 August 2000
Resolved
PROVE CARGO P-TANK RELIEF VALVES PRIOR TO OPERATION OF P-TANKS.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Accommodation/Occupational Safety
Issued 4 August 2000
Resolved
PROVE PROPER OPERATION OF TYPE II MSD SEWAGE SYSTEM TO MARINE INSPECTOR.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Construction/Loadline
Issued 4 August 2000
Resolved
MAKE PERMANENT REPAIRS TO STARBOARD EXHAUST TRUNK AT MAIN DECK ACCESS - DOUBLER PLATE ALLOWED AS TEMP REPAIR.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Navigation
Issued 4 August 2000
Resolved
PROVE PROPER OPERATION OF STARBOARD RADAR
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Construction/Loadline
Issued 4 August 2000
Resolved
REMOVE EXCESS WATER, FUEL, OIL AND SEWAGE FROM MACHINERY SPACE BILGES.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Construction/Loadline
Issued 4 August 2000
Resolved
PROVIDE RUBBER GASKETS ON ALL WATER TIGHT DOORS, VICE OPEN CELL SPONGE RUBBER.
Condition: Unknown
Due 4 August 2000
Resolved 4 August 2000
Navigation
Issued 22 March 2000
Resolved
REPACK AND PROVE RUDDER PACKING ON BOTH RUDDERS.
Condition: Unknown
Due 22 March 2000
Resolved 22 March 2000
Engineering
Issued 22 March 2000
Resolved
REPACK AND PROVE STARBOARD SHAFT PACKING.
Condition: Unknown
Due 22 March 2000
Resolved 22 March 2000
Engineering
Issued 14 January 2000
Resolved
PROVE OPERATION OF REMOTE REACH RODS FOR F/O SERVICE LINES FROM BOTH DAY TANKS TO ENGINES IN ENGINE ROOM.
Condition: Unknown
Due 14 January 2000
Resolved 14 January 2000
Fire Fighting
Issued 14 January 2000
Resolved
REPLACE SEAL ON FIRE MONITOR PUMP.
Condition: Unknown
Due 14 January 2000
Resolved 25 February 2000
Documentation
Issued 14 January 2000
Resolved
PROVIDE PROOF OF SATISFACTORY ANNUAL LOADLINE SURVEY.
Condition: Unknown
Due 14 February 2000
Resolved 25 February 2000
Fire Fighting
Issued 14 January 2000
Resolved
ADD ADDITIONAL FIRE EXTINGUISHER IN BRIDGE AS REQUIRED BY 46 CFR 95.50- 10(A) OR 132.220.
Condition: Unknown
Due 14 January 2000
Resolved 25 February 2000
Fire Fighting
Issued 14 January 2000
Resolved
REPLACE SEAL ON FIRE PUMP.
Condition: Unknown
Due 14 January 2000
Resolved 14 January 2000
Fire Fighting
Issued 14 January 2000
Resolved
REPLACE EXPENDED CO2 FOR PAINT LOCKER.
Condition: Unknown
Due 14 January 2000
Resolved 14 January 2000
Lifesaving
Issued 18 October 1999
Resolved
PREFORM & PROVE 5 YR INFLATION TEST ON RAFT LOT 30 SERIAL 11.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Accommodation/Occupational Safety
Issued 18 October 1999
Resolved
PROVIDE NEW FILTERS FOR A/C RETURN.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Documentation
Issued 18 October 1999
Resolved
PROVIDE APPROVED FIRE AND SAFETY PLAN.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Fire Fighting
Issued 18 October 1999
Resolved
PROVIDE ABS REPORT OF REPAIRS TO FIREMAIN IN FOREPEAK OR MAKE FOREPEAK GAS FREE FOR CG INSPECTION OF REPAIRS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Construction/Loadline
Issued 18 October 1999
Resolved
PROVE PROPER OPERATION OF VESSELS OILY WATER SEPERATOR.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
DEMONSTRATE PROPER MAN OVERBOARD DRILL ON NEXT VISIT.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Fire Fighting
Issued 18 October 1999
Resolved
DEMONSTRATE PROPER FIRE DRILL ON NEXT VISIT.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Navigation
Issued 18 October 1999
Resolved
PROVIDE THE FOLLOWING PUBS: LIGHT LIST, CURRENT TABLE AND COAST PILOT.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Documentation
Issued 18 October 1999
Resolved
PROPERLY POST STABILITY LETTER.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Deck/Cargo
Issued 18 October 1999
Resolved
