Documentation record
Registered dimensions (L × B × D)200.0 ft × 54.0 ft × 12.0 ft
Registered tonnagegross 1,088 / net 1,088
ITC dimensions (L × B × D)Not recorded
ITC tonnageNot recorded
BuilderNEWPARK SHIPBLDG GALVESTO · GALVESTON, TX, UNITED STATES · built 1999
Hull materialSteel
PropulsionUNSPECIFIED
Hull shapeBox
Hull configurationMonohull
Hailing portNEW ORLEANS, LA
Endorsements, as the file codes themcw_un, reg_nfv
DocumentationValid · issued 16 September 2025 · expires 30 September 2026
Service, as the file records itTank Barge
Hull formbarge (Maury's inference from propulsion, hull shape, material and length, rule hf-1; not a recorded fact)
Tonnage as PSIX records it1088 - Simplified, Gross Ton
1088 - Simplified, Net Ton
Every line above is a field of the National Vessel Documentation Center's file as served by NOAA Fisheries, dated 10 August 2026, matched to this hull on its Official Number. Registered and ITC measurements are two systems and are never combined. One snapshot is held so far; documentation history begins with the next.
Inspection history · 48
1 July 2025
Examination of Repairs · Deficiency Check · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 8172692
20 May 2025
Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 8139781
2 May 2024
Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 7905392
17 October 2023
In-Service Inspection · Administrative Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7810178
29 September 2023
Examination of Repairs · COI Inspection · Administrative Inspection · Internal Structural Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 7800581
7 June 2023
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 7708060
29 December 2021
Damage Survey · Examination of Repairs
Physical examination · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 7373637
22 July 2019
Examination of Repairs · Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6758501
17 June 2019
Damage Survey · Administrative Inspection
Physical examination · Marine Safety Unit Paducah · USCG Heartland District (CGD-H) · Activity 6716417
4 February 2019
MTSA Verification · COI Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6616062
9 November 2018
Internal Structural Exam · Administrative Inspection · Drydock Exam · Cargo Tank Internal · Examination of Repairs
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 6578275
15 August 2018
Administrative Inspection
Administrative · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 6513273
27 September 2017
Internal Structural Exam · Deficiency Check · Examination of Repairs · Administrative Inspection · Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6276227
20 September 2017
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6271469
16 September 2016
Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 6009353
2 September 2015
Deficiency Check
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 5233741
24 August 2015
Examination of Repairs · Deficiency Check
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 5225869
6 August 2015
Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 5208772
31 July 2015
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 5233734
17 December 2014
MTSA Verification · Examination of Repairs · Annual Inspection
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 5041371
16 October 2013
Administrative Inspection · Examination of Repairs · COI Inspection · MTSA Verification · Internal Structural Exam
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4735612
17 December 2012
Type not recorded
No type recorded · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 4503381
22 February 2012
Damage Survey
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 4249463
12 December 2011
Periodic Inspection · MTSA Verification
Physical examination · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 4206525
10 October 2011
Type not recorded
No type recorded · Marine Safety Unit Morgan City · USCG Heartland District (CGD-H) · Activity 4198315
22 December 2010
Administrative Inspection
Administrative · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3914812
10 November 2010
MTSA Verification · Annual Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3888765
1 March 2010
Annual Inspection · MTSA Verification
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 3687804
4 September 2009
Type not recorded
No type recorded · Sector Corpus Christi · USCG Heartland District (CGD-H) · Activity 3596918
14 November 2008
COI Inspection · Internal Structural Exam · Hull Examination · Cargo Tank Internal · MTSA Verification
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3360711
5 August 2008
Examination of Repairs
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 3288790
9 May 2008
MTSA Verification · Annual Inspection
Physical examination · Marine Safety Unit Port Arthur · USCG Heartland District (CGD-H) · Activity 3202597
12 July 2007
Type not recorded
No type recorded · Marine Safety Unit Chicago · USCG Great Lakes District (CGD-GL) · Activity 3021518
11 June 2007
MTSA Verification · Periodic Inspection
Physical examination · Sector Houston/Galveston · USCG Heartland District (CGD-H) · Activity 2958356
2 December 2006
Deficiency Check · Damage Survey
Physical examination · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 2833539
2 December 2006
Type not recorded
No type recorded · Marine Safety Unit Galveston · USCG Heartland District (CGD-H) · Activity 2836254
8 May 2006
Plan Review (Other than "T") · Annual Inspection · MTSA Verification · Administrative Inspection
Physical examination · Sector New Orleans · USCG Heartland District (CGD-H) · Activity 2643842
