Records from 2005 to 2025. Most recent: inspection, 28 March 2025.
Documentation record
Registered dimensions (L × B × D)297.5 ft × 54.0 ft × 12.0 ft
Registered tonnagegross 1,619 / net 1,619
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderTRINITY MARINE PRODUCTS INC · MADISONVILLE, LA, UNITED STATES · built 2005
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portPORT ARANSAS, TX
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 19 March 2026 · expires 31 March 2027
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1619 - Simplified, Gross Ton
1619 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 36
28 March 2025
Internal Structural Exam · COI Inspection · Administrative Inspection · Drydock Exam · Deficiency Check
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 8101310
16 August 2023
Administrative Inspection · Periodic Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7769698
19 May 2023
Administrative Inspection
Administrative · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7691970
21 March 2023
Administrative Inspection · Internal Structural Exam · Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7654227
15 December 2022
Administrative Inspection
Administrative · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7609757
21 October 2022
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7583002
6 June 2022
Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7469988
6 December 2021
Administrative Inspection
Administrative · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 7363822
6 December 2021
Type not recorded
No type recorded · Marine Safety Unit Victoria · USCG Heartland District (CGD-H) · Activity 7368135
12 November 2021
Administrative Inspection
Administrative · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7349703
10 February 2021
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7138620
25 June 2020
COI Inspection · Examination of Repairs · Cargo Tank Internal · MTSA Verification · Hull Examination · Deficiency Check · Internal Structural Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6961621
19 February 2020
In-Service Inspection
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 6912459
6 September 2017
Damage Survey · Administrative Inspection
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 6260865
4 May 2016
Administrative Inspection · Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5869114
30 April 2015
MTSA Verification · COI Inspection · Cargo Tank Internal · Internal Structural Exam · Examination of Repairs · Drydock Exam
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 5114235
25 August 2014
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4965314
21 May 2014
Annual Inspection
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4864674
17 May 2012
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4313793
29 July 2011
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4094644
6 October 2010
Damage Survey
Physical examination · Marine Safety Unit Houma · USCG Heartland District (CGD-H) · Activity 3864538
5 October 2010
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 4211119
21 May 2010
Cargo Tank Internal · Drydock Exam · COI Inspection · MTSA Verification · Internal Structural Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3735668
26 April 2010
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3724801
12 June 2009
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3501967
17 December 2008
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3382522
14 July 2008
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3264501
24 June 2008
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3267964
19 July 2007
MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2999445
12 December 2006
Damage Survey · Deficiency Check
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2838949
11 December 2006
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 2844767
13 June 2006
Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2678101
15 June 2005
Deficiency Check
Physical examination · MIDET HARVEY CANAL DETAIL · USCG Heartland District (CGD-H) · Activity 2391516
31 May 2005
Deficiency Check
Physical examination · MIDET EAST BANK DETAIL · USCG Heartland District (CGD-H) · Activity 2373767
26 April 2005
Initial Certification · Hull Examination · MTSA Verification · Internal Structural Exam · Cargo Tank Internal · Initial Construction-Excluding Oversight
Physical examination · MIDET EAST BANK DETAIL · USCG Heartland District (CGD-H) · Activity 2340651
24 March 2005
Security Plan Amendment Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 2318539
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 29 April 2025
Resolved
Each cargo tank of a tank barge must have a high-level indicating device, unless the barge complies with 46 CFR 39.2009(a). The high-level indicating device must—(1) Indicate visually the level of liquid in the cargo tank when the liquid level is within a range of 1 meter (3.28 feet) of the top of the tank; Identified 5 meter sticks on the 1P, 1S, 2P, FWD Slop, and AFT slop that were not connected to meter stick housing. Repair meter sticks to the satisfaction of the attending Marine Inspector.
Condition: Improper Installation
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 30 April 2025
Resolution: Barge rep [name withheld] provided photo evadence of visual inicators being affixed.
06 - Cargo Operations Including Equipment › N/A - No Subsystem › Other (cargo)
Issued 29 April 2025
Resolved
Each nonrising-stem valve, lever-operated valve, or other valve where, because of design, the position of the disc or closure mechanism is not obvious must be fitted with an indicator to show whether the valve is opened or closed. Valve indicator on #2 tank Port cargo transfer line valve does not indicate properly when valve is in closed position. Repair to the satisfaction of the attending Marine Inspector.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 13 May 2025
Resolved 30 April 2025
Resolution: Barge Rep [name withheld] provide video evidence of valve indicator working properly.
Construction/Loadline › Hull › Hull Plating
Issued 6 September 2017
Resolved
Barge shall be made available for inspection upon removal from ground. Thereafter, the barge shall be hauled out for dry-dock and made available for internal structure exam and hull exam.
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 June 2020
Resolution: Barge was Drydocked at Sienna shipyard. Where they found pitting in 40% of the hull plating. Shipyard replaced all damaged plating. Conducted cargo tank internal inspection, internal structural exam. Shipyard repaired several damage cords. Coast Guard iss
Construction/Loadline › Hull › Hull Plating
Issued 12 December 2006
Resolved
11Dec06: Recieved notification via MSU Port Arthur CDO of a collision that involved the T/B EBL 2996. The collision occurred in the vicinity of Texaco Island, Port Arthur. The EBL 2996 was empty and was e/r to a loading facility. Attended barge at Valero, Port Arthur. Identified several areas of impact on the bow rake, all above the waterline. Issued CG-835 requiring the barge to perform an
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 12 December 2006
Resolution: 12Dec06: Attended barge moored at Gulf Copper Marine in Port Arthur. Witnessed airtest of bow void. Identified no leaks to areas of impact. Cleared 01 requirement.
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Cargo Pump
Issued 31 May 2005
Resolved
Make the battery installation and computer installation explosion proof as well as the electronic ignition located on the pump engine.
Condition: Improper Installation
Due 15 June 2005
Resolved 15 June 2005
Deck/Cargo › Cargo Transfer/Lightering (liquid) › Cargo Pump
Issued 26 April 2005
Resolved
The wire connections on the pump engine computer system must be made explosion proof and intrinsrically safe. Also, the battery box, computer box and starter/monitoring device must be made explosion proof and intrinsically safe.
Condition: Improper Installation
Action required: 701 - Prior to carriage of passengers/cargo
Due 26 May 2005
Resolved 31 May 2005
Resolution: The computer box and starter are not required to be intrinsically safe.