PROVIDE AND PROVE ASME APPROVED POP OFF VALVES FOR BULK TANKS AND DRY BULK COMPRESSOR.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Documentation
Issued 18 October 1999
Resolved
PROPERLY POST EMERGENCY INSTRUCTIONS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Documentation
Issued 18 October 1999
Resolved
POST EMERGENCY BROADCAST PLACARD.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Navigation
Issued 18 October 1999
Resolved
PROVIDE UPDATED COMPASS DEVIATION CARD.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Navigation
Issued 18 October 1999
Resolved
PROVIDE DAYLIGHT SIGNAL LAMP.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVIDE AND PROPERLY INSTALL REQUIRED EMBARKATION LADDERS AT DESIGNATED EMBARKATION STATIONS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Deck/Cargo
Issued 18 October 1999
Resolved
PROVE PROPER OPERATION OF STBD ANCHOR WINDLASS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVIDE DAVIT LAUNCH SYSTEM FOR RESCUE BOAT IAW CG DISTRICT EIGHT LETTER DATED 12 NOV 98.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
REMOVE STENCILLING FROM LIFERAFT CONTAINERS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Accommodation/Occupational Safety
Issued 18 October 1999
Resolved
MAKE PERMANENT REPAIRS TO USCG APPROVED TYPE II MSD AND PROVE OPERATION TO CG MARINE INSPECTOR. SYSTEM IS CREATING A SEVERE HEALTH HAZARD FOR CREW. RESTORE SYSTEM TO A CG APPROVED CONDITION.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 18 October 1999
Resolved
REPAIR AND PROVE SHAFT TACHOMETERS ON BRIDGE.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 18 October 1999
Resolved
REPAIR PORT SHAFT PACKING TO PREVENT EXCESSIVE UNCONTROLLABLE LEAKING INTO ENGINE ROOM BILGE.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Fire Fighting
Issued 18 October 1999
Resolved
PROVE VESSELS FIXED CO2 SYSTEM IN THE PRESENCE OF A CG MARINE INSPECTOR. VESSEL IS IN A NO-SAIL STATUS UNTIL THIS ITEM IS CLEARED.
Condition: Unknown
Due 18 November 1999
Resolved 4 November 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVIDE VESSEL WITH CG APPROVED LIFERAFTS. VESSEL IS IN A NO SAIL STATUS UNTIL THIS ITEM IS CLEARED.
Condition: Unknown
Due 18 October 1999
Resolved 4 November 1999
Unknown
Issued 18 October 1999
Resolved
MAKE VESSEL AVAILABLE FOR REINSPECTION.
Condition: Unknown
Due 18 October 1999
Resolved 4 November 1999
Engineering
Issued 18 October 1999
Resolved
PROVIDE "T" HANDLES TO SECURE FUEL OIL REACH RODS ON DECK.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Documentation
Issued 18 October 1999
Resolved
PROPERLY POST COI.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVE PROPER OPERATION OF AIR RECEIVER RELIEF VALVES.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVIDE LIGHT BULBS AND EQUIPMENT LABELS FOR ENGINE ROOM AND PILOTHOUSE ENGINE ALARM PANELS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Electrical
Issued 18 October 1999
Resolved
PROPERLY LABEL ALL ELECTRICAL PANELS WITH BREAKER NUMBER, EQUIPMENT AND AMPBREAKER INSTALLED.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Electrical
Issued 18 October 1999
Resolved
PROVIDE BREAKER LOCKOUT DEVICE TO PREVENT ENERGIZING SECURED GENERATOR BREAKER WITH ONLINE ENERGIZED GENERATOR BREAKER.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Accommodation/Occupational Safety
Issued 18 October 1999
Resolved
REMOVE ALL SPARE PARTS AND SUPPLIES FROM CREWS QUARTERS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVIDE 100 PSI RELIEF VALVE, OR OPEN FOR VISUAL EXAMINATION OR HYDROSTATICTEST, ON WATER HEATER.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 18 October 1999
Resolved
PROVIDE FLYWHEEL GUARD OUTBOARD ON BOTH MAINS AND STBD REDUCTION GEAR.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 18 October 1999
Resolved
PROVE PORT MAIN ENGINE TACHOMETER OPERATES ABOVE 800 RPM - OVERSPEED SET AT900+ RPM.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 18 October 1999
