MAURY USCG vessel records
← All vessels

SPIRIT OF CAROLINA

Built
1998
Last inspected
22 June 2026
Documentation
Valid · NVDC file of 10 August 2026
Controls
None recorded without a removal date

Coast Guard record current through 23 August 2026, retrieved 5 September 2026 from PSIX. Every field on this page was recorded by the Coast Guard. Records for the Passenger Ship class in Maury's sources begin in 2016.

Inspection record

Last inspected 22 June 2026
Operational controls None recorded without a removal date
Years with a record 11 calendar years (2016–2026)
Every line above is a count of records the US Coast Guard wrote, or a date it recorded. A blank resolution means none was recorded in this data; it does not establish that a deficiency is outstanding. Years with a record are calendar years in which a record exists, not years in service. What Maury does not do.

Identity

WDP4624
469369
Flag
UNITED STATES
Maury page id
psix-469369

Documentation record

Registered dimensions (L × B × D)87.7 ft × 30.0 ft × 8.0 ft
Registered tonnagegross 94 / net 64
ITC dimensions (L × B × D)87.7 ft × 30.0 ft × 8.0 ft
ITC tonnagegross 520 / net 189
BuilderFREEPORT SHIPBUILDING INC · FREEPORT, FL, UNITED STATES · built 1998
Hull materialSteel
PropulsionDiesel Reduction
Hull shapeUNSPECIFIED
Hull configurationUNSPECIFIED
Hailing portCHARLESTON, SC
Endorsements, as the file codes themcw_un
DocumentationValid · issued 1 December 2025 · expires 31 December 2026
Service, as the file records itPassenger (Inspected)
Hull formpowered (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it520 - Convention (Subpart B), Gross Ton
94 - Regulatory (Subpart C or D), Gross Ton
189 - Convention (Subpart B), Net Ton
64 - Regulatory (Subpart C or D), Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Professional
The full record for this vessel

Behind this panel: 24 inspections, each with its date, unit and type; 41 deficiencies with the resolution recorded against each; operational controls, none recorded without a removal date; no tow-unit appearances recorded; no other recorded names; the documentation record: dimensions, tonnage, builder, hailing port and endorsements. Every line is a record the Coast Guard wrote; the counts above are the same counts as in the summary, and they are free.

Professional is $39 a month or $299 a year, or $19.99 a month locked for life at the founding rate, for the first 200 subscribers. It unlocks every detail section on every vessel page, fleet watch tied to your account, and ownership records on request. Already a subscriber? Sign in.

Maury does not score, rate or grade vessels, at any price.

Vessel history report
Every record for this hull, in one document — $299

Every recorded inspection, 1972 to 2026, in one chronology · every deficiency, with system, dates and resolution · operational controls imposed and removed · every name this hull has been recorded under · the vessels it was inspected alongside, and when · how its record compares with hulls of similar age and size, as a fact about the population and never a judgement about this vessel.

Read one first, in full: a forty-year chronology · a hull that changed operators four times · the sparse case, shown as an example, not for sale.

This report is in development and is not for sale yet. There is no date, and nothing is charged. Leave an email and we will tell you when it exists, once.

