Records from 2014 to 2026. Most recent: inspection, 26 February 2026.
Documentation record
Registered dimensions (L × B × D)109.4 ft × 35.5 ft × 12.5 ft
Registered tonnagegross 262 / net 178
ITC dimensions (L × B × D)109.4 ft × 35.5 ft × 12.5 ft
ITC tonnagegross 573 / net 171
BuilderBOCONCO INC · BAYOU LA BATRE, AL, UNITED STATES · built 2014
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeNot recorded
Hull configurationNot recorded
Hailing portHOUSTON, TX
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 11 August 2026 · expires 30 September 2027
Service, as the file records itTowing Vessel
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it171 - Convention (Subpart B), Net Ton
178 - Regulatory (Subpart C or D), Net Ton
573 - Convention (Subpart B), Gross Ton
262 - Regulatory (Subpart C or D), Gross Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 19
26 February 2026
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8317124
19 December 2025
Damage Survey · Deficiency Check
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 8285587
29 September 2025
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8243270
22 July 2025
Administrative Inspection · Deficiency Check
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 8191634
12 January 2025
Type not recorded
No type recorded · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8062389
17 July 2024
In-Service Inspection
Physical examination · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 7967071
13 October 2021
Administrative Inspection · Initial Certification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7359659
25 March 2021
Damage Survey
Physical examination · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 7162598
25 March 2021
Type not recorded
No type recorded · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 7162996
27 April 2020
Deficiency Check · Damage Survey
Physical examination · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 6951428
26 April 2020
Type not recorded
No type recorded · Sector Ohio Valley · USCG Heartland District (CGD-H) · Activity 6955160
21 January 2020
Type not recorded
No type recorded · USCGC SAWFISH (WPB 87357) · USCG Southeast District (CGD-SE) · Activity 6898597
3 October 2019
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6827222
27 April 2019
Damage Survey · Administrative Inspection · Deficiency Check
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 6678124
25 December 2018
In-Service Inspection · Damage Survey · Examination of Repairs
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6603176
25 December 2018
Type not recorded
No type recorded · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6608137
27 October 2015
Type not recorded
No type recorded · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 5752639
21 September 2015
MTSA Verification · Industry Initiated Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5727093
19 August 2014
Administrative Inspection
Administrative · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 4960020
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 22 July 2025
Resolved
Machinery and electrical systems must be designed and maintained to provide for the safe operation of the towing vessel and safety of persons onboard under normal and emergency conditions. #1 Steering pump was reported as inoperable. The vessel's TPO has the option to clear this deficiency with notification to the local OCMI within 72-hours in accordance with CG-CVC Policy Letter 17-10.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 22 July 2025
Resolution: Received TPO and technician report attesting to replacement of 12v batteries that were connected to UPS.
07 - Fire Safety › N/A - No Subsystem › Evaluation of crew performance (fire drills)
Issued 17 July 2024
Resolved
The master of a towing vessel must ensure that drills are conducted and instructions are given to ensure that all crewmembers are capable of performing the duties expected of them during emergencies. The vessel's deck and engineering crew did not know how to operate the fixed-firefighting system. Provide a corrective action plan.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 29 July 2024
Resolution: Received, reviewed and accepted close out report from ABS.
07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 17 July 2024
Resolved
The portable fire pump must be self-priming and power-driven, with sufficient amount of lined commercial fire hose 15 meters (50 feet) in length, at least 40 mm (1.5 inches) in diameter and immediately available to attach to it so that a stream of water will reach any part of the vessel. The vessel is fitted with 75 ft. fire hoses and does not have a special consideration allowing the alternative arrangement.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 29 July 2024
Resolution: Received, reviewed and accepted close out report from ABS.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 17 July 2024
Resolved
Electrical connections must be suitably installed to prevent them from coming loose through vibration or accidental contact. There are no electrical outlets near the freezer in the forward hold and is powered from an extension cord. The extension cord is taught and poses a risk of coming loose.
Action required: 50 - Rectify deficiencies w/in 30 days
Resolved 29 July 2024
Resolution: Received, reviewed and accepted close out report from ABS.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 27 April 2020
Resolved
On 26 April 2020 the starboard MDE shut down when the #5 exhaust valve broke and damaged the #5 piston and cam drive gear for the starboard MDE.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 2 May 2020
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 27 April 2019
Resolved
Port main engine was secured due to possible head gasket issue. Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons onboard under normal and emergency conditions. 46cfr143.205(a)
Condition: Damaged By Earlier Event
Action required: 17 - Rectify deficiencies prior to departure
Due 6 May 2019
Resolved 29 April 2019
Resolution: Port main engine aftercooler leaks were found and new gaskets and seals installed. Underway test performed satisfactorly.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 25 December 2018
Resolved
Machinery must be designed and maintained to provide for safe operation of the towing vessel and safety of persons on board under normal and emergency conditions. Received report of loss of steering. Make necessary repairs to the satisfaction of the marine inspector.
46 CFR 143.205
Condition: Design Flaw
Action required: 17 - Rectify deficiencies prior to departure
Resolved 29 December 2018
Resolution: called out divers to make sure that there was no damage under the boat. Then quadrant and Jockey bar were taken to St Louis where the Machine Shop repaired the Quadrant by bending it back and re boring the holes. Then fabricated two new bushings.
Documentation › Safety/Response Plans/Programs › Vessel Response Plan
Issued 19 August 2014
Resolved
New vessel found operating without NTVRP. Company has QI, Alternate QI, OSRO, and salvor under VRP. Vessel required to submit NTVRP by 19 Sep. 14.
Action required: 705 - Other - as specified
Due 19 September 2014
Resolved 22 September 2014
Resolution: Vessel obtained full approval of the NTVRP.