Resolved
PROVIDE WRITTEN COPY OF AUTOMATION TESTS CONDUCTED BY THIRD PARTY.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Construction/Loadline
Issued 18 October 1999
Resolved
PROPERLY ADJUST ALL WATERTIGHT DOORS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 18 October 1999
Resolved
REPAIR OIL LEAKS ON #1 STBD GENERATOR.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Fire Fighting
Issued 18 October 1999
Resolved
PROVE PROPER OPERATION OF VENTILATION SHUT DOWN ON CO2 FIXED SYSTEM.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 18 October 1999
Resolved
PROVE OVERSPEED, LOW LUBE OIL AND HIGH JACKET WATER ALARM ON EMERGENCY GENERATOR LOCATED ON DECK.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVIDE COPY OF MSC APPROVAL FOR CRANE INSTALLATION AS REQUIRED BY ABS APPROVAL.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVE PROPER STOWAGE OF ALL LIFESAVING AND FIREFIGHTING GEAR IAW FIRE AND SAFETY PLAN.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROVIDE ALL REQUIRED STENCILLING THROUGHOUT VESSEL.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Fire Fighting
Issued 18 October 1999
Resolved
REMOVE ALL BRAZILLIAN FIRE EXTINGUISHERS AND PROVIDE U.L./CG APPROVED WITH CURRENT SERVICING. LOCATIONS AND TYPE TO BE IAW FIRE AND SAFETY PLAN.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Deck/Cargo
Issued 18 October 1999
Resolved
PROVE ANNUAL HYDROSTATIC TESTS OF ALL LIQUID MUD AND FUEL HOSES ONBOARD VESSEL. NO CARGO TRANSFERS UNTIL THIS ITEM IS CLEARED.
Condition: Unknown
Due 21 October 1999
Resolved 17 November 1999
Fire Fighting
Issued 18 October 1999
Resolved
PROVIDE COPIES OF SERVICING REPORTS FOR FIXED CO2 SYSTEM.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Navigation
Issued 18 October 1999
Resolved
PROVE REPAIRS TO RADARS.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Lifesaving
Issued 18 October 1999
Resolved
PROPERLY STENCIL RESCUE BOAT.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Electrical
Issued 18 October 1999
Resolved
REPLACE CABLE AND INSTALL PROPER JUNCTION BOX AT PORT TUGGER.
Condition: Unknown
Due 18 October 1999
Resolved 18 October 1999
Engineering
Issued 17 August 1998
Resolved
REPAIR/REPLACE PORT MDE FLEX HOSE TO L/O PUMP.
Condition: Unknown
Due 17 September 1998
Resolved 20 August 1998
Construction/Loadline
Issued 17 August 1998
Resolved
REPAIR PORT LIGHT COVERS IN OILERS BERTH, AND 01 DECK FWD HEAD.
Condition: Unknown
Due 17 September 1998
Resolved 20 August 1998
Fire Fighting
Issued 17 August 1998
Resolved
PROVIDE CO2 MANUAL OPERATION INSTRUCTIONS AT REMOTE STATIONS
Condition: Unknown
Due 17 September 1998
Resolved 20 August 1998
Documentation
Issued 17 August 1998
Resolved
PROVIDE VALID DOCUMENTATION CERTIFICATE.
Condition: Unknown
Due 17 September 1998
Resolved 20 August 1998
Unknown
Issued 17 August 1998
Resolved
RE-STENCIL BILGE MANIFOLD, EMERGENCY EXIT, AND ALL MARKINGS AFTER PAINT JOB.
Condition: Unknown
Due 17 September 1998
Resolved 20 August 1998
Engineering
Issued 17 August 1998
Resolved
PROVIDE AUTOMATION TEST PROCEDURES.
Condition: Unknown
Due 17 September 1998
Resolved 20 August 1998
Engineering
Issued 17 August 1998
Resolved
REPAIR/REPLACE PORT MDE F/O PRESSURE GUAGE.
Condition: Unknown
Due 17 September 1998
Resolved 20 August 1998
Deck/Cargo
Issued 14 August 1998
Resolved
REPAIR AS REQUIRED AND DEMONSTRATE PROPER OPERATION OF DECK WINCH ASSEMBLY NO LATER THAN 31AUG98 AND PRIOR TO USE. ORGIN ISSUED GALMS MI98003512. EXTENSION GRANTED UNTIL 31AUG98.
Condition: Unknown
Due 14 August 1998
Resolved 14 August 1998
Engineering
Issued 14 August 1998
Resolved
RENEW OR REPAIR AS REQUIRED PORT AND STBD MAIN DIESEL STARBOARD MAIN DIESELENGINE VULCAN COUPLINGS. ORIGN ISSUE GALMS MI98003512. EXTENSION GRANTED PATMS UNTIL 31AUG98.