Inspection history · 24

22 June 2026 Vessel Attendance · Special Consideration
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 8412901
25 March 2026 Administrative Inspection
Administrative · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 8329403
18 June 2025 COI Inspection · Examination of Repairs · Deficiency Check · Vessel Attendance
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 8162300
28 January 2025 Drydock Exam · Internal Structural Exam
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 8071302
8 October 2024 Administrative Inspection
Administrative · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 8016401
10 June 2024 Annual Inspection
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 7931866
17 April 2023 Deficiency Check · COI Inspection
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 7670145
8 February 2023 Drydock Exam · Internal Structural Exam
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 7633827
26 July 2022 Administrative Inspection · Annual Inspection
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 7516630
4 February 2022 MTSA Verification · Deficiency Check
Physical examination · Detached Duty Office Myrtle Beach · USCG Southeast District (CGD-SE) · Activity 7391102
23 July 2021 Administrative Inspection · Annual Inspection · DAPI Audit
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 7265707
12 March 2021 Hull Examination · Internal Structural Exam · Examination of Repairs
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 7162860
14 January 2021 Internal Structural Exam · Administrative Inspection · Drydock Extension
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 7124704
4 March 2020 Annual Inspection · Deficiency Check · DAPI Audit · Administrative Inspection
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6920488
7 August 2019 Deficiency Check · Examination of Repairs · Drydock Exam · Internal Structural Exam
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6777959
24 July 2019 Deficiency Check · Annual Inspection · DAPI Audit
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6760767
22 January 2019 Administrative Inspection · Examination of Repairs
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6618576
30 April 2018 DAPI Audit · COI Inspection · Deficiency Check
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6402640
7 February 2018 Drydock Exam · Hull Examination · Examination of Repairs
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6355743
12 October 2017 Damage Survey
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6286446
4 October 2017 Deficiency Check
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6281030
24 July 2017 DAPI Audit · Annual Inspection
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 6215912
25 July 2016 MTSA Verification · Deficiency Check · Annual Inspection · DAPI Audit
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 5949199
4 February 2016 Drydock Exam · Administrative Inspection · Hull Examination · Deficiency Check
Physical examination · Sector Charleston · USCG Southeast District (CGD-SE) · Activity 5817721