15 July 2005
COI Inspection · MTSA Verification
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 2426970
20 December 2004
Annual Inspection · Internal Structural Exam · MTSA Verification
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 2262375
30 December 2003
Security Plan Review - ASP
Administrative · Marine Safety Center (MSC) · Activity 1997048
25 September 2003
Annual Inspection
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 1912994
19 February 2003
Damage Survey
Physical examination · Marine Safety Unit Baton Rouge · USCG Heartland District (CGD-H) · Activity 1747012
1 November 2002
Annual Inspection
Physical examination · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 1699363
4 December 2001
Re-Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 772791
24 October 2000
Type not recorded
No type recorded · MSU LAKE CHARLES · USCG Heartland District (CGD-H) · Activity 494555
21 September 2000
COI Inspection
Physical examination · MSO PORT ARTHUR · USCG Heartland District (CGD-H) · Activity 822640
28 June 2000
Administrative
Administrative · MSO NEW ORLEANS · USCG Heartland District (CGD-H) · Activity 820360
16 December 1999
Initial Construction-Excluding Oversight · Initial Certification · Hull Examination
Physical examination · MSU GALVESTON · USCG Heartland District (CGD-H) · Activity 1443020
02 - Structural Conditions › N/A - No Subsystem › Other (Structural condition)
Issued 14 July 2025
Resolved
When major alterations or major repairs of tank vessels become necessary the work shall be done under the direction of the Officer in Charge, Marine Inspection, and shall be in accordance with the regulations in effect for new construction insofar as possible. MI observed deck gunwale insert at STBD #3 wing void. During the examination of repairs, MI found adjacent side chord crushed beyond 25% at all five side longitudinal connections. Crop and renew side chord to the satisfaction of the attending marine inspector prior to cargo operations. 46 CFR 30.01-10 701c
Action required: 701 - Prior to carriage of passengers/cargo
Due 14 July 2025
Resolved 22 July 2025
02 - Structural Conditions › N/A - No Subsystem › Hull damage impairing seaworthiness
Issued 17 June 2019
Resolved
Fracture 11’ inboard of the starboard side and extending inboard 10’, the upper estimated 4’ of stern log is set in 0 - 4” to varying degrees with the adjacent deck distorted in way. Located 13’ inboard of the starboard side, deck is fractured 1.5” x 1/8”; located approximately 19’ inboard of the starboard side, the deck is pulled from internal vertical stiffener and holed in way 3” x 1.5”.
Condition: Invalid
Action required: 50 - Rectify deficiencies w/in 30 days
Due 17 June 2019
Resolved 1 August 2019
Resolution: Damaged areas have been repaired and a satisfactory air test was witnessed for deck plate and gunwale repaired areas to Marine Inspector satisfaction.
Construction/Loadline › Hull › Hull Plating
Issued 20 September 2017
Resolved
Gas free all voids and have CG inspector conduct the ISE and make all repairs.
46 CFR 31.10-21
Condition: Damaged By Earlier Event
Action required: 701 - Prior to carriage of passengers/cargo
Due 20 September 2017
Resolved 12 October 2017
Resolution: conducted all repairs called out from ISE in bow and STBD #2 wing void.
Deck/Cargo › Holds/Tanks › Bulkhead
Issued 6 August 2015
Resolved
Verify barge and hull structure is intact. Determine cause of unknown smell and possible cargo contamination in void space.
Action required: 701 - Prior to carriage of passengers/cargo
Due 6 September 2015
Resolved 24 August 2015
Resolution: Shipyard found two pinhole leaks as the cause of the cargo contamination in the void space.
Fire Fighting › Portable Dry Chemical Fire Extinguisher › Mounting Bracket
Issued 31 July 2015
Resolved
Provide onboard brackets to mount Coast Guard approved B-II extinguishers that are required by the COI per 46 CFR 34.05-10
Condition: Improper/Lack of Maintenance
Action required: 705 - Other - as specified
Due 30 September 2015
Resolved 2 September 2015
Operations/Management › Vessel Safety Management › External Certification/Verification/Control
Issued 12 December 2011
Resolved
Provide proper sign IAW 46 CFR 151.45-2(b)(3)
Action required: 705 - Other - as specified
Due 7 January 2012
Resolved 12 December 2011
Resolution: Installed proper sign on barge.
Construction/Loadline › Hull › Hull Plating
Issued 2 December 2006
Resolved
Hull sustained 8' X 6' x4" inset to sideshell port side between #1 and #2 wing tanks at the water tight bulkhead Approx. 32" above waterline at the 5' 6" draft mark.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 2 January 2007
Resolved 14 December 2006
Resolution: Repairs completed at Texas Barge and Boat, 10''x7'' plate inserted and airtested. All repair appear sataisfactory.
Construction/Loadline › Hull › Longitudinal Frame
Issued 2 December 2006
Resolved
Water tight bulk head between #1 and #2 portside. tripped 2' X 8' and fractured. 4 ea. tripping brackets fractured and 2 sidelongs twisted approx 40 degrees.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 2 January 2007
Resolved 14 December 2006
Resolution: Repairs completed at Texas Barge and boat, 3''X12'' insert plate inserted and inspected. All repairs appear satisfactory.
Construction/Loadline › Hull › Hull Plating
Issued 2 December 2006
Resolved
3' X 6" X 2" inset on deck knuckle 15' aft of the forward bulkhead on the port side.
Condition: Damaged By Earlier Event
Action required: 705 - Other - as specified
Due 2 January 2007
Resolved 14 December 2006
Resolution: Repairs completed at Texas Barge and boat, 4''x 8" insert installed