Records from 2002 to 2022. Most recent: inspection, 7 June 2022.
Documentation record
Registered dimensions (L × B × D)297.5 ft × 54.0 ft × 12.0 ft
Registered tonnagegross 1,619 / net 1,619
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderTRINITY MARINE PRODUCTS INC · ASHLAND CITY, TN, UNITED STATES · built 2002
Hull materialSteel
PropulsionNot recorded
Hull shapeBox
Hull configurationMonohull
Hailing portVICKSBURG, MS
Trade endorsementsCoastwise, unrestricted
DocumentationValid · issued 7 August 2025 · expires 31 August 2026
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1619 - Simplified, Gross Ton
1619 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 September 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 28
7 June 2022
Administrative Inspection
Administrative · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 7470855
19 February 2020
Damage Survey · Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 6911324
7 February 2020
Examination of Repairs · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6904707
14 February 2019
Administrative Inspection · Examination of Repairs
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 6625786
11 February 2019
Damage Survey
Physical examination · Marine Safety Unit Texas City · USCG Heartland District (CGD-H) · Activity 6623544
18 April 2018
Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6549794
3 March 2017
COI Inspection · Examination of Repairs · MTSA Verification · Internal Structural Exam
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 6096921
11 March 2016
MTSA Verification · Annual Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 5829840
11 March 2015
MTSA Verification · Periodic Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 5079239
1 December 2014
Type not recorded
No type recorded · Marine Safety Unit Vicksburg · USCG Heartland District (CGD-H) · Activity 5032594
5 April 2014
Damage Survey · Administrative Inspection · Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 4830647
5 April 2014
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 4830880
14 March 2014
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 4814173
17 February 2012
COI Inspection · Cargo Tank Internal · MTSA Verification · Construction Oversight · Internal Structural Exam · Examination of Repairs · Drydock Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4246448
14 June 2010
Periodic Inspection · MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3761980
27 April 2009
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 3468843
29 May 2008
Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3220286
24 May 2008
Type not recorded
No type recorded · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3219379
24 May 2008
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 3219702
8 May 2008
Annual Inspection
Physical examination · Marine Safety Unit Huntington · USCG Heartland District (CGD-H) · Activity 3260745
9 April 2007
Internal Structural Exam · MTSA Verification · Examination of Repairs · COI Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2903564
20 March 2007
Type not recorded
No type recorded · Marine Safety Unit Lake Charles · USCG Heartland District (CGD-H) · Activity 2891656
31 March 2006
Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2613684
22 February 2005
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 2297125
2 July 2004
Periodic Inspection · MTSA Verification
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 2123639
30 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1996541
25 April 2003
Re-Inspection
Physical examination · MSO Paducah · USCG Heartland District (CGD-H) · Activity 1787671
24 April 2002
Cargo Tank Internal · Construction Oversight · Initial Certification · Deadweight Survey · Hull Examination
Physical examination · Marine Safety Detachment Nashville · USCG Heartland District (CGD-H) · Activity 1608544
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 19 February 2020
Resolved
Scantlings, materials, and workmanship shall be equivalent to ABS or other classification society. Repair as original damage to #2 port cargo tank. Barge authorized discharge of current cargo prior to repairs then must complete permanent repairs to the satisfaction of attending USCG Marine Inspector prior to further cargo operations.
Action required: 15 - Rectify deficiencies by next port
Due 19 February 2020
Resolved 20 March 2020
Construction/Loadline › Hull › Side Shell
Issued 5 April 2014
Resolved
Make temporary repairs to the 20" x 2.5" vertical split in the #7 stbd wing void starting at the 3' draft ending at the 5' draft. After temp repairs have dried barge may proceed to offload at Exxon.
Action required: 705 - Other - as specified
Resolved 6 April 2014
Construction/Loadline › Hull › Side Shell
Issued 5 April 2014
Resolved
Upon discharge the barge must proceed directly to repair yard to make permanent repairs. NO FURTHER CARGO OPERATIONS ARE AUTHORIZED AFTER DISCHARGE.
Action required: 705 - Other - as specified
Resolved 14 April 2014
Construction/Loadline › Hull › Bottom Plating
Issued 24 May 2008
Resolved
Present barge for further examination of the bow, #1 and #2 wing voids, due to a grounding occurring on 24MAY08.
Action required: 705 - Other - as specified
Due 24 June 2008
Resolved 29 May 2008