Every line above is a count of records the US Coast Guard wrote, or a date it recorded.
A blank resolution means none was recorded in this data; it does not establish that a
deficiency is outstanding. Years with a record are calendar years in which a record
exists, not years in service. What Maury does
not do.
1058 - Regulatory (Subpart C or D), Gross Ton
1058 - Regulatory (Subpart C or D), Net Ton
Maury page id
psix-31209
Vessel history report
Every record for this hull, in one document — $299
Every recorded inspection, 1972 to
2026, in one chronology · every deficiency, with system, dates
and resolution · operational controls imposed and removed · every name this
hull has been recorded under · the vessels it was inspected alongside, and when
· how its record compares with hulls of similar age and size, as a fact about the
population and never a judgement about this vessel.
This report is in development and is not for sale yet. There is
no date, and nothing is charged. Leave an email and we will tell you when it exists, once.
Used only to tell you when the report exists.
Not shared, not sold, and not added to a mailing list.
The Coast Guard recorded this vessel and the following in the same
inspection activity — normally a tug and the barges in its tow. Only barges and towing
vessels are in this archive, so any other vessel type in the same activity does not
appear here: these lists are a floor, not a complete manifest.
Vessel's high level and overfill alarms do not function properly. Alarms are excess equipment, but are required to function properly if onboard. Vessel is required to remove or repair equipment properly to the satisfaction of the CG prior to cargo operations
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 3 October 2019
Resolution: High Alarms tested, All SAT.
Deck/Cargo › Cargo Stowage
Issued 11 August 2003Resolved
Test PV Valves, prove proper operation and provide test report to Coast Guard. LEGACY COMPONENT DESC: PV Valves
Due 18 August 2003
Resolved 14 August 2003
Resolution: Received report verifying proper operation of PV valves.