Inspection history · 51
3 February 2026
Deficiency Check
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 8305541
13 January 2026
Deficiency Check
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 8295942
4 November 2025
Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 8264019
26 November 2024
Drydock Exam · Examination of Repairs · Administrative Inspection · Internal Structural Exam
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 8053009
15 October 2024
Drydock Extension · COI Inspection · Administrative Inspection
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 8019490
10 July 2023
Annual Inspection
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 7738676
7 February 2023
Type not recorded
No type recorded · Station Sabine · USCG Heartland District (CGD-H) · Activity 7633698
29 June 2022
Initial Certification · Administrative Inspection
Physical examination · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 7490595
27 January 2022
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7386515
5 January 2022
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7376049
4 January 2022
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7375557
23 July 2021
Type not recorded
No type recorded · Station Freeport · USCG Heartland District (CGD-H) · Activity 7267363
15 December 2019
Deficiency Check
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6874029
13 December 2019
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6880612
2 October 2019
Administrative Inspection · Initial Certification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6826842
30 June 2015
MTSA Verification · Industry Initiated Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5169152
30 June 2015
Industry Initiated Exam · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 5186004
24 May 2014
Type not recorded
No type recorded · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 4989175
15 May 2013
Industry Initiated Exam · MTSA Verification · DAPI Audit
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 4606239
13 December 2011
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4208907
12 August 2010
Industry Initiated Exam · MTSA Verification
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3821917
8 January 2010
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 3660832
30 August 2009
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3580347
13 January 2009
Administration
Administrative · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3393921
18 November 2008
Administration
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3365182
15 August 2008
Type not recorded
No type recorded · Station Pensacola · USCG Heartland District (CGD-H) · Activity 3301359
20 June 2008
Type not recorded
No type recorded · Sector Mobile · USCG Heartland District (CGD-H) · Activity 3253914
13 August 2007
Type not recorded
No type recorded · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3026975
13 July 2006
MTSA Verification
Physical examination · Sector Mobile · USCG Heartland District (CGD-H) · Activity 2711772
27 January 2006
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 2578078
13 May 2005
Administrative Inspection
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 2356995
24 May 2004
Type not recorded
No type recorded · USCG Heartland District (dre) · USCG Heartland District (CGD-H) · Activity 2077091
3 March 2004
Type not recorded
No type recorded · Station New Orleans · USCG Heartland District (CGD-H) · Activity 2017535
24 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1996365
21 December 2003
Type not recorded
No type recorded · Station Dauphin Island · USCG Heartland District (CGD-H) · Activity 1968099
18 December 2003
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 1973705
31 October 2003
Type not recorded
No type recorded · Station Gulfport · USCG Heartland District (CGD-H) · Activity 1943239
31 October 2003
Type not recorded
No type recorded · Station Gulfport · USCG Heartland District (CGD-H) · Activity 1943244
11 February 2003
Type not recorded
No type recorded · Station New Orleans · USCG Heartland District (CGD-H) · Activity 1743543
19 June 2001
Type not recorded
No type recorded · MSO Mobile · USCG Heartland District (CGD-H) · Activity 68745
22 November 1999
Type not recorded
No type recorded · Station New Orleans · USCG Heartland District (CGD-H) · Activity 1511220
8 April 1998
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 442580
8 April 1998
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 535301
31 December 1997
Type not recorded
No type recorded · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 96574
5 October 1997
Type not recorded
No type recorded · MSO HOUSTON/GALVESTON · USCG Heartland District (CGD-H) · Activity 111699
4 January 1996
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 386546
10 November 1995
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 210029
10 November 1995
Type not recorded
No type recorded · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 753851
12 August 1994
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 726698
10 August 1994
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 369393
7 August 1986
Type not recorded
No type recorded · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 311114
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 16 December 2025
Resolved
Machinery must be designed and maintained to provide safe operation of the towing vessel under normal and emergency conditions. Starboard generator and both main engines had several fuel hoses with significant wear on outer sheathing due to chafing from vibration. Replace damaged hoses.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 16 January 2026
Resolved 13 January 2026
Resolution: Operator provided proof that the hoses were replaced and shielded.