Condition: Unknown
Due 31 August 1998
Resolved 19 August 1998
Engineering
Issued 14 August 1998
Resolved
REPAIR AS REQUIRED EXCESSIVE AND NUMEROUS OIL LEAKS IN WAY OF PORT AND STBDMAIN DIESEL ENGINES AND REDUCTION GEARS. ORGIN ISSUE GALMS MI98003512, EXTENSION GRANTED UNTIL 31AUG98.
Condition: Unknown
Due 14 August 1998
Resolved 14 August 1998
Engineering
Issued 14 August 1998
Resolved
REPAIR WASTED STACK TRUNK EXHAUST PIPING PENETRATIONS ON PORT AND STARBOARDSTACKS. ORIGIN ISSUE GALMS MI98003512, EXTENSION GRANTED UNTIL 31AUG98.
Condition: Unknown
Due 31 August 1998
Resolved 19 August 1998
Engineering
Issued 4 February 1998
Resolved
Renew output and quill shaft oil seals on port and starboard reduction gears prior to getting underway.
Condition: Unknown
Due 5 February 1998
Resolved 9 February 1998
Engineering
Issued 4 February 1998
Resolved
Renew or repair as required starboard clutch assembly.
Condition: Unknown
Due 4 February 1998
Resolved 4 February 1998
Construction/Loadline
Issued 1 February 1998
Resolved
Repair as required wasted stack trunk exhaust piping penetrations on port and starboard stacks.
Condition: Unknown
Due 1 February 1998
Resolved 1 February 1998
Engineering
Issued 1 February 1998
Resolved
Renew or repair as required port and starboard Main Diesel Engine Vulcan coulings.
Condition: Unknown
Due 1 February 1998
Resolved 1 February 1998
Lifesaving
Issued 1 February 1998
Resolved
Repair or renew flammable stores stowage locker.
Condition: Unknown
Due 1 February 1998
Resolved 1 February 1998
Engineering
Issued 1 February 1998
Resolved
Repair as required excessive and numerous lube oil leaks in way of port andstarboard Main Diesel Engines and Reduction Gears.
Condition: Unknown
Due 1 February 1998
Resolved 1 February 1998
Deck/Cargo
Issued 1 February 1998
Resolved
Repair as required and demonstrate proper operation of deck winch assembly no later than 31MAR98 and prior to use.
Condition: Unknown
Due 1 February 1998
Resolved 1 February 1998
Navigation
Issued 20 February 1991
Resolved
REPAIR NO. 1 STBD STEERING SYSTEM TO PREVENT THE RUDDER FROM TURNING ON ITSOWN._x001C_ _x001C_ _x001C_
Condition: Unknown
Due 20 February 1991
Resolved 20 February 1991
Electrical
Issued 8 November 1990
Resolved
Prove proper operation of both port and starboard generator revese power relays.
Condition: Unknown
Due 6 March 1992
Resolved 16 March 1992
Construction/Loadline
Issued 8 November 1990
Resolved
Adjust dogs for watertight door leading into steering room from engine room.
Condition: Unknown
Due 6 March 1992
Resolved 16 March 1992
Accommodation/Occupational Safety
Issued 8 November 1990
Resolved
Conduct internal exam on all dry bulk tanks at next drydocking but no laterthan 28 FEB 1993.
Condition: Unknown
Due 8 November 1990
Resolved 8 November 1990
Fire Fighting
Issued 8 November 1990
Resolved
Provide for examination a corrected fire control plan showing the correct number of and location of; fire extingushers, fire stations and emergency lights
Condition: Unknown
Due 6 March 1992
Resolved 16 March 1992
Engineering
Issued 8 November 1990
Resolved
Prove proper operation of starboard main engine overspeed.