Deficiency record · 41

07 - Fire Safety › N/A - No Subsystem › Fire fighting equipment and appliances
Issued 26 January 2026 Resolved
Spanner wrenches must be provided for each fire hydrant required. Spanner wrenches were missing from fire hydrants.
Condition: Improper/Lack of Maintenance
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 February 2026
Resolved 5 February 2026
Resolution: MI attended vessel to verify spanner wrenches were placed at each fire station.
09 - Working and Living Conditions › 092 - Working Conditions › Guards - fencing around dangerous machinery parts
Issued 26 January 2026 Resolved
An exposed hazard, such as gears or rotating machinery, must be protected by a cover, guard, or rail. Port and Starboard engines have openings to mount starters that require engine covers to be installed.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 February 2026
Resolved 5 February 2026
Resolution: MI attended vessel to verify engine starter port covers were installed.
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 26 January 2026 Resolved
Nonconducting mats or grating must be provided on the deck in front of each switchboard. Switchboards in engine room were missing the non-conductive mats.
Condition: Improper Installation
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 February 2026
Resolved 5 February 2026
Resolution: MI's attended vessel to verify deck matting had been installed.
01 - Certificates & Documentation › 011 - Ships Certificates › Certificate of Inspection (COI)
Issued 31 July 2025 Resolved
Your vessel must undergo an annual inspection within the 3 months before or after each anniversary date. You must contact the cognizant OCMI to schedule an inspection at a time and place which he or she approves. No written application is required. Vessel did not complete annual inspection required no later than 29 July 2025 due to ongoing repairs in dry dock. 46 CFR 176.500(b)(1)
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 26 January 2026
Resolution: Vessel completed annual COI
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 10 June 2024 Resolved
Electrical equipment on a vessel must be installed and maintained to: Protect passengers, crew, other persons, and the vessel from electrical hazards, including fire, caused by or originating in electrical equipment, and electrical shock; Termination box behind bar on second deck exposing dead end wires and missing cover. 46 CFR 120.200 (b)
Action required: 16 - Rectify deficiencies w/in 14 days
Due 24 June 2024
Resolved 17 June 2024
Resolution: Cover added to electrical box.
09 - Working and Living Conditions › 091 - Living Conditions › Lighting (Accommodation)
Issued 17 April 2023 Resolved
Protect passengers, crew, other persons, and the vessel from electrical hazards, including fire, caused by or originating in electrical equipment, and electrical shock; The light in the vicinity of the main deck was hanging loose and did not have a lamp attached.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 May 2023
Resolved 3 May 2023
Resolution: Light was secured.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 17 April 2023 Resolved
Protect passengers, crew, other persons, and the vessel from electrical hazards, including fire, caused by or originating in electrical equipment, and electrical shock. The cable for the steamer located in the galley was not secured with strain relief at the junction box.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 May 2023
Resolved 3 May 2023
Resolution: Conduit secured to junction box and strain relief installed.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 17 April 2023 Resolved
Protect passengers, crew, other persons, and the vessel from electrical hazards, including fire, caused by or originating in electrical equipment, and electrical shock. The strain relief for the HVAC cable located in the chair hold was not connected.
Action required: 16 - Rectify deficiencies w/in 14 days
Due 1 May 2023
Resolved 3 May 2023
Resolution: Strain relief connected.
09 - Working and Living Conditions › 092 - Working Conditions › Lighting (Working spaces)
Issued 23 July 2021 Resolved
Each vessel must have adequate emergency lighting fitted along the line of escape to the main deck from all passenger and crew accommodation spaces located below the main deck. Watertight door leading to engine room has inadequate emergency lighting in way of the engine room side of watertight door. Demonstrate adequate engine room lighting.
Condition: Design Flaw
Action required: 16 - Rectify deficiencies w/in 14 days
Due 9 August 2021
Resolved 23 August 2021
08 - Alarms › N/A - No Subsystem › Other (alarms)
Issued 23 July 2021 Resolved
Gauges to indicate engine revolutions per minute (RPM), jacket water discharge temperature, and lubricating oil pressure must be provided for all propulsion engines installed in the vessel. The gauges must be readily visible at the operating station. Starboard main engine oil pressure gauge at operating station does not function. Prove proper operation of the starboard main engine oil pressure gauge. 46 CFR 120.410(b)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2021
Resolved 23 August 2021
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 23 July 2021 Resolved
Each battery must be located as high above the bilge as practicable, secured to protect against shifting with the roll and pitch of the vessel, and free from exposure to water splash or spray. Batteries on bridge and in lazarette are not secured to prevent shifting. Battery charger is not protected with drip tray. 46 CFR 120.350(b)
Condition: Design Flaw
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2021
Resolved 23 August 2021
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Propulsion main engine
Issued 23 July 2021 Resolved
Machinery and equipment installed on each vessel must be suitable for the vessel and its operation and for the purpose intended. Starboard raw water AC pump is not properly bolted down. Demonstrate proper securing of raw water pump for marine use. 46 CFR 119.200 (a)