09 - Working and Living Conditions › 092 - Working Conditions › Guards - fencing around dangerous machinery parts
Issued 16 December 2025
Resolved
An exposed hazard, such as rotating machinery, must be protected by a guard, cover, or rail. Both propulsion shafts were exposed, with no guard. Install guard, cover, or rail to prevent personnel entanglement.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 16 January 2026
Resolved 13 January 2026
Resolution: Vessel installed metal grating over exposed machinery.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 16 December 2025
Resolved
Machinery must be designed and maintained to provide safe operation of the towing vessel under normal and emergency conditions. Potable water pump was not permanently secured to its mount. Ensure pump is mounted or secured to prevent pump from falling from mount plate.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 16 January 2026
Resolved 13 January 2026
Resolution: Pump was properly mounted with a bolt and strap.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 15 October 2024
Resolved
Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons onboard under normal and emergency conditions. Port generator had smoke coming from exhaust turbo and lagging during operation.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 November 2024
Resolved 8 November 2024
Resolution: Vessel rep [name withheld], provided video showing the generator running with no smoke coming from original location. All sat.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 15 October 2024
Resolved
Paints, coatings, or other flammable and combustible products onboard a towing vessel must be stored in a designated storage room or cabinet when not in use. Flammable and combustible products were stored forward of the collision bulkhead and on aft steering deck.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 October 2024
Resolved 31 October 2024
Resolution: Photo documentation showing flammable and combustible liquid removed from forward of the collision bulkhead.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 15 October 2024
Resolved
A fixed fire pump must be capable of:
Delivering water simultaneously from the two highest hydrants, or from both branches of the fitting if the highest hydrant has a Siamese fitting, at a pitot-tube pressure of at least 344 kilopascals (kPa) (50 pounds per square inch (psi)), and a flow rate of at least 300 liters per minute (lpm) (80 gallons per minute (gpm)). Fixed fire pump pressure gauge was unreadable due to paint over spray.
Condition: Damaged By Earlier Event
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 October 2024
Resolved 17 October 2024
Resolution: Vessel rep provided photo documentation of readable gauge.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 15 October 2024
Resolved
Piping and machinery components that exceed 220 °C (428 °F), including fittings, flanges, valves, exhaust manifolds, and turbochargers, must be insulated. Measures must be in place to prevent flammable or combustible liquid piping leaks from coming into contact with these components. Starboard main engine was missing approximately a foot and a half of lagging on exhaust piping.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 October 2024
Resolved 8 November 2024
Resolution: Vessel rep [name withheld], provided photo documentation showing lagging installed on exposed exhaust piping. All sat.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 15 October 2024
Resolved
Each towing vessel must be equipped with an industrial type first aid cabinet or kit, appropriate to the size of the crew and operating conditions. First aid kit had numerous medications expired.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 October 2024
Resolved 31 October 2024
Resolution: Photo documentation showing new first aid kit installed.
11 - Life Saving Appliances › N/A - No Subsystem › Other (life saving)
Issued 15 October 2024
Resolved
The master must ensure that all lifesaving equipment is properly maintained and ready for use at all times. Life float needs re-stenciling, re-taping with reflective tape, and arranged so that it is float free.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 October 2024
Resolved 31 October 2024
Resolution: Photo documentation attesting to restenciling and retaping of life float.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 15 October 2024
Resolved
The master must ensure that all hatches, doors, and other openings designed to be watertight or weather-tight function properly. Aft voids hatches were sealed shut. Only one of three was able to be opened by crew.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 October 2024
Resolved 31 October 2024
Resolution: Photo documentation of aft void hatches opened to assess internal void condition.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 15 October 2024
Resolved
Machinery and electrical systems must be designed and maintained to provide for safe operation of the towing vessel and safety of persons onboard under normal and emergency conditions. Emergency lighting in the upper deck of machinery space had one of two lights dangling from electrical wire.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 29 October 2024
Resolved 8 November 2024
Resolution: Vessel rep [name withheld], provided photo documetation showing fixed electrical lighting in machinery space. All sat.
02 - Structural Conditions › N/A - No Subsystem › Bulkhead -corrosion
Issued 15 October 2024
Resolved
Nature of Inspection. The inspection will include inspections of the structure, pressure vessels and their appurtenances, piping, main and auxiliary machinery, electrical installations, lifesaving appliances, fire detecting and extinguishing equipment, pilot boarding equipment, and other equipment. Aft bulkhead structure was not in compliance due to an approximate 2" hole going through the bulkhead, just behind the fire pump switch. Crop and renew.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 November 2024
Resolved 17 October 2024
Resolution: Vessel rep provided photo documentation of cropped and renewed section.
99 - Other › N/A - No Subsystem › Other (Safety in general)
Issued 15 October 2024
Resolved
A vessel must be operated IAW applicable laws and regulations and in such a manner as to afford protection against hazards to life, property, and the environment. Aft ladder well missing half chain link to secure it.
Condition: Improper/Lack of Maintenance
Action required: 17 - Rectify deficiencies prior to departure
Resolved 17 October 2024
Resolution: Vessel rep provided photo documentation showing new chain link at ladder well.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 15 December 2019
Resolved
A vessel's machinery is designed and must be maintained to provide for safe operation of the vessel and safety of persons on board under normal and emergency conditions.
Vessel reported a loss of propulsion operating with a barge in the Houston Ship Channel. The cause of the loss must be diagnosed and repaired prior to the vessel being put back in service. 46CFR143.205(a) 701c
Condition: Invalid
Action required: 701 - Prior to carriage of passengers/cargo
Due 15 December 2019
Resolved 16 December 2019
Resolution: Received ABS survey report. All SAT.