Condition: Unknown
Due 6 March 1992
Resolved 16 March 1992
Deck/Cargo
Issued 2 February 1990
Resolved
TUGGER WINCH ON DECK MUST HAVE A PROTECTIVE GUARD INSTALLED
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Engineering
Issued 2 February 1990
Resolved
TEST THE HIGH JACKET WATER SENSORS IN BOTH MAIN ENGINES.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Construction/Loadline
Issued 2 February 1990
Resolved
REPAINT LOADLINE MARKS ON STARBOARD SIDE.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Documentation
Issued 2 February 1990
Resolved
RE-EDIT OIL TRANSFER PROCEDURES TO ADDRESS FIXED VICE PORTABL CONTAINMENT.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Engineering
Issued 2 February 1990
Resolved
REPLACE TEMPERATURE GAUGE IN STARBOARD REDUCTION GEAR LUBE OIL COOLANT LINE.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Documentation
Issued 2 February 1990
Resolved
SUBMIT AUTOMATION PANEL TEST PROCEDURES FOR COAST GUARD APPROVAL.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Electrical
Issued 2 February 1990
Resolved
INSTALL DIRECTORY CARD FOR CIRCUIT BREAKER PANEL ON PORT SIDE OF SWITCHBOARD.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Electrical
Issued 2 February 1990
Resolved
REPAIR AND TEST #1 SHIP SERVICE GENERATOR OVERSPEED TRIP.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Electrical
Issued 2 February 1990
Resolved
REPAIR AND TEST REVERSE POWER RELAY ON #2 SHIP SERVICE GENERATOR.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Engineering
Issued 2 February 1990
Resolved
CALIBRATE PORT MAIN ENGINE TACHOMETER ON THE BRIDGE TO THE TACHOMETER IN THE ENGINEROOM PANEL FOR THE PORT MAIN ENGINE.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Engineering
Issued 2 February 1990
Resolved
REPAIR STARBOARD SHAFT TACHOMETER IN THE WHEELHOUSE AND ENGINEROOM.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Electrical
Issued 2 February 1990
Resolved
LINE THE BATTERY BOXES IN ENGINEROOM WITH NON-CORROSIVE MATERIAL.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Construction/Loadline
Issued 2 February 1990
Resolved
MAKE PERMANENT REPAIRS TO BALLAST PIPING IN ENGINEROOM IN VICINITY OF SEA CHEST AND OVERHEAD OF THE BALLAST PUMP.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Navigation
Issued 2 February 1990
Resolved
REPAIR SINGLE SIDE BAND RADIO RECEIVER.
Condition: Unknown
Due 2 February 1990
Resolved 2 February 1990
Documentation
Issued 2 March 1989
Resolved
PROVIDE AN APPROVED FIRE CONTROL PLAN FOR THE VESSEL.
Condition: Unknown
Due 2 March 1989
Resolved 2 March 1989
Electrical
Issued 2 March 1989
Resolved
RE-LOCATE THE SHUT-OFF PRESSURE SWITCH ON THE POTABLE WATER TANK IN ORDER TO REMOVE THE SPLICE.
Condition: Unknown
Due 2 March 1989
Resolved 2 March 1989
Engineering
Issued 2 March 1989
Resolved
MAKE OPERABLE THE STARBOARD GENERATOR'S LOW LUBE OIL ALARM.
Condition: Unknown
Due 2 March 1989
Resolved 2 March 1989
Engineering
Issued 2 March 1989
Resolved
MAKE OPERABLE THE PORT MAIN DIESEL'S TACHOMETER.
Condition: Unknown
Due 2 March 1989
Resolved 2 March 1989
Engineering
Issued 1 February 1988
Resolved
MAKE THE REMOTE REACH ROD FOR #2 PORT FUEL OIL TANK ACCESSIBLE AFTER COMPLETE INSTALLATION OF THE AFT DECK WINCH CONTROLS.
Condition: Unknown
Due 1 February 1988
Resolved 1 February 1988
Documentation
Issued 1 February 1988
Resolved
PROVIDE A CURRENT COPY OF THE VESSELS CERTIFICATE OF DOCUMENTATION.
Condition: Unknown
Due 1 February 1988
Resolved 1 February 1988
Deck/Cargo
Issued 1 February 1988
Resolved
TEST THE RELIEF VALVES AND COMPLETE OPERATION OF THE PRESSURIZED DRY BULK SYSTEM.
Condition: Unknown
Due 1 February 1988
Resolved 1 February 1988
Navigation
Issued 1 February 1988
Resolved
MAKE THE SHAFT TACHS ON THE BRIDGE AND AT THE ENGINE ROOM CONTROL STATION OPERABLE.
Condition: Unknown
Due 1 February 1988
Resolved 1 February 1988
Deck/Cargo
Issued 12 December 1985
Resolved
REPLACE MISSING STBD ANCHOR. COMPLIANCE DATE IS 12JAN86
Condition: Unknown
Due 12 December 1985
Resolved 12 December 1985
Electrical
Issued 6 February 1985
Resolved
MAKE OPERABLE/TEST BOTH SHIPS SERVICE GENERATOR REVERSE POWER RELAYS.
Condition: Unknown
Due 6 February 1985
Resolved 6 February 1985
Unknown
Issued 6 February 1985
Resolved
THE FOLLOWING DEFICIENCY PERTAIN TO THE VESSEL, MARSEA SEVEN, DN636293.
Condition: Unknown
Due 6 February 1985
Resolved 6 February 1985