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2021
Resolved 23 August 2021
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 23 July 2021 Resolved
Electrical equipment on a vessel must be installed and maintained to provide services necessary for safety under normal and emergency conditions. "Power available" lights for generators on main switchboard were not functioning. Prove proper operation of power available lights. 46 CFR 120.200(a)
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2021
Resolved 23 August 2021
02 - Structural Conditions › N/A - No Subsystem › Electrical installations in general
Issued 23 July 2021 Resolved
Each connection to a conductor or terminal part of a conductor must be made within an enclosure and have either: A pressure type connector on each conductor; A solder lug on each conductor; A splice made with a pressure type connector to a flexible lead or conductor; or A splice that is soldered, brazed, or welded to a flexible lead or conductor. Microphone and horn wiring connections are not in junction boxes and multiple crimp connections used for various bridge equipment. Prove proper electrical installation
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 26 August 2021
Resolved 23 August 2021
02 - Structural Conditions › N/A - No Subsystem › Hull - corrosion
Issued 15 January 2021 Resolved
Each watertight bulkhead must be of sufficient strength to be capable of remaining watertight with a head of water to the top of the bulkhead. Pin holes and doubler were identified in the aft bulkhead of the Engine Room, Temporary repairs must be conduct until permanent repairs can be completed at dry dock. Rounds must be conducted every 30 min and results logged in ships log.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Resolved 7 October 2021
Resolution: Superseded or corrected on another inspection.
07 - Fire Safety › N/A - No Subsystem › Maintenance of Fire protection systems
Issued 13 July 2020 Resolved
A-Class bulkheads or decks must be composed of steel or equivalent material, suitably stiffened and made intact with the main structure of the vessel, such as the shell, structural bulkheads, and decks. They must be so constructed that, if subjected to the standard fire test, they are capable of preventing the passage of smoke and flame for 1 hour. In addition, they must be so insulated with approved structural insulation. Port and Stbd sides of the engineroom are missing required insulation.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 August 2020
Resolved 12 August 2020
Resolution: Replaced insulation as per required.
07 - Fire Safety › N/A - No Subsystem › Main Vertical zone
Issued 13 July 2020 Resolved
A door in a stairtower, stairway, and main vertical zone bulkhead must meet the following additional requirements:(i) A door must be of the self-closing type capable of closing against a 3.5 list of the vessel. Fire doors are not closing properly.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 August 2020
Resolved 12 August 2020
Resolution: Fire doors were adjusted.
03 - Water/Weathertight Conditions › N/A - No Subsystem › Manholes/flush scuttles
Issued 13 July 2020 Resolved
a) A hatch exposed to the weather must be watertight, except that the following hatches may be weathertight. fore peak flush hatch is not water tight.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 August 2020
Resolved 12 August 2020
Resolution: Fore peak hatch was adjusted
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 13 July 2020 Resolved
Each connection to a conductor or terminal part of a conductor must be made within an enclosure and have either: (1) A pressure type connector on each conductor; (2) A solder lug on each conductor; (3) A splice made with a pressure type connector to a flexible lead or conductor Dead end wires in stbd fwd engine room.
Condition: Improper Installation
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 August 2020
Resolved 12 August 2020
Resolution: Dead end wires were properly terminated and or removed
10 - Safety of Navigation › N/A - No Subsystem › Lights, shapes, sound-signals
Issued 13 July 2020 Resolved
(a) Shapes shall be black and of the following sizes: (i) A ball shall have a diameter of not less than 0.6 meter. (ii) A cone shall have a base diameter of not less than 0.6 meters and a height equal to its diameter. (iii) A diamond shape shall consist of two cones (as defined in paragraph (a)(ii) of this section) having a common base. (b) The vertical distance between shapes shall be at least 1.5 meters.
Condition: Invalid
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 August 2020
Resolved 12 August 2020
Resolution: Day shape was placed into service
11 - Life Saving Appliances › N/A - No Subsystem › Lifejackets incl. provision and disposition
Issued 4 March 2020 Resolved
In addition, a number of child-size life jackets equal to at least 10% of the number of persons permitted on board must be provided, or such greater number as necessary to provide a life jacket for each person being carried that is smaller than the lower size limit of the the adult life jackets provided to meet this section 4 child life jackets were unservicable limited to 300 adult passengers
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Resolved 7 October 2021
Resolution: Superseded or corrected on another inspection.
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Operation of machinery
Issued 4 March 2020 Resolved
Shutoff valves, installed so as to close against the fuel flow, must be fitted in the fuel supply lines, one at the tank connection and one at the engine end of the fuel line to stop fuel flow when servicing accessories. The shutoff valve at the tank must be manually operable from outside the compartment in which the valve is located. Fuel shut off valve will not close completely due to flex in the cable run tubing.
Condition: Improper/Lack of Maintenance
