Records from 2004 to 2026. Most recent: inspection, 6 January 2026.
Documentation record
Registered dimensions (L × B × D)116.1 ft × 38.0 ft × 22.0 ft
Registered tonnagegross 288 / net 203
ITC dimensions (L × B × D)116.1 ft × 38.0 ft × 22.0 ft
ITC tonnagegross 760 / net 228
BuilderMANITOWOC MARINE GROUP LLC · STURGEON BAY, WI, UNITED STATES · built 2004
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeShip
Hull configurationMonohull
Hailing portPHILADELPHIA, PA
Trade endorsementsCoastwise, unrestricted, Registry
DocumentationCase Pending · issued 18 November 2025 · expires 31 December 2026
Service, as the file records itTowing Vessel
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it288 - Regulatory (Subpart C or D), Gross Ton
760 - Convention (Subpart B), Gross Ton
203 - Regulatory (Subpart C or D), Net Ton
228 - Convention (Subpart B), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 42
6 January 2026
Administrative Inspection
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8290926
4 November 2025
COI Inspection · MTSA Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 8261346
27 September 2025
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8242556
23 May 2025
MTSA/ISPS Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8126477
12 December 2024
Administrative Inspection
Administrative · Sector Mobile · USCG Heartland District (CGD-H) · Activity 8047255
27 August 2024
TPO Audit
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7990546
23 July 2024
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7965324
17 August 2023
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7770214
19 July 2023
MTSA/ISPS Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 7750714
11 August 2022
TPO Audit
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7531428
1 October 2021
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7324455
24 January 2021
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7129664
30 November 2020
Administrative Inspection · Initial Certification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7103720
29 July 2020
Administrative Inspection · MTSA/ISPS Verification
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 7019030
5 April 2019
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6656421
22 March 2018
MTSA/ISPS Verification · Industry Initiated Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6377264
28 March 2017
In-Service Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6112950
27 March 2017
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6133816
13 February 2015
Administration
Administrative · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 5068669
13 February 2015
Industry Initiated Exam
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 5068938
3 October 2014
Damage Survey
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 5006208
29 January 2013
MTSA/ISPS Verification
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4524196
20 September 2012
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 4445967
18 June 2012
Type not recorded
No type recorded · Sector Mobile · USCG Heartland District (CGD-H) · Activity 4350955
27 April 2012
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4299350
13 December 2011
MARPOL Annex VI Survey · MTSA/ISPS Verification · MARPOL Annex I Examination
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4203133
13 December 2011
Deficiency Check · Industry Initiated Exam · DAPI Audit
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4207613
26 November 2011
Type not recorded
No type recorded · Sector Jacksonville · USCG Southeast District (CGD-SE) · Activity 4226760
18 March 2011
Marine Casualty Follow Up · Administration
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3968623
10 September 2010
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3846666
7 January 2010
Administrative Inspection · MTSA/ISPS Verification
Physical examination · Sector St Petersburg · USCG Southeast District (CGD-SE) · Activity 3660850
27 February 2009
MARPOL Annex I Examination · Uninspected Other · MTSA/ISPS Verification
Physical examination · Sector Miami · USCG Southeast District (CGD-SE) · Activity 3426928
10 October 2008
Type not recorded
No type recorded · Sector Miami · USCG Southeast District (CGD-SE) · Activity 3342332
6 March 2008
MTSA/ISPS Verification · Administration
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3151848
12 December 2007
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3114160
15 February 2007
MTSA/ISPS Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2872736
12 October 2006
Security Plan Amendment Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2798935
25 January 2006
MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2571640
2 November 2004
Security Plan Amendment Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2233346
26 October 2004
Security Plan Amendment Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2228594
24 September 2004
Security Plan Review - VSP
Administrative · Marine Safety Center (MSC) · Activity 2204110
15 September 2004
MARPOL Annex I Examination · Construction Oversight · MTSA/ISPS Verification · Initial Certification
Physical examination · Marine Safety Unit Sturgeon Bay · USCG Great Lakes District (CGD-GL) · Activity 2196762
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Auxiliary engine
Issued 27 September 2025
Resolved
Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons onboard under normal and emergency conditions. The vessel experienced a temporary loss of power on the number 1 generator and the failure resulted in a loss of power to the vessel for approximately 30 seconds before the number 3 standby generator came online. The root cause of the failure remains unidentified.
46 CFR 143.205(a)
60ac
Condition: Damaged By Earlier Event
Action required: 60 - Rectify deficiencies prior to movement
Resolved 28 September 2025
Resolution: The ABS report confirms that the generator issue has been resolved, and no further faults were identified during testing. Based on this information, the deficiency related to the No. 1 generator incident is considered cleared.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 23 July 2024
Resolved
Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons onboard under normal and emergency conditions. Vessel reported total loss of steering. Provide applicable technician report(s) for necessary repairs and TPO report attesting to proper repair and operation of steering systems to the satisfaction of Coast Guard prior to vessel movement.
46 CFR 143.205(a)
Action required: 60 - Rectify deficiencies prior to movement
Resolved 23 July 2024
Resolution: provided technician report and TPO report attesting to satisfactory operation of steering system
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 17 August 2023
Resolved
Propulsion machinery, including main engines, reduction gears, shafting, bearings, and electrical equipment and systems, must be maintained to ensure proper operation. Vessel suffered loss of propulsion on port main engine. Vessel is allowed to transit from Boothville, LA to St. Charles, LA under own power utilizing shaddow vessel for transit. Vessel to conduct repairs prior to departing St. Charles. TPO report required to be submitted attesting to full operations and safe navigation of vessel.
Action required: 17 - Rectify deficiencies prior to departure
Due 17 August 2023
Resolved 18 August 2023
Resolution: Received ABS report attesting to repairs and full operation of vessel.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 5 April 2019
Resolved
Propulsion machinery, including main engines, reduction gears, shafting, bearing, and electrical equipment and systems, must: be maintained to ensure proper operation. Vessel reported that starboard steering pump is inoperable. Vessel is required to repair the starboard steering pump and conduct a steering test satisfactory to the inspector.
Condition: Invalid
Action required: 17 - Rectify deficiencies prior to departure
Resolved 6 April 2019
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 13 December 2011
Resolved
The OWS is inoperable due to burnt motor.
Action required: 17 - Rectify deficiencies prior to departure
Due 13 December 2011
Resolved 14 December 2011
Resolution: Motor repaired and OWS operation witnessed by ABS.
Pollution Prevention/Response › Prevention Equipment › Oily Water Separator (15 ppm)
Issued 13 December 2011
Resolved
OWS is fitted with a bypass valve in the overboard discharge line.
Action required: 17 - Rectify deficiencies prior to departure
Due 13 December 2011
Resolved 15 December 2011
Engineering › Shafting/Propeller Arrangements › Bearing
Issued 13 December 2011
Resolved
Port and Stbd shaft seals have excessive leaks.
Action required: 17 - Rectify deficiencies prior to departure
Due 13 December 2011
Resolved 15 December 2011