Action required: 50 - Rectify deficiencies w/in 30 days
Due 13 August 2020
Resolved 12 August 2020
Resolution: Fuel valve bracket was adjusted.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 13 January 2020 Resolved
A smoke actuated fire detection system of a type approved by the Commandant that is installed in accordance with 46 CFR part 76. Control panel was found un-servicable and was replace with a new panel, submit plans to MSC to verify meets the requirement and update drawing to reflect updated installation.
Action required: 50 - Rectify deficiencies w/in 30 days
Due 14 February 2020
Resolved 7 February 2020
Resolution: Submitted updated plan to MSC
13 - Propulsion and Auxiliary Machinery › N/A - No Subsystem › Other (machinery)
Issued 24 July 2019 Resolved
Provide repairs to the cracked welds on the hydraulic pump/reservoir. Additionally, fix crack on starboard side jockey bar. Replace to new the rudder angle indicator alarm.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 25 July 2019
Resolution: repairs were made to the system and tested, sat.
07 - Fire Safety › N/A - No Subsystem › Fire detection and alarm system
Issued 24 July 2019 Resolved
Provide repairs to the fire detection panel and show operation without truble light.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 3 February 2020
07 - Fire Safety › N/A - No Subsystem › Ventilation
Issued 24 July 2019 Resolved
Place in service ventilation closure for galley intake vent.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 25 July 2019
Resolution: A new closure was fabricated and placed in service.
07 - Fire Safety › N/A - No Subsystem › Other (fire safety)
Issued 24 July 2019 Resolved
Provide cleaning for galley hood.
Action required: 705 - Other - as specified
Resolved 25 July 2019
Resolution: The galley hood was cleaned by a qualified third party.
04 - Emergency Systems › N/A - No Subsystem › Emergency, lighting, batteries and switches
Issued 24 July 2019 Resolved
Show proper operation of emergency lighting outside the galley.
Action required: 17 - Rectify deficiencies prior to departure
Resolved 29 July 2019
Resolution: Emergency light was repaired and tested.
09 - Working and Living Conditions › 092 - Working Conditions › Electrical
Issued 24 July 2019 Resolved
Place a breaker or a spacer in distribution panel at wait staff station.
Action required: 16 - Rectify deficiencies w/in 14 days
Resolved 29 July 2019
Resolution: A breaker spacer was placed in the panel.
Fire Fighting › Structural - A Class Divisions › Machinery Spaces
Issued 30 April 2018 Resolved
Structural fire protection in machinery space above batteries is serverly damaged due to a fire. Replace damaged SFP in accordance with original construction to the satisfaction of the attending marine inspector.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 31 May 2018
Resolved 3 February 2020
Resolution: Old deficiency, cleared
Fire Fighting › Portable CO2 Fire Extinguisher › Mounting Bracket
Issued 30 April 2018 Resolved
Three fire extinguishers are missing brackets. Replace as per manufacturer to the satisfaction of the USCG.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 May 2018
Resolved 30 May 2018
Lifesaving › Lifebuoys › Serviceable
Issued 30 April 2018 Resolved
Ring buoy located on STBD side main deck is deterioated. Replace to the satisfaction of the attending USCG.
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 31 May 2018
Resolved 30 May 2018
Fire Fighting › Fixed CO2 Fire Extinguishing System › Servicing
Issued 12 October 2017 Resolved
Vessel experienced fire in engine room and CO2 was released. Prior to carrying passengers vessel must have system recharged and retested in the presence of a USCG Marine Inspector.
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Due 31 October 2017
Resolved 13 October 2017
Electrical › Electrical Distribution System (service) › Panelboard
Issued 24 July 2017 Resolved
Replace knock out missing from engine room breaker box.
Due 24 August 2017
Resolved 4 October 2017
Fire Fighting › Ventilation Systems › Operating Controls
Issued 24 July 2017 Resolved
Label ventilation motor controller on port side of engine room.
Due 24 August 2017
Resolved 4 October 2017
Fire Fighting › Structural Fire Protection - General › Accommodation Space Protection
Issued 24 July 2017 Resolved
Provide CG approval certificate for new carpet in salon areas.
Due 24 August 2017
Resolved 4 October 2017
Operations/Management › Lifesaving › Op Readiness/Maintenance/Inspection
Issued 24 July 2017 Resolved
Begin maintaining a life saving maintenance record.
Due 24 August 2017
Resolved 4 October 2017
Electrical › Electric Generation Source (service) › Generator
Issued 25 July 2016 Resolved
Provide cleaning maintenance to generator windings.
Action required: 705 - Other - as specified
Due 1 August 2016
Resolved 10 August 2016
Resolution: Preventive maintenance was performed on generator windings.
Accommodation/Occupational Safety › Cooking Systems › Cooking Fuel
Issued 25 July 2016 Resolved
Provide cleaning to galley hood.
Action required: 705 - Other - as specified
Due 1 August 2016
Resolved 10 August 2016
Resolution: Galley hood was cleaned by qualified company.
Electrical › Electrical Distribution System (service) › Cable
Issued 25 July 2016 Resolved
Rewire entrance light in E/R.
Action required: 705 - Other - as specified
Due 1 August 2016
Resolved 10 August 2016
Resolution: Light fixture at E/R entrance was remounted and rewired.
Communications › Alarms/Indicators › High Water Alarm
Issued 25 July 2016 Resolved
Show proper operation of H/W alarm in "chair room."
Action required: 701 - Prior to carriage of passengers/cargo
Resolved 25 July 2016
Resolution: Vessel showed proper operation of HW alarm.

Ownership record

The Coast Guard's documentation record for this hull -- the Abstract of Title, with its owners and liens as filed -- is not in PSIX. Ask, and Maury buys it from the National Vessel Documentation Center, files it here with its date, and every reader of this page gets it.